Permit Information
Permit NumberBLD18-02292
StatusFinaled
Name LUSARDI CONSTRUCTION COMPANY
Site Address 917 S LUSK ST
Project NameKeynatics Building Facade
Customer Number 
ePlanReviewYes
Description
(KEYNETICS BLDG – EXTERIOR FACADE) This building is fully fire sprinklered for story increase and area increase. Permit to remodel select exterior façade veneer of the existing building. Approval is contingent upon adhering to the approved plans on file and plan review report. Work to include: removal of select exterior stone veneer due to bond failure and replace it with stucco cement approximately 1,793 sq. ft. of surface area and select new coping cap at parapet. This building is fully Fire Sprinklered. Any alterations or modifications to the buildings Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 & NFPA 72 as regulated by the Boise Fire Department. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Print Statement  11/30/2018 DONE
Second Notice 10/22/201811/7/2018 DONE
mailed 11-12
First Notice9/26/20189/26/201810/12/2018 DONE
DetailsJim Storey
mailed 10-15-18
BLD-Final9/25/20189/26/20189/26/2018APASS
DetailsJim Storey
Brian Phone #: ###-####
DOC - Permit Finaled9/26/20189/26/20189/26/2018PPASS
DetailsJim Storey
BLD-Final9/24/20189/25/20189/25/2018ADEFR
DetailsJim Storey
Brian Phone #: ###-####
Inspection Record Card- Bld  9/25/2018 DONE
Permit Ready to Issue  7/9/2018 DONE
MET
Need
GC Form
(GC is Applicant)
Issue PAID IN FULL permit  7/9/2018 DONE
Inspection Record Card- Bld  7/9/2018 DONE
Plan assigned to (JG)7/2/20187/2/20187/7/2018 PASS
DetailsJavier Guzman
7/06 L1 Facade Renovation for RCP,LP ePlan**
Routing - PLAN CHECK7/2/2018 7/7/2018 PASS
DetailsJavier Guzman
1st review completed  7/7/2018 DONE
DetailsAdele J Schaffeld-Griffin
PLANS/APPL TAKEN TO FRONT DESK  7/7/2018 DONE
DetailsJavier Guzman
Routing - Erosion and Sediment7/2/2018 7/3/2018 PASS
DetailsMichael Zawacki
Cosmetic TI. Contractor responsible for keeping area clean. If area becomes mess an ESC waiver explaining house keeping and cleaning schedule will be required.
Routing - Addressing7/2/2018 7/2/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS7/2/2018 7/2/2018 PASS
DetailsMorgan Webb
Routing - Design Review7/2/2018 7/2/2018 PASS
DetailsKayCee Babb
per CZC18-00163. 5 days of appeal period waived due to safety concern.
Intake Approval  7/2/2018 PASS
DetailsJavier Guzman
Application received  6/27/2018 DONE
Application submitted via PDS Online on Jun 27 2018 12:17PM