BLD-Final | 1/7/2020 | 1/9/2020 | 1/10/2020 | A | PASS |
Tony Young
|
|
|
PJ Smith// status of public works pass
|
DOC - Permit Finaled | 1/10/2020 | 1/10/2020 | 1/10/2020 | P | PASS |
Tony Young
|
|
|
|
PubWorks Occupancy Approval | 1/9/2020 | 1/9/2020 | 1/9/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 1/2/2020 | 1/7/2020 | 1/7/2020 | A | PEND |
Tony Young
|
|
|
PJ Smith// status of public works pass
|
BLD-Final | 12/27/2019 | 1/2/2020 | 1/2/2020 | P | PEND |
Tony Young
|
|
|
PJ Smith
|
BLD-Final | 12/24/2019 | 12/26/2019 | 12/27/2019 | P | PEND |
Tony Young
|
|
|
PJ Smith// ok pending hillside approval
|
BLD-Final | 12/19/2019 | 12/24/2019 | 12/24/2019 | A | PEND |
Tony Young
|
|
|
PJ Smith// ok pending hillside approval
|
BLD-Final | 12/19/2019 | 12/19/2019 | 12/19/2019 | P | PEND |
Tony Young
|
|
|
PJ Smith
|
BLD-Conference | 11/20/2019 | 11/20/2019 | 11/20/2019 | P | PASS |
Tony Young
|
|
|
Call PJ Smith - Would like to meet inspector at job site. Thanks! Inspection requested via web by PJ Smith// walk through,, just needs hillside pass
|
BLD-Conference | 11/19/2019 | 11/20/2019 | 11/20/2019 | A | CANC |
Tony Young
|
|
|
Please call PJ Smith so he can meet inspector at job. Have a great week! Phone #: ###-#### >> Inspection requested via web by PJ Smith Inspection cancelled from web by: PJ Smith
|
BLD-Aging Inspection | 10/3/2019 | 10/3/2019 | 10/7/2019 | | PASS |
Tony Young
|
|
|
|
BLD-Aging Inspection | 10/2/2019 | 10/2/2019 | 10/7/2019 | | PASS |
Tony Young
|
|
|
|
BLD-Energy code compliance | 5/21/2019 | 5/21/2019 | 5/21/2019 | P | PART |
Tony Young
|
|
|
Call PJ Smith when in route
Have a gtreat week!
PJ Phone #: ###-#### Inspection requested via web by PJ Smith,, will get backing on before final,, ok to cover
|
BLD-Energy code compliance | 5/16/2019 | 5/20/2019 | 5/21/2019 | P | PART |
Tony Young
|
|
|
Call PJ Smith when in route
Have a gtreat week!
PJ Phone #: ###-#### Inspection requested via web by PJ Smith,, ok to cover,, just need to verify 6 sided on the basement/ crawl walls
|
BLD-Framing/Rough-in | 5/16/2019 | 5/17/2019 | 5/17/2019 | P | CANC |
Brandon Shaw
|
|
|
Call PJ Smith when in route
Have a gtreat week!
PJ Phone #: ###-#### Inspection requested via web by PJ Smith
|
BLD-Energy code compliance | 5/16/2019 | 5/16/2019 | 5/16/2019 | P | PART |
Tony Young
|
|
|
Call PJ Smith when in route
Have a gtreat week!
PJ Phone #: ###-#### Inspection requested via web by PJ Smith// needs 6 sided cover on basement/ crawl space walls,, rim area,, all else ok for cover
|
BLD-Framing/Rough-in | 5/16/2019 | 5/16/2019 | 5/16/2019 | P | PASS |
Tony Young
|
|
|
Call PJ Smith when in route
Have a gtreat week!
PJ Phone #: ###-#### Inspection requested via web by PJ Smith
|
BLD-Framing/Rough-in | 5/13/2019 | 5/14/2019 | 5/14/2019 | A | PART |
Tony Young
|
|
|
Tony Text me when you''re headed up to inspect. Have a great week!
PJ Smith 208 559 0588 Inspection requested via web by PJ Smith,, brace and support the trusses per engineering,, add header for point load,, see notes,, ok to insulate
|
BLD-Conference | 5/8/2019 | 5/8/2019 | 5/8/2019 | A | PART |
Tony Young
|
|
|
Tony Young: Call me and I''ll meet you at job site Lot 13 Block 4, 4131 N Eyrie way Boise. Please try to make it mid-late morning if you can.
PJ Smith 208 559 0588 Thanks! Phone #: ###-#### Inspection requested via web by PJ Smith,,, frame walk through,, needs truss engineering
|
BLD-Wall Bracing | 4/16/2019 | 4/17/2019 | 4/17/2019 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... Interior hold downs to be located (2), as per plans...
|
BLD-Foundation | 1/9/2019 | 1/10/2019 | 1/10/2019 | A | PASS |
Brandon Shaw
|
|
|
Work in progress...
|
BLD-Footing | 1/3/2019 | 1/3/2019 | 1/3/2019 | P | PART |
Tony Young
|
|
|
Eric Phone #: ###-####,, remainder of house footings ok,, work in progress
|
PubWorks Subgrade Approval | 1/3/2019 | 1/3/2019 | 1/3/2019 | | DONE |
Melissa Jannusch
|
|
|
MAIN LEVEL AND LOWER FOUNDATIONS. NOT COLUMN FOOTINGS FOR PORCH. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####. *UPDATE LETTER FOR COLUMN FOOTING PROVIDED 1-9-2020
|
BLD-Foundation | 12/20/2018 | 12/21/2018 | 12/21/2018 | A | PART |
Tony Young
|
|
|
Eric Phone #: ###-####,, basement wall ok
|
BLD-Footing | 12/13/2018 | 12/14/2018 | 12/14/2018 | A | PART |
Tony Young
|
|
|
Eric-pour 2:00 Phone #: ###-####,, basement portion of footings ok
|
BLD-Footing | 12/12/2018 | 12/13/2018 | 12/13/2018 | A | CANC |
Tony Young
|
|
|
Tyler Phone #: ###-####-cancerlled - outside reports not in yet
|
PubWorks Subgrade Approval | 12/13/2018 | 12/13/2018 | 12/13/2018 | | DONE |
Melissa Jannusch
|
|
|
Lower level footing subgrade only not columns for patio. A letter from the applicant’s geotechnical engineer indicating that the lower level footing subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Issue PAID IN FULL permit | | | 11/27/2018 | | DONE |
|
|
|
|
(F) Reprint permit | | | 11/27/2018 | | DONE |
|
|
|
|
Expiration Notice | 11/23/2018 | 12/14/2018 | 11/23/2018 | | DONE |
Brittany Hill
|
|
|
|
OVERRIDE | | | 11/16/2018 | | |
|
|
|
|
Routing - FIRE | 11/16/2018 | 11/16/2018 | 11/16/2018 | | PASS |
Tim Frost
|
|
|
|
Plan assigned to (BJM) | 11/13/2018 | 11/13/2018 | 11/16/2018 | | DONE |
Brian McGowan
|
|
|
changed status from RDY to Fev-no fire plan review was passed.
FIRE signed off.
|
Routing - PLAN CHECK | 11/13/2018 | | 11/16/2018 | | PASS |
Brian McGowan
|
|
|
changed status to REV- still needs fire sign off
|
Permit Ready to Issue | | | 11/16/2018 | | DONE |
|
|
|
all met
|
Telephone call | | | 11/16/2018 | | DONE |
|
|
|
Called PJ to advise permit is ready and gave fees due
|
Routing - FRONT DESK | 6/26/2018 | | 11/16/2018 | | PASS |
Brittany Hill
|
|
|
Route to front desk for hold until CFH application is approved. --MMJ
|
CHANGE STATUS TO (REV) | | | 11/13/2018 | | DONE |
|
|
|
permit was made ready but still needs fire plan review-assigned to Brian McGowan
|
OVERRIDE | | | 11/9/2018 | | |
|
|
|
|
Plan assigned to (BJM) | | 6/20/2018 | 11/9/2018 | | DONE |
Brian McGowan
|
|
|
Corrections Required - Need Cat II hillside application, all review halted until process is completed. Start back up at PW Hillside
|
Inspection Record Card- Bld | | | 11/9/2018 | | DONE |
|
|
|
|
Meeting | | | 11/9/2018 | | DONE |
|
|
|
Took plans back to Brian. No pass on fire review
|
Routing - PLAN CHECK | 11/9/2018 | | 11/9/2018 | | PASS |
Brian McGowan
|
|
|
|
Case Summary (BLD) | | | 11/9/2018 | | DONE |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 11/9/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/25/2018 | | DONE |
|
|
|
received two copies of foundation calcs, lateral calcs, and plan sheets 1 thru 13; taken to Brian McGowan
|
Routing - FIRE | 7/27/2018 | 7/20/2018 | 8/7/2018 | | FAIL |
Tim Frost
|
|
|
Resubmittal New SFH
Fire flow information not provided. 5101 ft² fire area. Required 2000 Gpm
Sent email to applicant
|
Routing - Erosion and Sediment | 7/26/2018 | | 7/27/2018 | | PASS |
Michael Zawacki
|
|
|
Hillside home, site prep inspection required.
|
Routing - MECHANICAL | 7/25/2018 | | 7/26/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 7/24/2018 | | 7/25/2018 | | PASS |
Todd Tucker
|
|
|
|
Routing PW Grading-Hillside | 7/20/2018 | | 7/24/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-####
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
|
Routing - PUBLIC WORKS | 7/20/2018 | | 7/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 7/20/2018 | | 7/20/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing PW Grading-Hillside | 6/21/2018 | | 6/26/2018 | | FAIL |
Melissa Jannusch
|
|
|
Project will require a CAT II Hillside application prior to acceptance of the building permit application. Application #114 will need to be filled out and turned in to the Planning & Zoning counter at city hall with the application fee. Once the application has been approved by P&Z please upload the approval letter and then this building permit case can be routed for approval. Melissa Jannusch ###-####.
|
Routing - PLAN CHECK | | | 6/26/2018 | | FAIL |
Brian McGowan
|
|
|
Failed due to CFH requirements
|
1st review completed | | | 6/26/2018 | | FAIL |
Brian McGowan
|
|
|
Failed due to CFH requirements
|
Route to Impact Fee Review | 6/21/2018 | 6/24/2018 | 6/25/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing PW Sewer Rating | 6/21/2018 | | 6/21/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 6/20/2018 | | 6/21/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - FIRE | | 6/20/2018 | 6/20/2018 | | CANC |
|
|
|
7/09 New SFH paper
Need Cat II hillside application, all review halted until process is completed. Start back up at PW Hillside
|
Plans ACCEPTED BY PLAN TECH | | | 6/20/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/20/2018 | | FAIL |
|
|
|
Need Cat II hillside application, all review halted until process is completed. Start back up at PW Hillside
|
Recd Pcfee & Taken To Pln CK | | | 6/20/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/20/2018 | | PASS |
|
|
|
|
Application received | | 6/20/2018 | | | |
|
|
|
|