Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberBLD18-02142
StatusFinaled
Name MICRON TECHNOLOGY INC
Site Address 8000 S FEDERAL WAY
Project NameMicron Bike Shelter C32958
Customer Number 
ePlanReviewYes
Description
(MICRON BIKE RACK SHELTER) C32958. Permit to construct a 31 foot by 47 foot steel canopy structure to cover bike racks on the Micron Campus near Building B27. Scope of work includes: construction of concrete slab, column footings and metal structure, installation of bike racks. Per the attached code modification, the structure has been classified as a ā€œUā€ occupancy similar to a carport to allow the structure to be located 8ā€™-4ā€ from the imaginary property line. An accessible route is required to the structure per the approved code modification. Special inspections are required per attached Form 310. This building is not sprinklered. All work to comply with applicable codes, approved code modification letter, and attached engineeering. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final9/6/20189/10/20189/10/2018APASS
DetailsJim Storey
Mike Jones Phone #: ###-####
DOC - Permit Finaled9/10/20189/10/20189/10/2018PPASS
DetailsJim Storey
FIRE-Final Inspection9/6/20189/10/20189/7/2018ADONE
DetailsJim Page
No fire final required for U occupancy, open outside bike rack storageMike Jones Phone #: ###-####
BLD-Footing8/23/20188/24/20188/24/2018APASS
DetailsJim Storey
Mke Phone #: ###-#### col ok letter from engineer ok to proceed
BLD-Footing8/8/20188/9/20188/9/2018APART
DetailsJim Storey
Mike Phone #: ###-#### pending si reopts/ rebar ok
OVERRIDE  7/30/2018  
Route to Impact Fee Review7/28/20187/31/20187/30/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Issue & PRINT to be Invoiced  7/30/2018 DONE
Print Occupancy Form  7/30/2018 DONE
Permit Ready to Issue  7/30/2018 DONE
Need
GC
Emailed Paul 7/30/18 AM, need GC form
Plan assigned to (JAR)6/25/20186/25/20187/28/2018 DONE
DetailsJulie Romig
08/03 - 502 Micron Bike Storage Canopy
1st review completed  7/28/2018 DONE
DetailsJulie Romig
PLANS/APPL TAKEN TO FRONT DESK  7/28/2018 DONE
Routing - PLAN CHECK6/25/2018 7/28/2018 PASS
DetailsJulie Romig
Routing Off Site - STRUCTURAL7/18/2018 7/25/2018 PASS
DetailsJulie Romig
2nd Review
Routing Off Site - STRUCTURAL6/25/2018 7/10/2018 FAIL
DetailsJulie Romig
Routing - FIRE6/25/20186/25/20186/28/2018 PASS
DetailsErika Akin
No fire life safety inspection required
Routing - PLANNING6/25/2018 6/26/2018 PASS
DetailsDavid Moser
Routing - Addressing6/25/2018 6/25/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS6/25/2018 6/25/2018 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment6/25/2018 6/25/2018 PASS
DetailsMichael Zawacki
Waiver request provided and approved.
Intake Approval  6/25/2018 PASS
Routing - Design Review6/25/2018 6/25/2018 PASS
DetailsKatelyn Menuge
No Design Review Requried.
Routing PW Drainage6/25/2018 6/25/2018 PASS
DetailsBrian Murphy
MASTER PLAN OK
Intake Approval  6/19/2018 FAIL
DetailsMichael Hanson
This permit has failed prescreen due to the following:
1. Checklist indicates site specific fire flow letter provided although it is not located in the documents. Please upload...
Application received  6/18/2018 DONE
Application submitted via PDS Online on Jun 18 2018 11:03AM