Permit Information
Permit NumberBLD18-02130
StatusFinaled
Name CONNER CONSTRUCTION LLC
Site Address 4040 N SANDPOINT WAY
Project NamePowell Residence
Customer Number 
ePlanReviewYes
Description
SPECIAL INSPECTIONS FOR COMPACTED FILL - Permit for the construction of a new 2715 sq. ft., two story (first story 2128 sq. ft., second story 587 sq. ft.) single family dwelling with 4 bedrooms, 3 bathrooms, approximately 288 sq. ft. of covered patio/porch and a 1513 sq. ft. attached garage per the approved plans, any notations, local codes & ordinances. **JAB** A-1 zoning and setbacks per planning.

A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.

Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/13/20195/14/20195/14/2019APASS
DetailsTony Young
Please give me a call when you are headed this way. Thanks! Phone #: ###-#### Inspection requested via web by Clayton Conner
DOC - Permit Finaled5/14/20195/14/20195/14/2019PPASS
DetailsTony Young
BLD-Final5/10/20195/13/20195/13/2019APASS
DetailsTony Young
Please give me a call when you are headed this way. Thanks! Phone #: ###-#### Inspection requested via web by Clayton Conner,, ok pending hillside pass
BLD-Blower Door Test Results5/13/20195/13/20195/13/2019PDONE
DetailsTony Young
Please give me a call when you are headed this way. Thanks! Phone #: ###-#### Inspection requested via web by Clayton Conner/// 3.42
PubWorks Occupancy Approval5/13/20195/13/20195/13/2019 DONE
DetailsMelissa Jannusch
A letter from the applicant’s civil engineer indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.

BLD-Energy code compliance1/18/20191/18/20191/18/2019PPASS
DetailsBrandon Shaw
Corrections SAT...
BLD-Framing/Rough-in1/9/20191/10/20191/10/2019APART
DetailsTony Young
Please call before arrival as the permit plans are locked in a trailer. Thank you Phone #: ###-#### Inspection requested via web by Clayton Conner,, ok to insulate,, see corrections,, walked with framer
BLD-Framing/Rough-in1/9/20191/9/20191/9/2019PFAIL
DetailsBrandon Shaw
Air/foam seal OK...
No approved city plans on site...
Plan Modification Accepted  11/20/2018 DONE
New manual j report
Routing - MECHANICAL11/20/2018 11/20/2018 PASS
DetailsTroy James
resubmitted manual j report
BLD-Wall Bracing11/7/201811/7/201811/7/2018APASS
DetailsBrandon Shaw
OK to cover exterior...
BLD-Wall Bracing11/6/201811/7/201811/7/2018ACANC
DetailsBrandon Shaw
OK to insulate
BLD-Foundation8/23/20188/24/20188/24/2018PPART
DetailsTony Young
Phone #: 2088708888 >> Inspection requested via mobile web by Wes
BLD-Foundation8/24/20188/24/20188/24/2018APART
DetailsTony Young
Phone #: 2088708888 >> Inspection requested via mobile web by Wes
BLD-Foundation8/23/20188/24/20188/24/2018ACANC
DetailsTony Young
Wes Phone #: ###-####
BLD-Foundation8/22/20188/23/20188/23/2018PNR
DetailsTony Young
Wes Phone #: ###-####
BLD-Footing8/22/20188/22/20188/22/2018PPASS
DetailsTony Young
As early as possible Phone #: 2088708888 >> Inspection requested via mobile web by Wes
PubWorks Subgrade Approval8/17/20188/17/20188/17/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
OVERRIDE  8/6/2018  
Routing - FIRE8/3/20188/3/20188/6/2018 PASS
DetailsTim Frost
Resubmittal New SFH ePlan
An alternate was approved by the Fire Marshal based on additonal information supplied by Suez.
Plan assigned to (JAB) Josh7/6/20187/6/20188/6/2018 PASS
DetailsJosh Bogle
07/06 sfd L2 ePlan - Plan Check PASS, waiting fir Fire review
PLANS/APPL TAKEN TO FRONT DESK  8/6/2018 DONE
DetailsJosh Bogle
Permit Ready to Issue  8/6/2018 DONE
met
Issue PAID IN FULL permit  8/6/2018 DONE
Inspection Record Card- Bld  8/6/2018 DONE
Routing - FIRE7/24/20187/24/20188/2/2018 FAIL
DetailsTim Frost
Resubmittal New SFH ePlan

Previous comment has not been addressed see annoated drawng CVR. Fire flow availability letter is required.
Routing PW Grading-Hillside7/24/2018 7/31/2018 PASS
DetailsMelissa Jannusch


A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.

Routing - PLAN CHECK7/24/2018 7/30/2018 PASS
DetailsJosh Bogle
Plan assigned to (RDP)6/19/20186/19/20187/6/2018 DEFR
DetailsRob Patrick
7/6 sfd L2 ePlan
Routing - PLAN CHECK6/19/2018 7/6/2018 FAIL
DetailsJosh Bogle
good looking plans, minor details missing
1st review completed  7/6/2018 FAIL
DetailsJosh Bogle
Route to Impact Fee Review6/19/20186/22/20186/20/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing PW Grading-Hillside6/19/2018 6/20/2018 FAIL
DetailsMelissa Jannusch
See changemark in ePlan
Routing - FIRE6/19/20186/19/20186/19/2018 FAIL
DetailsTim Frost
Plans ACCEPTED BY PLAN TECH  6/19/2018 DONE
Intake Approval  6/19/2018 PASS
Recd Pcfee & Taken To Pln CK  6/19/2018 DONE
Routing - MECHANICAL6/19/2018 6/19/2018 PASS
DetailsTroy James
Routing - PLANNING6/19/2018 6/19/2018 PASS
DetailsSue Cummings
Routing - Addressing6/19/2018 6/19/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS6/19/2018 6/19/2018 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment6/19/2018 6/19/2018 PASS
DetailsMichael Zawacki
Foothills home. Site prep inspection required.
Application received  6/15/2018 DONE
Application submitted via PDS Online on Jun 15 2018 3:04PM