Permit Information
Permit NumberBLD18-02372
StatusFinaled
Name MUSSELL CONSTRUCTION
Site Address 5823 W FRANKLIN RD
Project NameChristian Faith Center Boise
Customer NumberDEMO BLD18-02897
ePlanReviewYes
Description
(CHRISTIAN FAITH CENTER) (DRH18-00317) A fire sprinkler system will be installed in conjunction with this permit and is used for building area increase, for fire flow, and for occupancy. Interior nonstructural demolition work was done under permit BLD18-02897. To remodel an existing 12,023 square foot building and convert it to a church (11,431 square feet inside and 592 square feet below the canopy). This tenant space is not approved as a child daycare facility. The sanctuary will have a total floor area of about 4,073 square feet (2,687 square feet seating area, 753 square feet platform, 144 square feet sound platform, 218 square feet storage, 220 square feet ramp, and 51 square feet interior walls) and an occupant load of 357 (305 chairs, 1 sound, 1 storage, and 50 platform). The new 24 inch high platform will be served by stairways and a ramp. The new 24 inch high sound platform will be served by a stairway. Work is to include cripple walls to support the platform floors, platform sheathing, platform bracing walls and panels, a new interior 2 inch thick concrete topping slab over the existing slab on grade, a new exterior concrete sidewalk, interior nonbearing walls, furred and insulated exterior walls, two multi-user toilet rooms accessible to the disabled, three single-user toilet rooms accessible to the disabled (one per child dimensions), interior doors, interior windows, a warming kitchen with a range and hood, suspended acoustical ceilings, suspended gypsum board ceilings, gypsum board ceilings, foil-scrim-kraft vapor retarder, millwork, and finishes. Cooking operations that create grease laden vapors are not allowed within this building. An existing double leaf exterior doorway will be partially filled in with masonry and a new single leaf door will be installed. Structural work to the existing building includes concrete footings, steel columns, steel beam, and steel glu-lam beam hangers. Two existing columns will be removed. Special Inspection is required for anchors post-installed in hardened concrete and for welding. The work is required to comply with the approved drawings, with the structural design, with the plan review report, and with all applicable codes and ordinances. The fire sprinkler system is required to comply with NFPA 13 and the fire alarm system is required to comply with NFPA 72 as regulated by the Fire Department. Separate fire sprinkler permits and fire alarm permits shall be obtained prior to beginning any modification or installation work on such systems. **CJW**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 4/13/20194/15/2019 DONE
This permit finaled on the web by Jay Lundergan
Second Notice 3/21/20194/8/2019 DONE
mailed 4-11-19
First Notice 2/18/20193/11/2019 DONE
mailed 3-12
BLD-Final2/7/20192/8/20192/8/2019APASS
DetailsMike Jordan
Gary Phone #: ###-####. All issues have been resolved. Ok for perm occ.
Permanent Occupancy  2/8/2019 DONE
FIRE-Final Inspection2/5/20192/6/20192/6/2019APASS
DetailsTroy Cobbley
Life safety passed

Gary Phone #: ###-####
BLD-Final1/29/20191/31/20191/31/2019PFAIL
DetailsMike Jordan
Gerla Phone #: ###-####. Provide code compliant handrails on ramp and all stairs.
FIRE-Final Inspection1/30/20191/31/20191/31/2019APART
DetailsTroy Cobbley
A temporary for life safety until the knox box is provided.

Gary Phone #: ###-####
BLD-Ceiling Grid Inspection1/11/20191/14/20191/14/2019APASS
DetailsBrandon Shaw
Gary Phone #: ###-####
BLD-Framing/Rough-in11/19/201811/19/201811/19/2018PPASS
DetailsMike Jordan
Gary Phone #: ###-####. Interior steel stud framed walls be stage and front of house ok.
BLD-Other11/12/201811/13/201811/13/2018PPASS
DetailsMike Jordan
Gary is the on-site superintendent. This is for the insulation inspection for the exterior walls. Phone #: ###-#### Inspection requested via web by Mark Fledderjohann
BLD-Framing/Rough-in11/6/201811/7/201811/7/2018PPASS
DetailsMike Jordan
Gary Phone #: ###-####. Interior steel stud framed walls only ok.
BLD-Framing/Rough-in10/3/201810/5/201810/5/2018APASS
DetailsMike Jordan
Gary-framing in ceiling only-or ###-#### Calvin Phone #: ###-####. New framed openings in roof structure for new RTU's and curbs. All work done per the New engineering provided by performance engineers.
BLD-Conference9/28/20189/28/20189/28/2018PDONE
DetailsMike Jordan
Mark Phone #: ###-####. Contractor wants to hardlid the ceiling. Will need to show how to ventilate the created attic and maintain the 1 inch airgap at roof deck. Will also need to verfiy adequate fire sprinkler clearances with the fire inspector.
BLD-Footing9/13/20189/13/20189/13/2018PPASS
DetailsMike Jordan
Gary Gerla Phone #: ###-####
Issue PAID IN FULL permit  9/13/2018 DONE
Print Occupancy Form  9/13/2018 DONE
(F) Reprint permit  9/13/2018 DONE
Print Occupancy Form  9/13/2018 DONE
Plan assigned to (CJW)8/15/20188/15/20189/12/2018 PASS
DetailsCarl Westfall
(2nd done) 08/21/18 (L3 - 15 days) (ePlan - 27 sheets) Faith Christian Center
Routing - MECHANICAL9/5/2018 9/12/2018 PASS
DetailsTroy James
Routing Off Site - STRUCTURAL9/5/2018 9/12/2018 PASS
DetailsCarl Westfall
Dave Haugland (AHJ)
PLANS/APPL TAKEN TO FRONT DESK  9/12/2018 DONE
Permit Ready to Issue  9/12/2018 DONE
MET
NEED
GC FORM
Telephone call  9/12/2018 DONE
sent email info@mussellconstruction.com informing 302 form is still needed before issuance
Routing - PLAN CHECK9/4/2018 9/5/2018 PASS
DetailsCarl Westfall
Routing - Design Review9/5/2018 9/5/2018 PASS
DetailsKatelyn Menuge
DRH18-00317
Plan resubmittals received  9/4/2018 DONE
1st review completed  8/30/2018 DONE
Plan resubmittals requested  8/30/2018 DONE
Routing - PLAN CHECK8/1/2018 8/30/2018 FAIL
DetailsCarl Westfall
Pass pending structural
Routing - FIRE8/1/20188/1/20188/29/2018 PASS
DetailsErika Akin
Attached comments to case
Routing Off Site - STRUCTURAL8/1/2018 8/23/2018 FAIL
DetailsCarl Westfall
Dave Haugland (AHJ)
Plan Reviewer's activity  8/21/2018 DONE
Uploaded revised sheets. Left message for Dave Haugland letting him know that I had uploaded structural sheets for his review.
Plan assigned to (CJW)8/1/20188/1/20188/11/2018 PASS
DetailsCarl Westfall
* 08/21/18 (L3 - 15 days) (ePlan - 27 sheets) Faith Christian Center
Routing - MECHANICAL8/1/2018 8/8/2018 FAIL
DetailsTroy James
Routing - Erosion and Sediment8/1/2018 8/6/2018 PASS
DetailsMichael Zawacki
Interior TI. No ESC required.
Routing - PLUMBING8/1/2018 8/2/2018 PASS
DetailsBill VanDegrift
Per plan and ISPC
Routing - PLANNING8/1/2018 8/2/2018 PASS
DetailsSusan Riggs
No review required
Routing - Design Review8/1/2018 8/2/2018 FAIL
DetailsKatelyn Menuge
Please add notes that seats in the sanctuary will not exceed 365 at this time, and all new rooftop equipment will be screened from view to comply with the Design Review requirements.
Routing - PUBLIC WORKS8/1/2018 8/2/2018 PASS
DetailsMorgan Webb
Intake Approval  8/1/2018 PASS
Plan Reviewer's activity  8/1/2018 DONE
Jeff, as this is a change in use for this space please contact ACHD to verify whether any ACHD impact fees are due. The city will require documentation whether fees are due or not. If fees are due they may be paid to ACHD prior to the issuance of the permit or to the city at the time the permit is issued.
Routing - Addressing8/1/2018 8/1/2018 PASS
DetailsDoug Chausow
Intake Approval  7/9/2018 FAIL
DetailsMichael Hanson
This permit has failed prescreen due to the following:
1. Provide completed and signed 518 checklist document.
2. Provide completed and signed 304 registered design professional form.
3. New exterior door requires Design Review approval. Complete the DR process through boisecity.org (Andrea Tuning X7078)
4. Provide wall bracing detail (how are new interior wall connected to existing structure)
5. Provide completed, stamped, and signed 310 form for steel beam.
Application received  7/3/2018 DONE
Application submitted via PDS Online on Jul 3 2018 11:31AM