BLD-Final | 3/7/2019 | 3/7/2019 | 3/7/2019 | A | PASS |
Mike Jordan
|
|
|
door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
DOC - Permit Finaled | 3/7/2019 | 3/7/2019 | 3/7/2019 | P | PASS |
Mike Jordan
|
|
|
All issues resolved.
|
BLD-Blower Door Test Results | 3/7/2019 | 3/7/2019 | 3/7/2019 | A | DONE |
Mike Jordan
|
|
|
3.93ACH @ 50pa.
|
BLD-Final | 2/26/2019 | 2/27/2019 | 2/27/2019 | P | FAIL |
Mike Jordan
|
|
|
Door code is 2468 Phone #: ###-#### Inspection requested via web by Joel Hirtle. Provide code compliant landing and stairs from rear door. install the handrails. Install the 20 min. door and smoke seal.
|
BLD-Energy code compliance | 1/15/2019 | 1/16/2019 | 1/16/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 1/15/2019 | 1/15/2019 | 1/15/2019 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle
|
BLD-Framing/Rough-in | 1/14/2019 | 1/14/2019 | 1/14/2019 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Remove insulation for framing inspection.
|
BLD-Framing/Rough-in | 1/10/2019 | 1/10/2019 | 1/10/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Mech. rough in inspection has failed.
|
BLD-Framing/Rough-in | 1/8/2019 | 1/10/2019 | 1/10/2019 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Joel Hirtle Inspection cancelled from web by: Joel Hirtle
|
BLD-Framing/Rough-in | 1/7/2019 | 1/8/2019 | 1/8/2019 | A | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Joel Hirtle. Mech rough in inspection has failed.
|
Plan Modification Accepted | | | 1/2/2019 | | DONE |
|
|
|
resubmitted manual j report
|
Routing - MECHANICAL | 1/2/2019 | | 1/2/2019 | | PASS |
Troy James
|
|
|
New manual j report
|
BLD-Wall Bracing | 12/20/2018 | 12/21/2018 | 12/21/2018 | P | PASS |
Mike Jordan
|
|
|
Matt Phone #: ###-####
|
BLD-Foundation | 11/26/2018 | 11/27/2018 | 11/27/2018 | P | NR |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
BLD-Footing | 11/21/2018 | 11/26/2018 | 11/26/2018 | P | PASS |
Mike Jordan
|
|
|
Dane Phone #: ###-####
|
Issue PAID IN FULL permit | | | 8/21/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/21/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 8/7/2018 | | |
|
|
|
|
Plan assigned to (BJM) | 7/2/2018 | 7/2/2018 | 8/7/2018 | | DONE |
Brian McGowan
|
|
|
1st Review Complete - 07/16 sfd L1 ePlan
|
Routing - PLAN CHECK | 8/7/2018 | | 8/7/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 8/7/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/2/2018 | | 7/16/2018 | | FAIL |
Brian McGowan
|
|
|
|
1st review completed | | | 7/16/2018 | | FAIL |
Brian McGowan
|
|
|
|
Route to Impact Fee Review | 7/2/2018 | 7/5/2018 | 7/3/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 7/2/2018 | | 7/3/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 7/2/2018 | | 7/2/2018 | | PASS |
Colleen T Carroll
|
|
|
|
Routing - Addressing | 7/2/2018 | | 7/2/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/2/2018 | | 7/2/2018 | | PASS |
Morgan Webb
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 7/2/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/2/2018 | | DONE |
|
|
|
|
Intake Approval | | | 7/2/2018 | | PASS |
|
|
|
|
Application received | | | 6/29/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jun 29 2018 8:49AM
|