BLD-Final | 11/15/2018 | 11/16/2018 | 11/16/2018 | A | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-####
|
DOC - Permit Finaled | 11/16/2018 | 11/16/2018 | 11/16/2018 | P | PASS |
Jim Storey
|
|
|
|
BLD-Energy code compliance | 8/27/2018 | 8/30/2018 | 8/30/2018 | A | PASS |
Brandon Shaw
|
|
|
TOdd Phone #: ###-####
|
BLD-Framing/Rough-in | 8/28/2018 | 8/28/2018 | 8/28/2018 | P | PASS |
Jim Storey
|
|
|
TOdd Phone #: ###-#### truss c/n made ok
|
BLD-Framing/Rough-in | 8/27/2018 | 8/28/2018 | 8/28/2018 | A | NR |
Dave Hannah
|
|
|
TOdd Phone #: ###-#### no plans on site
|
BLD-Energy code compliance | 8/20/2018 | 8/24/2018 | 8/24/2018 | A | NR |
Jim Storey
|
|
|
Todd Phone #: ###-####
|
BLD-Framing/Rough-in | 8/20/2018 | 8/22/2018 | 8/22/2018 | P | FAIL |
Jim Storey
|
|
|
Todd Phone #: ###-#### c/n
|
BLD-Wall Bracing | 8/9/2018 | 8/10/2018 | 8/10/2018 | A | PASS |
Jim Storey
|
|
|
Todd Phone #: ###-####
|
BLD-Wall Bracing | 8/7/2018 | 8/9/2018 | 8/9/2018 | A | FAIL |
Jim Storey
|
|
|
Shear // Todd Phone #: ###-#### nails overdriven/nr
|
BLD-Footing | 7/25/2018 | 7/25/2018 | 7/25/2018 | P | PASS |
Jim Storey
|
|
|
Ryan Phone #: ###-####
|
Inspection Record Card- Bld | | | 7/16/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/16/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 7/13/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 7/12/2018 | 7/12/2018 | 7/13/2018 | | DONE |
Brian McGowan
|
|
|
1st Review Complete 07/12 sfd L1 ePlan
|
Routing - PLAN CHECK | 7/13/2018 | | 7/13/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/13/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 7/13/2018 | | DONE |
|
|
|
todd@liveinboise.com
|
1st review completed | | | 7/12/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - PLAN CHECK | 6/29/2018 | | 7/12/2018 | | FAIL |
Brian McGowan
|
|
|
|
Routing - MECHANICAL | 6/29/2018 | | 7/3/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 6/29/2018 | 7/2/2018 | 7/2/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - PLANNING | 6/29/2018 | | 7/2/2018 | | PASS |
Colleen T Carroll
|
|
|
ROS18-00050
|
Routing - Addressing | 6/29/2018 | | 7/2/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 6/29/2018 | | 7/2/2018 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 6/29/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 29 2018 8:20AM
|
Plan assigned to (RDP) | 6/29/2018 | 6/29/2018 | 6/29/2018 | | DEFR |
Rob Patrick
|
|
|
7/12 sfd L1 ePlan
|
Intake Approval | | | 6/29/2018 | | FAIL |
|
|
|
1.Building Cross section of the whole building.
2. Elevation heights
3. ROS18-00050 needs to be recorded
|
Intake Approval | | | 6/29/2018 | | FAIL |
|
|
|
Missing height on elevations
(PER TODD PLANS ON IN EPLAN OK TO TAKE IN) ROS18-00050 has not been recorded/approved
|
Plans ACCEPTED BY PLAN TECH | | | 6/29/2018 | | DONE |
|
|
|
|
Intake Approval | | | 6/29/2018 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 6/29/2018 | | DONE |
|
|
|
|