BLD-Framing/Rough-in | 9/13/2018 | 9/14/2018 | 9/14/2018 | A | CANC |
Dave Hannah
|
|
|
Phone #: ###-#### >> Inspection requested via web by kevin debelloy Inspection cancelled from web by: kevin debelloy
|
BLD-Foundation | 7/17/2018 | 7/17/2018 | 7/17/2018 | P | PASS |
Dave Hannah
|
|
|
Pour is scheduled for 2:00 Phone #: ###-#### Inspection requested via web by kevin debelloy
|
BLD-Footing | 7/16/2018 | 7/16/2018 | 7/16/2018 | P | PASS |
Dave Hannah
|
|
|
footing Pour is set for 3:00 Phone #: ###-#### Inspection requested via web by kevin debelloy
|
PubWorks Subgrade Approval | 7/16/2018 | 7/16/2018 | 7/16/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Routing Walk-In (BLD) | 7/13/2018 | 7/13/2018 | 7/13/2018 | A | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 7/3/2018 | 7/3/2018 | 7/13/2018 | | PASS |
Josh Bogle
|
|
|
1st done - Hillside detached structure
|
Inspection Record Card- Bld | | | 7/13/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 7/13/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/13/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 7/13/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/13/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 7/13/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 7/11/2018 | | 7/13/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing - FIRE | 7/11/2018 | 7/11/2018 | 7/12/2018 | | PASS |
Tim Frost
|
|
|
|
Routing Walk-In (BLD) | 7/11/2018 | 7/11/2018 | 7/11/2018 | P | PASS |
Josh Bogle
|
|
|
conversation with Merlin about resubmittal process
|
Plan resubmittals received | | | 7/11/2018 | | DONE |
|
|
|
Received 2 sets revised L1.02 and L1.05 and 2 11X17 plan sets; plans stamped and taken to JAB for review
|
Routing - PLAN CHECK | 7/3/2018 | | 7/9/2018 | | FAIL |
Josh Bogle
|
|
|
structure not allowed by Fire, size/location
|
1st review completed | | | 7/9/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - FIRE | 7/3/2018 | 7/3/2018 | 7/6/2018 | | FAIL |
Tim Frost
|
|
|
7/24 New Poolhouse SFH paper
|
Routing - Erosion and Sediment | 7/3/2018 | | 7/6/2018 | | PASS |
Andy J. Long
|
|
|
ESC permit already issued with initial pool permit. See ESC18-00551
|
Routing PW Grading-Hillside | 7/3/2018 | | 7/5/2018 | | PASS |
Jason C. Taylor
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Call Jason Taylor ###-####.
|
Routing Walk-In (Zoning) | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | PASS |
Jeff Lowe
|
|
|
|
Routing Walk-In (BLD) | 7/3/2018 | 7/3/2018 | 7/3/2018 | P | PASS |
Josh Bogle
|
|
|
took in as a level 2 - Hillside
|
Application received | | 7/3/2018 | | | |
|
|
|
|