PubWorks Occupancy Approval | 5/22/2019 | 5/22/2019 | 5/22/2019 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. A letter from the applicant’s engineer indicating that the wall is acceptable has been received by Public Works.
|
BLD-Aging Inspection | 5/13/2019 | 5/13/2019 | 5/21/2019 | | PEND |
Tony Young
|
|
|
|
PubWorks Occupancy Approval | 7/18/2018 | 10/19/2018 | 7/18/2018 | | FAIL |
Melissa Jannusch
|
|
|
The wall has been compromised during construction activities for the footings. A new approval letter from structural engineer and compaction testing from MTI will be required prior to public works occupancy approval of the wall.
|
OVERRIDE | | | 6/27/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 6/26/2018 | 6/26/2018 | 6/27/2018 | | PASS |
Josh Bogle
|
|
|
1st done - boulder retaining wall
|
Routing PW Grading-Hillside | 6/26/2018 | | 6/27/2018 | | PASS |
Melissa Jannusch
|
|
|
Permit approved for boulder retaining wall and related grading.
|
Routing - PLAN CHECK | 6/26/2018 | | 6/27/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 6/27/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 6/27/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 6/27/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 6/27/2018 | | DONE |
|
|
|
|
Plan assigned to (JAB) Josh | 6/22/2018 | 6/22/2018 | 6/26/2018 | | PASS |
Josh Bogle
|
|
|
due 6/28 - retaining wall
|
Routing - PLAN CHECK | 6/22/2018 | | 6/26/2018 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 6/26/2018 | | DONE |
Josh Bogle
|
|
|
|
Routing - Erosion and Sediment | 6/22/2018 | | 6/25/2018 | | PASS |
Michael Zawacki
|
|
|
Waiver approved. Waiver only covers retaining wall and work related to retaining wall. No home site prep is covered by waiver request.
|
Routing PW Grading-Hillside | 6/22/2018 | | 6/25/2018 | | FAIL |
Melissa Jannusch
|
|
|
Applicant needs to upload grading plan from June 4, 2018
|
Plan Reviewer's activity | | | 6/25/2018 | | DONE |
Josh Bogle
|
|
|
e-mail to team verifying which lot this app relates to
|
Routing - PLANNING | 6/22/2018 | | 6/22/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 6/22/2018 | | 6/22/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/22/2018 | | 6/22/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/22/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/22/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/22/2018 | | DONE |
|
|
|
no fees paid at intake
|
Intake Approval | | | 6/20/2018 | | FAIL |
|
|
|
need erosion plan or waiver-talked to Jessica 6-19-18 and she was going to email me the waiver but haven't heard back so failed the prescreen so she can upload whats needed and sign off
|
Application received | | | 6/19/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 19 2018 9:26AM
|