Information based on query as of Sunday, June 2, 2024.
Permit Information
Permit NumberBLD18-02193
StatusFinaled
Name JPC BUILDERS LLC
Site Address 4131 N EYRIE WAY
Project Name 
Customer Number 
ePlanReviewNo
Description
HILLSIDE, WUI FOOTHILLS, ZONE "A" REQUIREMENTS, CLASS "A" ROOF REQUIRED. Project will require a CAT II Hillside application prior to acceptance of the building permit application. Application #114 will need to be filled out and turned in to the Planning & Zoning counter at city hall with the application fee. Once the application has been approved by P&Z please upload the approval letter and then this building permit case can be routed for approval. Melissa Jannusch 208-608-7168. Permit for the construction of a new 3664 sq. ft., one story single family dwelling, (2909 sq. ft. above grade, 755 sq. ft. finished daylight basement) with 4 bedrooms, 3.5 bathrooms, approximately 498 sq. ft. of covered patio/porch and a 938 sq. ft. attached garage per the approved plans and any notations. A-1 zoning and setbacks per planning.
***BJM***
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/7/20201/9/20201/10/2020APASS
DetailsTony Young
PJ Smith// status of public works pass
DOC - Permit Finaled1/10/20201/10/20201/10/2020PPASS
DetailsTony Young
PubWorks Occupancy Approval1/9/20201/9/20201/9/2020 DONE
DetailsMelissa Jannusch
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Final1/2/20201/7/20201/7/2020APEND
DetailsTony Young
PJ Smith// status of public works pass
BLD-Final12/27/20191/2/20201/2/2020PPEND
DetailsTony Young
PJ Smith
BLD-Final12/24/201912/26/201912/27/2019PPEND
DetailsTony Young
PJ Smith// ok pending hillside approval
BLD-Final12/19/201912/24/201912/24/2019APEND
DetailsTony Young
PJ Smith// ok pending hillside approval
BLD-Final12/19/201912/19/201912/19/2019PPEND
DetailsTony Young
PJ Smith
BLD-Conference11/20/201911/20/201911/20/2019PPASS
DetailsTony Young
Call PJ Smith - Would like to meet inspector at job site. Thanks! Inspection requested via web by PJ Smith// walk through,, just needs hillside pass
BLD-Conference11/19/201911/20/201911/20/2019ACANC
DetailsTony Young
Please call PJ Smith so he can meet inspector at job. Have a great week! Phone #: ###-#### >> Inspection requested via web by PJ Smith Inspection cancelled from web by: PJ Smith
BLD-Aging Inspection10/3/201910/3/201910/7/2019 PASS
DetailsTony Young
BLD-Aging Inspection10/2/201910/2/201910/7/2019 PASS
DetailsTony Young
BLD-Energy code compliance5/21/20195/21/20195/21/2019PPART
DetailsTony Young
Call PJ Smith when in route

Have a gtreat week!

PJ Phone #: ###-#### Inspection requested via web by PJ Smith,, will get backing on before final,, ok to cover
BLD-Energy code compliance5/16/20195/20/20195/21/2019PPART
DetailsTony Young
Call PJ Smith when in route

Have a gtreat week!

PJ Phone #: ###-#### Inspection requested via web by PJ Smith,, ok to cover,, just need to verify 6 sided on the basement/ crawl walls
BLD-Framing/Rough-in5/16/20195/17/20195/17/2019PCANC
DetailsBrandon Shaw
Call PJ Smith when in route

Have a gtreat week!

PJ Phone #: ###-#### Inspection requested via web by PJ Smith
BLD-Energy code compliance5/16/20195/16/20195/16/2019PPART
DetailsTony Young
Call PJ Smith when in route

Have a gtreat week!

PJ Phone #: ###-#### Inspection requested via web by PJ Smith// needs 6 sided cover on basement/ crawl space walls,, rim area,, all else ok for cover
BLD-Framing/Rough-in5/16/20195/16/20195/16/2019PPASS
DetailsTony Young
Call PJ Smith when in route

Have a gtreat week!

PJ Phone #: ###-#### Inspection requested via web by PJ Smith
BLD-Framing/Rough-in5/13/20195/14/20195/14/2019APART
DetailsTony Young
Tony Text me when you''re headed up to inspect. Have a great week!

PJ Smith 208 559 0588 Inspection requested via web by PJ Smith,, brace and support the trusses per engineering,, add header for point load,, see notes,, ok to insulate
BLD-Conference5/8/20195/8/20195/8/2019APART
DetailsTony Young
Tony Young: Call me and I''ll meet you at job site Lot 13 Block 4, 4131 N Eyrie way Boise. Please try to make it mid-late morning if you can.

PJ Smith 208 559 0588 Thanks! Phone #: ###-#### Inspection requested via web by PJ Smith,,, frame walk through,, needs truss engineering
BLD-Wall Bracing4/16/20194/17/20194/17/2019PPASS
DetailsBrandon Shaw
Work in progress...
Interior hold downs to be located (2), as per plans...
BLD-Foundation1/9/20191/10/20191/10/2019APASS
DetailsBrandon Shaw
Work in progress...
BLD-Footing1/3/20191/3/20191/3/2019PPART
DetailsTony Young
Eric Phone #: ###-####,, remainder of house footings ok,, work in progress
PubWorks Subgrade Approval1/3/20191/3/20191/3/2019 DONE
DetailsMelissa Jannusch
MAIN LEVEL AND LOWER FOUNDATIONS. NOT COLUMN FOOTINGS FOR PORCH. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####. *UPDATE LETTER FOR COLUMN FOOTING PROVIDED 1-9-2020

BLD-Foundation12/20/201812/21/201812/21/2018APART
DetailsTony Young
Eric Phone #: ###-####,, basement wall ok
BLD-Footing12/13/201812/14/201812/14/2018APART
DetailsTony Young
Eric-pour 2:00 Phone #: ###-####,, basement portion of footings ok
BLD-Footing12/12/201812/13/201812/13/2018ACANC
DetailsTony Young
Tyler Phone #: ###-####-cancerlled - outside reports not in yet
PubWorks Subgrade Approval12/13/201812/13/201812/13/2018 DONE
DetailsMelissa Jannusch
Lower level footing subgrade only not columns for patio. A letter from the applicant’s geotechnical engineer indicating that the lower level footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
Issue PAID IN FULL permit  11/27/2018 DONE
(F) Reprint permit  11/27/2018 DONE
Expiration Notice11/23/201812/14/201811/23/2018 DONE
DetailsBrittany Hill
OVERRIDE  11/16/2018  
Routing - FIRE11/16/201811/16/201811/16/2018 PASS
DetailsTim Frost
Plan assigned to (BJM)11/13/201811/13/201811/16/2018 DONE
DetailsBrian McGowan
changed status from RDY to Fev-no fire plan review was passed.
FIRE signed off.
Routing - PLAN CHECK11/13/2018 11/16/2018 PASS
DetailsBrian McGowan
changed status to REV- still needs fire sign off
Permit Ready to Issue  11/16/2018 DONE
all met
Telephone call  11/16/2018 DONE
Called PJ to advise permit is ready and gave fees due
Routing - FRONT DESK6/26/2018 11/16/2018 PASS
DetailsBrittany Hill
Route to front desk for hold until CFH application is approved. --MMJ
CHANGE STATUS TO (REV)  11/13/2018 DONE
permit was made ready but still needs fire plan review-assigned to Brian McGowan
OVERRIDE  11/9/2018  
Plan assigned to (BJM) 6/20/201811/9/2018 DONE
DetailsBrian McGowan
Corrections Required - Need Cat II hillside application, all review halted until process is completed. Start back up at PW Hillside
Inspection Record Card- Bld  11/9/2018 DONE
Meeting  11/9/2018 DONE
Took plans back to Brian. No pass on fire review
Routing - PLAN CHECK11/9/2018 11/9/2018 PASS
DetailsBrian McGowan
Case Summary (BLD)  11/9/2018 DONE
DetailsBrian McGowan
PLANS/APPL TAKEN TO FRONT DESK  11/9/2018 DONE
DetailsBrian McGowan
Permit Ready to Issue  11/9/2018 DONE
Plan resubmittals received  10/25/2018 DONE
received two copies of foundation calcs, lateral calcs, and plan sheets 1 thru 13; taken to Brian McGowan
Routing - FIRE7/27/20187/20/20188/7/2018 FAIL
DetailsTim Frost
Resubmittal New SFH
Fire flow information not provided. 5101 ft² fire area. Required 2000 Gpm
Sent email to applicant
Routing - Erosion and Sediment7/26/2018 7/27/2018 PASS
DetailsMichael Zawacki
Hillside home, site prep inspection required.
Routing - MECHANICAL7/25/2018 7/26/2018 PASS
DetailsChad Schwendiman
Routing - PLANNING7/24/2018 7/25/2018 PASS
DetailsTodd Tucker
Routing PW Grading-Hillside7/20/2018 7/24/2018 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
Routing - PUBLIC WORKS7/20/2018 7/24/2018 PASS
DetailsMorgan Webb
Routing - Addressing7/20/2018 7/20/2018 PASS
DetailsDoug Chausow
Routing PW Grading-Hillside6/21/2018 6/26/2018 FAIL
DetailsMelissa Jannusch
Project will require a CAT II Hillside application prior to acceptance of the building permit application. Application #114 will need to be filled out and turned in to the Planning & Zoning counter at city hall with the application fee. Once the application has been approved by P&Z please upload the approval letter and then this building permit case can be routed for approval. Melissa Jannusch ###-####.
Routing - PLAN CHECK  6/26/2018 FAIL
DetailsBrian McGowan
Failed due to CFH requirements
1st review completed  6/26/2018 FAIL
DetailsBrian McGowan
Failed due to CFH requirements
Route to Impact Fee Review6/21/20186/24/20186/25/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Routing PW Sewer Rating6/21/2018 6/21/2018 PASS
DetailsMorgan Webb
Routing - Addressing6/20/2018 6/21/2018 PASS
DetailsDoug Chausow
Routing - FIRE 6/20/20186/20/2018 CANC
7/09 New SFH paper

Need Cat II hillside application, all review halted until process is completed. Start back up at PW Hillside
Plans ACCEPTED BY PLAN TECH  6/20/2018 DONE
Intake Approval  6/20/2018 FAIL
Need Cat II hillside application, all review halted until process is completed. Start back up at PW Hillside
Recd Pcfee & Taken To Pln CK  6/20/2018 DONE
Intake Approval  6/20/2018 PASS
Application received 6/20/2018