Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD18-02318
StatusFinaled
Name TOWERCOM TECHNOLOGIES LLC
Site Address 3214 E AMITY RD
Project NameVerizon - BOI Terrace
Customer Number 
ePlanReviewYes
Description
(VERIZON MONOPOLE CELL TOWER – BOI-TERRACE) Permit for the modifications to the existing monopole cell tower with work to include: New (6) panel antennas, (6) RRH units, (2) MOVP units, new concrete pad with generator plug and equipment cabinet and fence. No changes to the height of the tower. All work per approved plans. MDH
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection11/22/201911/22/201911/22/2019 DONE
DetailsBrandon Shaw
DOC - Permit Finaled11/22/201911/22/201911/22/2019PPASS
DetailsBrandon Shaw
DOC - Permit Expired11/22/201911/22/201911/22/2019PDONE
DetailsBrandon Shaw
Issue PAID IN FULL permit  1/7/2019 DONE
Extend Review Timeline  1/3/2019 DONE
1st approved 180 day extension per adele. see documents
Meeting  1/2/2019 DONE
Jason Evans emailed in request for extension 12/31/18
Telephone call  12/27/2018 DONE
spoke with jason informing him that this permit is day past the date. stated still wanting for 302 and 306 forms and he is welcome to send in a request for an extension
Expiration Notice11/23/201812/14/201811/23/2018 DONE
DetailsBrittany Hill
1st review completed  9/4/2018 DONE
DetailsMichael Hanson
PLANS/APPL TAKEN TO FRONT DESK  9/4/2018 DONE
DetailsMichael Hanson
Permit Ready to Issue  9/4/2018 DONE
NEED
GC FORM
REVISED VALUE
Plan assigned to (M_H)8/9/2018 9/4/2018 DONE
DetailsMichael Hanson
09/07 #502 L1 ePlan Verizon
Routing - PLAN CHECK8/9/2018 9/4/2018 PASS
DetailsMichael Hanson
Routing - PLANNING8/9/2018 8/15/2018 PASS
DetailsNicolette Womack
Intake Approval  8/6/2018 PASS
Intake Approval  7/30/2018 FAIL
DetailsBrian McGowan
Please provide the following corrections or items;
1. 502 Submittal checklist.
2. Many of the Drawings have "PRELIMINARY NOT FOR CONSTRUCTION" on them. Please provide drawings without this on them.
7-30-18 BJM
Application received  6/28/2018 DONE
Application submitted via PDS Online on Jun 28 2018 5:04PM
First Notice11/22/201911/22/2019   
DetailsBrandon Shaw