BLD-Final | 4/3/2019 | 4/4/2019 | 4/4/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 4/4/2019 | 4/4/2019 | 4/4/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 4/3/2019 | 4/4/2019 | 4/4/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.85
|
BLD-Energy code compliance | 2/7/2019 | 2/11/2019 | 2/11/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Framing/Rough-in | 2/6/2019 | 2/7/2019 | 2/7/2019 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Wall Bracing | 2/6/2019 | 2/7/2019 | 2/7/2019 | A | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Framing/Rough-in | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | FAIL |
Brandon Shaw
|
|
|
Shear corrections not complete...
|
BLD-Wall Bracing | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | FAIL |
Brandon Shaw
|
|
|
All hold downs and anchor bolts to be as per plans and installed per Manufactures installations instructions...
|
BLD-Other | 2/5/2019 | 2/5/2019 | 2/5/2019 | P | PASS |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Framing/Rough-in | 1/30/2019 | 1/31/2019 | 1/31/2019 | P | NR |
Brandon Shaw
|
|
|
Air seal is scheduled same day, if we can do it later? Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Wall Bracing | 1/30/2019 | 1/31/2019 | 1/31/2019 | A | FAIL |
Brandon Shaw
|
|
|
Complete installation of all anchor bolts, hold downs, and straps as per plans...
|
BLD-Wall Bracing | 1/16/2019 | 1/16/2019 | 1/16/2019 | P | NR |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Foundation | 11/20/2018 | 11/20/2018 | 11/20/2018 | P | DEFR |
Brandon Shaw
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
BLD-Footing | 11/18/2018 | 11/19/2018 | 11/19/2018 | A | PASS |
Jim Sly
|
|
|
As late as possible Phone #: 2084207023 >> Inspection requested via mobile web by Dion Connell
|
Issue PAID IN FULL permit | | | 10/11/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/11/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 7/24/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 7/24/2018 | | DONE |
|
|
|
met
|
Plan assigned to (M_H) | 7/13/2018 | | 7/23/2018 | | DONE |
Michael Hanson
|
|
|
07/16 sfd L1 ePlan. 1st review completed - Structural deficiences. MDH
|
Routing - PLAN CHECK | 7/13/2018 | | 7/23/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/23/2018 | | DONE |
Michael Hanson
|
|
|
|
Plan assigned to (RDP) | 7/3/2018 | 7/3/2018 | 7/13/2018 | | DEFR |
Rob Patrick
|
|
|
7/16 sfd L1 ePlan
|
Routing - PLAN CHECK | 7/3/2018 | | 7/13/2018 | | FAIL |
Michael Hanson
|
|
|
Structural deficiences. MDH
|
1st review completed | | | 7/13/2018 | | DONE |
Michael Hanson
|
|
|
Structural deficiences. MDH
|
Route to Impact Fee Review | 7/3/2018 | 7/6/2018 | 7/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 7/3/2018 | | 7/5/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Routing - PLANNING | 7/3/2018 | | 7/5/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 7/3/2018 | | 7/5/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/3/2018 | | 7/5/2018 | | PASS |
Morgan Webb
|
|
|
|
Application received | | | 7/3/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 3 2018 3:39PM
|
Plans ACCEPTED BY PLAN TECH | | | 7/3/2018 | | DONE |
|
|
|
|
Intake Approval | | | 7/3/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/3/2018 | | DONE |
|
|
|
|