BLD-Final | 1/11/2019 | 1/11/2019 | 1/11/2019 | P | PASS |
Brandon Shaw
|
|
|
Garage code 0206 Phone #: ###-#### Inspection requested via web by Elena Stephens
|
DOC - Permit Finaled | 1/11/2019 | 1/11/2019 | 1/11/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 1/11/2019 | 1/11/2019 | 1/11/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.75
|
BLD-Energy code compliance | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PASS |
Jim Sly
|
|
|
Inspection requested via web by Marc Foote
|
BLD-Framing/Rough-in | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PASS |
Jim Sly
|
|
|
Inspection requested via web by Marc Foote
|
BLD-Framing/Rough-in | 10/18/2018 | 10/19/2018 | 10/19/2018 | A | NR |
Jim Sly
|
|
|
Inspection requested via web by Marc Foote Verified Foam Seal.......Contr. left no phone #...... Wanted to call..........
|
BLD-Framing/Rough-in | 10/17/2018 | 10/17/2018 | 10/17/2018 | P | PART |
Jim Storey
|
|
|
Inspection requested via web by Marc Foote c/n d1 not bearing on mlb/ tpo chord drilled by hvac at flue/ need air seal
|
BLD-Wall Bracing | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Jim Storey
|
|
|
Inspection requested via web by Marc Foote aprox.300 301
|
BLD-Wall Bracing | 9/28/2018 | 10/1/2018 | 10/1/2018 | A | DEFR |
Jim Storey
|
|
|
Inspection requested via web by Marc Foote
|
BLD-Footing | 8/22/2018 | 8/22/2018 | 8/22/2018 | P | PASS |
Jim Storey
|
|
|
Jared Phone #: ###-####
|
(F) Reprint permit | | | 8/16/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/16/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 8/15/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 7/6/2018 | 7/6/2018 | 8/15/2018 | | DONE |
Brian McGowan
|
|
|
2nd REVIEW COMPLETE 7-6 sfd L1 ePlan
|
Inspector's copy Bld permit | | | 8/15/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/15/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/15/2018 | | 8/15/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/15/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 8/15/2018 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 8/7/2018 | | 8/7/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLANNING | 7/17/2018 | | 7/17/2018 | | PASS |
Sue Cummings
|
|
|
Letter of satisfaction received. OK now
|
1st review completed | | | 7/6/2018 | | DONE |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/25/2018 | | 7/6/2018 | | FAIL |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 6/25/2018 | 6/28/2018 | 6/26/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 6/25/2018 | | 6/26/2018 | | PASS |
Troy James
|
|
|
|
Plan assigned to (RDP) | 6/25/2018 | 6/25/2018 | 6/25/2018 | | DEFR |
Rob Patrick
|
|
|
7/6 sfd L1 ePlan
|
Plans ACCEPTED BY PLAN TECH | | | 6/25/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/25/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/25/2018 | | DONE |
|
|
|
|
Routing - Addressing | 6/25/2018 | | 6/25/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/25/2018 | | 6/25/2018 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 6/22/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 22 2018 10:49AM
|
Routing - PLANNING | 6/25/2018 | | | | FAIL |
|
|
|
The letter of satisfaction for the subdiviseion has NOT been signed.
|
Routing - PLANNING | 7/9/2018 | | | | FAIL |
|
|
|
Still no letter of satisfaction for sub
|