BLD-Final | 11/1/2018 | 11/1/2018 | 11/1/2018 | P | PASS |
Jim Storey
|
|
|
Ken Phone #: ###-####
|
DOC - Permit Finaled | 11/1/2018 | 11/1/2018 | 11/1/2018 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 9/20/2018 | 9/20/2018 | 9/20/2018 | P | PASS |
Jim Storey
|
|
|
ken Phone #: ###-####
|
BLD-Framing/Rough-in | 9/20/2018 | 9/20/2018 | 9/20/2018 | P | PASS |
Jim Storey
|
|
|
ken Phone #: ###-####
|
BLD-Other | 9/18/2018 | 9/19/2018 | 9/19/2018 | A | PART |
Dave Hannah
|
|
|
fire wall // Kent Phone #: ###-#### sheet rock can light boxs ok
|
BLD-Energy code compliance | 9/17/2018 | 9/18/2018 | 9/18/2018 | A | NR |
Jim Storey
|
|
|
early am if poss // Ken Phone #: ###-####
|
BLD-Framing/Rough-in | 9/17/2018 | 9/18/2018 | 9/18/2018 | A | PART |
Jim Storey
|
|
|
early am if poss // Ken Phomech c
mech c\n
ne #: ###-####
|
BLD-Wall Bracing | 9/10/2018 | 9/10/2018 | 9/10/2018 | P | PASS |
Jim Storey
|
|
|
Ken Phone #: ###-####
|
Inspection Record Card- Bld | | | 8/29/2018 | | DONE |
|
|
|
|
BLD-Footing | 8/16/2018 | 8/17/2018 | 8/17/2018 | A | PASS |
Brandon Shaw
|
|
|
Jerry Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/1/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 7/18/2018 | | |
|
|
|
|
Inspection Record Card- Bld | | | 7/18/2018 | | DONE |
|
|
|
|
Telephone call | | | 7/18/2018 | | DONE |
|
|
|
called Kent to let know permit is ready and tell how much is owed-he asked me to email the info to him so i did
|
Plan assigned to (M_H) | 6/28/2018 | | 7/18/2018 | | DONE |
Michael Hanson
|
|
|
07/12 sfd L1 Paper. 1st review completed - Structural, energy, and design criteria deficiences. MDH
|
Case Summary (BLD) | | | 7/18/2018 | | DONE |
|
|
|
|
Routing - PLANNING | 7/18/2018 | | 7/18/2018 | | PASS |
Jeff Lowe
|
|
|
|
Routing - PLAN CHECK | 7/18/2018 | | 7/18/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/18/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 7/18/2018 | | DONE |
|
|
|
MET
Need
RP
|
Plan resubmittals received | | | 7/16/2018 | | DONE |
|
|
|
Resubmittals received 2 sets of sheets 1, 5 & 6-took to Michael Hanson
|
1st review completed | | | 7/12/2018 | | FAIL |
Michael Hanson
|
|
|
Structural, energy, and design criteria deficiences. MDH
|
Routing - PLAN CHECK | 7/5/2018 | | 7/12/2018 | | FAIL |
Michael Hanson
|
|
|
Structural, energy, and design criteria deficiences. MDH
|
Routing - MECHANICAL | 6/28/2018 | | 7/5/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 6/28/2018 | 7/1/2018 | 6/29/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Plans ACCEPTED BY PLAN TECH | | | 6/28/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/28/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/28/2018 | | DONE |
|
|
|
|
Routing - Addressing | 6/28/2018 | | 6/28/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | | | 6/28/2018 | | PASS |
|
|
|
|
Meeting | | | 6/28/2018 | | DONE |
|
|
|
KW HOmes came in yesterday and submitted for a new SFD-we took the plans and started the review so when the permit came in this morning I started it around as well but put a note in the subject line that it can not be issued unti the agreement issues have been met
|
Application received | | 6/28/2018 | | | |
|
|
|
|
Routing - PLANNING | 6/28/2018 | | | | FAIL |
|
|
|
Needs sub release letter
|