FIRE-Conference | 5/15/2020 | 5/15/2020 | 5/15/2020 | P | DONE |
Troy Cobbley
|
|
|
Fire dept access has been approved by Ron with Boise Fire, The fire alarm system has been resolved. Need battery storage data to final life safety.
|
PubWorks Occupancy Approval | 5/9/2019 | 5/9/2019 | 5/9/2019 | | DONE |
Tiffany Lowery
|
|
|
|
BLD-Final | 4/26/2019 | 4/26/2019 | 4/26/2019 | P | NR |
Mike Jordan
|
|
|
Jason Phone #: ###-####. Fire/life/safety failed. Also need public works final inspection.
|
FIRE-Final Inspection | 4/25/2019 | 4/26/2019 | 4/26/2019 | A | FAIL |
Troy Cobbley
|
|
|
I need verification of all requirements listed under "Battery Storage" section of the fire code reveiw comments. Project superintendant stated these items were provided by Idaho Power.
Call half hour before // Jason Phone #: ###-####
|
FIRE-Final Inspection | 2/6/2019 | 2/7/2019 | 2/7/2019 | A | FAIL |
Troy Cobbley
|
|
|
Need small documents, need fire dept access approved (pending), need a permit for the already installed fire alarm system.
Jason-please call 30 minutes prior Phone #: ###-####
|
BLD-Framing/Rough-in | 10/18/2018 | 10/18/2018 | 10/18/2018 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Other | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | CANC |
Mike Jordan
|
|
|
roof inspection // Jason Phone #: ###-####. Moved to pm per contracotr.
|
BLD-Concrete | 9/25/2018 | 9/26/2018 | 9/26/2018 | P | PASS |
Mike Jordan
|
|
|
rebar-Jason Phone #: ###-####. Interior thickend footing and reinforcement for slab on grade.
|
BLD-Footing | 9/10/2018 | 9/11/2018 | 9/11/2018 | P | CANC |
Mike Jordan
|
|
|
Stem wall, early PM, pouring at 2 - Jason Phone #: ###-####
|
BLD-Foundation | 9/11/2018 | 9/11/2018 | 9/11/2018 | P | PASS |
Mike Jordan
|
|
|
Stem wall, early PM, pouring at 2 - Jason Phone #: ###-####
|
BLD-Footing | 9/6/2018 | 9/7/2018 | 9/7/2018 | A | PART |
Mike Jordan
|
|
|
jason Phone #: ###-####. Perimeter footings. Work in progress on installing vertical reinforcement. Ok to place concrete after special inspection has approved footings.
|
BLD-Footing | 9/5/2018 | 9/6/2018 | 9/6/2018 | P | CANC |
Mike Jordan
|
|
|
Pouring at 3, special inspections prior - Jason Phone #: ###-####. Cancelled per contractor via phone call.
|
Routing - MECHANICAL | 8/29/2018 | | 8/29/2018 | | PASS |
Troy James
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/29/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 8/29/2018 | | DONE |
|
|
|
need - MET
GC Form
Revised Cert of Value
|
Issue PAID IN FULL permit | | | 8/29/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/29/2018 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 7/23/2018 | | 8/29/2018 | | DONE |
Michael Hanson
|
|
|
08/22 #502 L1 ePlan. 1st review completed - See ePlan for corrections required. MDH
|
Routing - PLAN CHECK | 7/23/2018 | | 8/29/2018 | | PASS |
Michael Hanson
|
|
|
|
Route to Impact Fee Review | 8/22/2018 | 8/25/2018 | 8/23/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 7/23/2018 | 7/23/2018 | 8/22/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing Off Site - STRUCTURAL | 7/23/2018 | | 8/22/2018 | | PASS |
Michael Hanson
|
|
|
Passed in ePlan per KPFF. MDH
|
1st review completed | | | 8/22/2018 | | DONE |
Michael Hanson
|
|
|
|
Routing PW Drainage | 7/24/2018 | | 8/1/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING | 7/23/2018 | | 7/30/2018 | | PASS |
Susan Riggs
|
|
|
cup18-00018
|
Routing - MECHANICAL | 7/23/2018 | | 7/27/2018 | | FAIL |
Troy James
|
|
|
|
Routing - Design Review | 7/23/2018 | | 7/25/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH18-00103
|
Routing - Erosion and Sediment | 7/23/2018 | | 7/25/2018 | | PASS |
Andy J. Long
|
|
|
See ESC17-01792 for ESC coverage, no new ESC permit required.
|
Routing PW Solid Waste | 7/24/2018 | | 7/25/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing PW Sewer Rating | 7/24/2018 | | 7/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Street Lights | 7/24/2018 | | 7/24/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing PW Sewer Design | 7/24/2018 | | 7/24/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing - Addressing | 7/23/2018 | | 7/24/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/23/2018 | | 7/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 7/19/2018 | | PASS |
|
|
|
|
Intake Approval | | | 6/29/2018 | | FAIL |
|
|
|
|
Application received | | | 6/27/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 27 2018 4:35PM
|