BLD-Final | 7/15/2019 | 7/16/2019 | 7/16/2019 | A | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Dwayne Robinson
|
DOC - Permit Finaled | 7/16/2019 | 7/16/2019 | 7/16/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 7/9/2019 | 7/12/2019 | 7/12/2019 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Dwayne Robinson. Electrical final has failed.
|
BLD-Final | 5/6/2019 | 5/6/2019 | 5/6/2019 | P | NR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Dwayne Robinson need final for open ele permit
|
BLD-Concrete | 2/21/2019 | 2/22/2019 | 2/22/2019 | A | PASS |
Mike Jordan
|
|
|
Steve Phone #: ###-####. Equipment pad ok.
|
Issue PAID IN FULL permit | | | 12/20/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 12/20/2018 | | DONE |
|
|
|
|
Extend Review Timeline | | | 11/27/2018 | | DONE |
|
|
|
1st Approved 180 day extension per Adele. See documents
|
Meeting | | | 11/26/2018 | | DONE |
|
|
|
Sarah sent in extension request letter
|
Expiration Notice | 11/14/2018 | 12/6/2018 | 11/14/2018 | | DONE |
Brittany Hill
|
|
|
|
Routing - Design Review | 8/30/2018 | | 8/30/2018 | | PASS |
KayCee Babb
|
|
|
per DRH18-00325
|
Routing - PLAN CHECK | 8/30/2018 | | 8/30/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/30/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 8/30/2018 | | DONE |
|
|
|
sarah.baird@crowncastle.com
MET
NEED
GC FORM
REVISED VALUE
|
Plan assigned to (M_H) | 6/28/2018 | | 8/30/2018 | | DONE |
Michael Hanson
|
|
|
06/25 #518 L2 ePlan - ATT Wireless ePlan. 1st review completed - Provide approved CAA from Boise city planning and zoning dept.. MDH
|
Routing - Design Review | 7/24/2018 | | 7/24/2018 | | FAIL |
KayCee Babb
|
|
|
DRH18-00325 has been received, but not yet approved.
|
Routing - PLANNING | 7/19/2018 | | 7/19/2018 | | PASS |
Nicolette Womack
|
|
|
|
Plan assigned to (BJM) | 6/14/2018 | 6/14/2018 | 6/28/2018 | | DEFR |
Brian McGowan
|
|
|
6/25 L2 ATT Wireless ePlan
|
Routing - PLAN CHECK | 6/8/2018 | | 6/28/2018 | | FAIL |
Michael Hanson
|
|
|
Provide approved CAA from Boise city planning and zoning dept.. MDH
|
Plan assigned to (JG) | 6/8/2018 | 6/8/2018 | 6/14/2018 | | DEFR |
Javier Guzman
|
|
|
6/20 L2 Sprint Wireless ePlan
|
Routing - PLANNING | 6/8/2018 | | 6/11/2018 | | FAIL |
Nicolette Womack
|
|
|
Cannot review until Administrative CAA18-00092 is completed.
|
Routing - Design Review | 6/8/2018 | | 6/8/2018 | | FAIL |
KayCee Babb
|
|
|
Needs to submit Design Review application for proposed project.
|
Intake Approval | | | 6/8/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 6/7/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 7 2018 10:45AM
|
First Notice | 7/16/2019 | 7/16/2019 | | | |
Mike Jordan
|
|
|
|