Print Statement | | | 4/19/2019 | | DONE |
|
|
|
sent 1st late notice
|
Print Statement | | | 12/20/2018 | | DONE |
|
|
|
|
First Notice | | 11/23/2018 | 12/14/2018 | | DONE |
|
|
|
mailed 12-17
|
Permanent Occupancy | | | 11/13/2018 | | DONE |
|
|
|
|
BLD-Final | 10/18/2018 | 10/19/2018 | 10/19/2018 | A | PASS |
Jim Sly
|
|
|
Tim Phone #: ###-#### OK for Perm Occ.
|
Temporary Occupancy | 10/16/2018 | 1/14/2019 | 10/16/2018 | | DONE |
Tiffany Carson-Herker
|
|
|
|
Print Occupancy Form | | | 10/16/2018 | | DONE |
|
|
|
|
BLD-Final | 10/11/2018 | 10/12/2018 | 10/12/2018 | A | PART |
Jim Storey
|
|
|
Tim Phone #: ###-#### c/n gaurdrail needs complet at each end min 4 inches open/ handrail extention top of stair needs per plan/ gate needs stop. // exit path needs defined.
|
FIRE-Final Inspection | 10/11/2018 | 10/11/2018 | 10/11/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed
Tim Brewer Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 9/27/2018 | 9/28/2018 | 9/28/2018 | P | PASS |
Jim Storey
|
|
|
Clinton Phone #: ###-####
|
Plan assigned to (CJW) | 8/6/2018 | 8/6/2018 | 9/20/2018 | | PASS |
Carl Westfall
|
|
|
(2nd done) 08/21/18 (L3 - 15 days) (ePlan - 32 sheets) Positive Pets
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/20/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/20/2018 | | DONE |
|
|
|
DMINEGAR@LAYTONCONSTRUCTION.COM
MET
NEED
GC
Rev Cert of Val
|
Issue PAID IN FULL permit | | | 9/20/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/20/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 9/19/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/19/2018 | | 9/19/2018 | | PASS |
Carl Westfall
|
|
|
Pending structural
|
Routing Off Site - STRUCTURAL | 9/19/2018 | | 9/19/2018 | | PASS |
Carl Westfall
|
|
|
Jan Welch (stapley)
|
Routing Off Site - STRUCTURAL | 9/13/2018 | | 9/18/2018 | | FAIL |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Plan resubmittals requested | | | 9/18/2018 | | DONE |
|
|
|
|
Routing - Design Review | 9/13/2018 | | 9/13/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Routing - PUBLIC WORKS | 9/13/2018 | | 9/13/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Drainage | 9/13/2018 | | 9/13/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLANNING | 9/13/2018 | | 9/13/2018 | | PASS |
David Moser
|
|
|
|
Plan resubmittals received | | | 9/13/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/13/2018 | | 9/13/2018 | | FAIL |
Carl Westfall
|
|
|
Item #3 about the mezzanine live load design was not resolved.
|
Route to Impact Fee Review | 9/4/2018 | 9/7/2018 | 9/4/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 9/4/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 9/4/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/6/2018 | | 9/4/2018 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - FIRE | 8/6/2018 | 8/6/2018 | 8/31/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing Off Site - STRUCTURAL | 8/7/2018 | | 8/16/2018 | | FAIL |
Carl Westfall
|
|
|
Jan Welch (Stapley)
|
Routing - MECHANICAL | 8/6/2018 | | 8/9/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 8/6/2018 | | 8/7/2018 | | PASS |
Bill VanDegrift
|
|
|
Per ISPC
|
Routing - PLANNING | 8/6/2018 | | 8/7/2018 | | PASS |
David Moser
|
|
|
|
Routing - Addressing | 8/6/2018 | | 8/7/2018 | | PASS |
Doug Chausow
|
|
|
Suite 140
|
Routing - PUBLIC WORKS | 8/6/2018 | | 8/7/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Environmental | 8/7/2018 | | 8/7/2018 | | PASS |
Terry Alber
|
|
|
Pretreatment finds no issues.
|
Plan Reviewer's activity | | | 8/6/2018 | | DONE |
Carl D Madsen
|
|
|
Joshua, just a heads up this permit will be routed as a major tenant improvement since it is a first time use for this space. Also please be sure to verify if any ACHD fees will be due for this tenant. Fee verification will be required prior to issuing the building permit.
|
Routing - Design Review | 8/6/2018 | | 8/6/2018 | | PASS |
Katelyn Menuge
|
|
|
Use okay per Cody
|
Intake Approval | | | 8/1/2018 | | PASS |
|
|
|
|
Intake Approval | | | 7/26/2018 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following: 1. Design review is pending review and approval. MDH
|
Intake Approval | | | 7/16/2018 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. Missing design review approval for exterior modifications.
2. Missing #310 form
|
Application received | | | 7/12/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 12 2018 2:41PM
|