Letter of compliance/Occupancy | | | 7/16/2019 | | DONE |
|
|
|
|
BLD-Final | 7/11/2019 | 7/11/2019 | 7/11/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: 2088598694 >> Inspection requested via mobile web by Brad
|
DOC - Permit Finaled | 7/11/2019 | 7/11/2019 | 7/11/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Conference | 7/8/2019 | 7/9/2019 | 7/9/2019 | A | DONE |
Brandon Shaw
|
|
|
As early as possible Phone #: 2088598694 >> Inspection requested via mobile web by Brad
|
BLD-Conference | 6/26/2019 | 6/26/2019 | 6/26/2019 | P | DONE |
Jim Storey
|
|
|
Brad Phone #: ###-#### max 38 top of handrail
|
CHANGE STATUS TO (ISS) | | | 6/26/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 6/5/2019 | | |
|
|
|
|
Permit Ready to Issue | | | 6/5/2019 | | DONE |
|
|
|
*Please do not issue permit* Plan mod approved
|
Plan assigned to (M_H) | 5/23/2019 | | 6/5/2019 | | DONE |
Michael Hanson
|
|
|
1st review completed - 05/29 plan mod ePlan - Pending planning review
|
Routing - PLANNING | 5/24/2019 | | 6/4/2019 | | PASS |
Celine Acord
|
|
|
per CAA18-00224
|
Routing - PLAN CHECK | 5/24/2019 | | 6/4/2019 | | PASS |
Michael Hanson
|
|
|
|
Plan Modification Accepted | | | 5/23/2019 | | DONE |
|
|
|
changes to sidewalks and driveway
|
BLD-Framing/Rough-in | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | PASS |
Jim Storey
|
|
|
Brad Phone #: ###-#### c/n made ok
|
BLD-Energy code compliance | 4/16/2019 | 4/16/2019 | 4/16/2019 | P | PASS |
Jim Storey
|
|
|
Brad Phone #: ###-####
|
BLD-Framing/Rough-in | 4/9/2019 | 4/10/2019 | 4/10/2019 | A | PART |
Jim Storey
|
|
|
Brad Phone #: ###-#### c/n gyp under stair common wall/hvac gpy garage side/ naioll hangers to trusses at gurder. ok to insulate.
|
BLD-Wall Bracing | 3/7/2019 | 3/8/2019 | 3/8/2019 | A | PASS |
Jim Storey
|
|
|
call for access- Brad Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 3/7/2019 | | DONE |
|
|
|
accidently put in review status.
|
BLD-Wall Bracing | 1/3/2019 | 1/4/2019 | 1/4/2019 | P | CANC |
Jim Storey
|
|
|
Jeremy Phone #: ###-####
|
BLD-Foundation | 1/4/2019 | 1/4/2019 | 1/4/2019 | P | PASS |
Jim Storey
|
|
|
Jeremy Phone #: ###-####
|
BLD-Footing | 12/28/2018 | 12/31/2018 | 12/31/2018 | A | PASS |
Jim Storey
|
|
|
concrete 11 // Jeremy Phone #: ###-####
|
Inspection Record Card- Bld | | | 11/13/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/13/2018 | | DONE |
|
|
|
|
Meeting | | | 11/6/2018 | | DONE |
|
|
|
Emailed BBC Idaho LLC to inform them we still need a 302 and RP before we can issue the permits.
|
OVERRIDE | | | 10/18/2018 | | |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2018 | | DONE |
Michael Hanson
|
|
|
|
Meeting | | | 10/18/2018 | | DONE |
|
|
|
Emailed ACHD (Austin) again to ask about the impact fees for this duplex.
|
Routing - PLANNING | 10/18/2018 | | 10/18/2018 | | PASS |
Celine Acord
|
|
|
|
Permit Ready to Issue | | | 10/18/2018 | | DONE |
|
|
|
Need- all requirements met
RP
GC form
met-(ACHD IS WAITING FOR FINAL PLAN APPROVAL TO BE SUBMITTED TO THEM)
See attached email
|
Plan assigned to (M_H) | 6/28/2018 | | 10/18/2018 | | DONE |
Michael Hanson
|
|
|
07/17 dplx L2 ePlan. 1st review completed - Energy, Structural, missing sheets, and planning failed. MDH
|
Routing - PLAN CHECK | 6/28/2018 | | 10/18/2018 | | PASS |
Michael Hanson
|
|
|
|
Plan Reviewer's activity | | | 9/4/2018 | | DONE |
Michael Hanson
|
|
|
Contacted Jeff Hatch via phone and he indicated that the civil engineer is engaged and that is the reason for the delay but the permit is to be kept open. They hope to move forward in the coming weeks. MDH
|
1st review completed | | | 7/17/2018 | | FAIL |
Michael Hanson
|
|
|
Energy, structural, sheets missing. MDH
|
Routing - PLAN CHECK | 7/17/2018 | | 7/17/2018 | | FAIL |
Michael Hanson
|
|
|
|
Routing - MECHANICAL | 6/28/2018 | | 7/3/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 6/28/2018 | 7/1/2018 | 6/29/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 6/28/2018 | | 6/29/2018 | | FAIL |
Celine Acord
|
|
|
-need landscape plan with irrigation lines - need to show sidewalk construction on High Street - need approval from Idaho Power - all per conditions of CAA17-00224
|
Routing - Addressing | 6/28/2018 | | 6/28/2018 | | PASS |
Doug Chausow
|
|
|
627 W Boise Ave
635 W Boise Ave
|
Routing - PUBLIC WORKS | 6/28/2018 | | 6/28/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 6/28/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/28/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/28/2018 | | DONE |
|
|
|
|
Application received | | | 6/20/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 20 2018 10:30AM
|