Letter of compliance/Occupancy | | | 7/29/2019 | | DONE |
|
|
|
|
BLD-Final | 12/13/2018 | 12/14/2018 | 12/14/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Erik Wylie
|
DOC - Permit Finaled | 12/14/2018 | 12/14/2018 | 12/14/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Blower Door Test Results | 12/14/2018 | 12/14/2018 | 12/14/2018 | A | DONE |
Mike Jordan
|
|
|
4.6ACH @50 pa.
|
BLD-Final | 12/13/2018 | 12/13/2018 | 12/13/2018 | P | PEND |
Mike Jordan
|
|
|
eric Phone #: ###-####. Everything ok. Needs blower door test.
|
BLD-Energy code compliance | 10/4/2018 | 10/5/2018 | 10/5/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Erik Wylie
|
BLD-Framing/Rough-in | 10/5/2018 | 10/5/2018 | 10/5/2018 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Erik Wylie. All framing issues have bee resolved. Also reviewed Engineers letter regarding the portal frames, those issues hve been correctedas well. ok to cover.
|
BLD-Framing/Rough-in | 10/3/2018 | 10/3/2018 | 10/3/2018 | P | PART |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Erik Wylie C/N posted....Lateral truss bracing and strap.
|
BLD-Wall Bracing | 9/17/2018 | 9/18/2018 | 9/18/2018 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Erik Wylie. Provide the portal frames as shown on braced wall plans or provide engineering showing that the in place work is acceptable.
|
BLD-Framing/Rough-in | 9/4/2018 | 9/5/2018 | 9/5/2018 | A | PASS |
Mike Jordan
|
|
|
Eric Phone #: ###-####. Verified install and nailing of STHD14 hold downs prior to cover.
|
BLD-Foundation | 8/6/2018 | 8/7/2018 | 8/7/2018 | P | PART |
Mike Jordan
|
|
|
wall // Dane Phone #: ###-####
|
BLD-Footing | 8/3/2018 | 8/6/2018 | 8/6/2018 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
OVERRIDE | | | 7/27/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 6/14/2018 | 6/14/2018 | 7/27/2018 | | DONE |
Brian McGowan
|
|
|
06/27 sfd L1 paper- 1st Review Complete
|
Routing - PLAN CHECK | 7/27/2018 | | 7/27/2018 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 7/27/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/27/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/27/2018 | | DONE |
|
|
|
Need -met
RP
|
Inspection Record Card- Bld | | | 7/27/2018 | | DONE |
|
|
|
|
Telephone call | | | 7/27/2018 | | DONE |
|
|
|
Spoke with Erik to inform him the permit is ready and got the name of the RP.
|
Issue PAID IN FULL permit | | | 7/27/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 7/26/2018 | | DONE |
|
|
|
Resubmittals received 2 sets of sheets A1, A1.1, S1 and took to Brian MacGowan
|
1st review completed | | | 7/25/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PUBLIC WORKS | | | 7/25/2018 | | PASS |
|
|
|
|
Routing - PLAN CHECK | 6/25/2018 | | 7/25/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 7/2/2018 | | 7/5/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 7/2/2018 | | 7/2/2018 | | PASS |
Colleen T Carroll
|
|
|
|
Plan resubmittals received | | | 7/2/2018 | | DONE |
|
|
|
received two full sets of plans and two reduced site plans; taken to BJM
|
Plan Reviewer's activity | | | 6/25/2018 | | |
Brian McGowan
|
|
|
Resubmittals required by Planning
|
Routing - MECHANICAL | 6/18/2018 | | 6/25/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 6/14/2018 | 6/17/2018 | 6/15/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 6/14/2018 | | 6/15/2018 | | PASS |
Doug Chausow
|
|
|
corrected sudivision address: 2712 S Simsbury Pl
|
Plans ACCEPTED BY PLAN TECH | | | 6/14/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/14/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/14/2018 | | DONE |
|
|
|
|
Application received | | 6/14/2018 | | | |
|
|
|
|
Routing - PLANNING | 6/15/2018 | | | | FAIL |
|
|
|
Needs to be 15' on Street side.
|