BLD-Final | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 3/21/2019 | 3/21/2019 | 3/21/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.85
|
BLD-Final | 3/14/2019 | 3/19/2019 | 3/19/2019 | A | NR |
Brandon Shaw
|
|
|
Need blower door test results posted...
|
BLD-Framing/Rough-in | 1/14/2019 | 1/14/2019 | 1/14/2019 | P | PASS |
Brandon Shaw
|
|
|
Corrections SAT... OK to insulate...
|
BLD-Framing/Rough-in | 1/4/2019 | 1/4/2019 | 1/4/2019 | P | FAIL |
Brandon Shaw
|
|
|
Shear corrections not complete... Approved plans show 10 HDU4 hold downs, onle 8 installed... No floor to floor MSTA24 straps at second floor... Strap needed at garage bearing wall... Per S1.1, note #10 A35 clips need to be installed, two locations... See Plans and red paint...
|
BLD-Other | 1/4/2019 | 1/4/2019 | 1/4/2019 | P | PASS |
Brandon Shaw
|
|
|
Soffit
|
BLD-Framing/Rough-in | 12/26/2018 | 12/27/2018 | 12/27/2018 | P | NR |
Brandon Shaw
|
|
|
Late as possible. I have air seal coming tomorrow. Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Wall Bracing | 12/7/2018 | 12/7/2018 | 12/7/2018 | P | FAIL |
Brandon Shaw
|
|
|
Need a complete set of approved plans... Achor botls to be no more than 12" from end of sill plates... Hold downs and anchor bolts missing hardware... First floor only... See Red Paint
|
BLD-Foundation | 10/18/2018 | 10/18/2018 | 10/18/2018 | A | PASS |
Jim Storey
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 10/11/2018 | 10/12/2018 | 10/11/2018 | A | CANC |
Brandon Shaw
|
|
|
10 am please- Phone #: 2088031073 >> Inspection requested via mobile web by Alex Arambul Inspection cancelled via mobile web on Thursday, October 11, 2018.
|
BLD-Conference | 10/11/2018 | 10/12/2018 | 10/11/2018 | A | CANC |
Brandon Shaw
|
|
|
As late as possible Phone #: 2088031073 >> Inspection requested via mobile web by Alex Arambul Inspection cancelled via mobile web on Thursday, October 11, 2018.
|
BLD-Footing | 10/10/2018 | 10/11/2018 | 10/11/2018 | P | CANC |
Brandon Shaw
|
|
|
As late as possible Phone #: 2088031073 >> Inspection requested via mobile web by Alex Arambul Inspection cancelled via mobile web on Thursday, October 11, 2018.
|
BLD-Conference | 10/10/2018 | 10/11/2018 | 10/10/2018 | P | CANC |
Brandon Shaw
|
|
|
As late as possible Phone #: 2088031073 >> Inspection requested via mobile web by Alex Arambul Inspection cancelled via mobile web on Wednesday, October 10, 2018.
|
Issue PAID IN FULL permit | | | 10/1/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/1/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 6/27/2018 | | |
|
|
|
|
1st review completed | | | 6/27/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 6/27/2018 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 6/18/2018 | | 6/27/2018 | | DONE |
Michael Hanson
|
|
|
06/29 sfd L1 ePlan. 1st review completed - Pending other department reviews. MDH
|
Routing - PLAN CHECK | 6/18/2018 | | 6/27/2018 | | PASS |
Michael Hanson
|
|
|
|
Routing - MECHANICAL | 6/18/2018 | | 6/27/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 6/18/2018 | | 6/26/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 6/18/2018 | | 6/26/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/18/2018 | | 6/26/2018 | | PASS |
Morgan Webb
|
|
|
|
Route to Impact Fee Review | 6/18/2018 | 6/21/2018 | 6/19/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Application received | | | 6/18/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 18 2018 2:58PM
|
Plans ACCEPTED BY PLAN TECH | | | 6/18/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/18/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/18/2018 | | DONE |
|
|
|
|