BLD-Final | 3/14/2019 | 3/15/2019 | 3/15/2019 | A | PASS |
Jim Sly
|
|
|
Dylan ###-#### I will make sure house is unlocked in the morning! Thanks Phone #: ###-#### Inspection requested via web by Dylan Schneider Blower Door 6.7
|
DOC - Permit Finaled | 3/15/2019 | 3/15/2019 | 3/15/2019 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 3/13/2019 | 3/14/2019 | 3/15/2019 | A | NR |
Jim Sly
|
|
|
DILLON Phone #: ###-####
|
BLD-Final | 3/11/2019 | 3/12/2019 | 3/12/2019 | A | NR |
Jim Sly
|
|
|
Dillon Phone #: ###-####
|
BLD-Energy code compliance | 11/9/2018 | 11/13/2018 | 11/13/2018 | A | PASS |
Jim Sly
|
|
|
Dylan Phone #: ###-####
|
BLD-Framing/Rough-in | 11/1/2018 | 11/2/2018 | 11/2/2018 | A | PASS |
Jim Sly
|
|
|
call 30 mins ahead- Dillan Phone #: ###-####
|
BLD-Wall Bracing | 9/26/2018 | 9/28/2018 | 9/28/2018 | A | PASS |
Jim Sly
|
|
|
dillon 724 0248 call 1st
|
BLD-Wall Bracing | 9/26/2018 | 9/25/2018 | 9/26/2018 | A | CANC |
Jim Sly
|
|
|
call 15 mins ahead-Dyaln Phone #: ###-####
|
BLD-Wall Bracing | 9/24/2018 | 9/25/2018 | 9/25/2018 | A | FAIL |
Mike Jordan
|
|
|
Shear // Dillon Phone #: ###-####. Install all missing blocking and nail. Rremove tyvek for wall bracing inspection. Correction notice posted.
|
BLD-Foundation | 7/10/2018 | 7/10/2018 | 7/10/2018 | P | PASS |
Jim Sly
|
|
|
wall pour at 230// Dillon Phone #: ###-####
|
BLD-Footing | 7/2/2018 | 7/9/2018 | 7/9/2018 | P | PASS |
Jim Sly
|
|
|
Trying to pour footing at 1pm. Thanks Andy Phone #: ###-#### Inspection requested via web by Dylan Schneider
|
Issue PAID IN FULL permit | | | 6/29/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 6/29/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 6/28/2018 | | |
|
|
|
|
Routing - PLAN CHECK | 6/25/2018 | | 6/28/2018 | | PASS |
Michael Hanson
|
|
|
|
Routing - PLANNING | 6/28/2018 | | 6/28/2018 | | PASS |
Jeff Lowe
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/28/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 6/28/2018 | | DONE |
|
|
|
Check BLD18-02267 is closed
|
Plan assigned to (M_H) | 6/18/2018 | | 6/28/2018 | | DONE |
Michael Hanson
|
|
|
06/29 sfd L1 ePlan. 1st review completed - Structural and energy corrections required. MDH
|
Routing - PLAN CHECK | 6/18/2018 | | 6/25/2018 | | FAIL |
Michael Hanson
|
|
|
Structural and energy corrections required. MDH
|
1st review completed | | | 6/25/2018 | | FAIL |
Michael Hanson
|
|
|
Structural and energy corrections required. MDH
|
Plan Reviewer's activity | | | 6/25/2018 | | DONE |
Michael Hanson
|
|
|
|
Route to Impact Fee Review | 6/18/2018 | 6/21/2018 | 6/19/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 6/18/2018 | | 6/18/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 6/18/2018 | | 6/18/2018 | | FAIL |
Jeff Lowe
|
|
|
Please provide a revised site plan showing driveway location and dimensions - requires hard surface. P&Z cannot approve permit until exisitng home is removed.
|
Routing - Addressing | 6/18/2018 | | 6/18/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/18/2018 | | 6/18/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/18/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/18/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/18/2018 | | PASS |
|
|
|
|
Intake Approval | | | 6/15/2018 | | FAIL |
|
|
|
Plans have been deleted in the drawings folder (except the cover page). Please upload all sheets in correct orientation for which they are formatted (landscape vs. portrait).
Drawing file names must include the first character of the sheet name, followed by the sheet number (example A2.0 Floor plan or Floor plan A2.0)
Double check prescriptive method for energy code on plans.
|
Application received | | | 6/12/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 12 2018 4:12PM
|