Case Summary (BLD) | | | 2/12/2019 | | DONE |
|
|
|
|
Telephone call | | | 2/12/2019 | | DONE |
|
|
|
as of 2-12-19-permit is now in parcel owners name-see letter from GC
|
BLD-Energy code compliance | 2/7/2019 | 2/8/2019 | 2/8/2019 | A | PASS |
Jim Storey
|
|
|
Call if you need access key Phone #: ###-#### Inspection requested via web by Andrew Clark
|
BLD-Framing/Rough-in | 2/6/2019 | 2/6/2019 | 2/6/2019 | P | PASS |
Jim Storey
|
|
|
All trades have inspections signed off. need okay to insulate. Phone #: ###-#### Inspection requested via web by Andrew Clark
|
BLD-Framing/Rough-in | 1/29/2019 | 1/30/2019 | 1/30/2019 | P | NR |
Jim Storey
|
|
|
Please use rear door for access if you have issues getting in please call sometimes subs lock up the doors. Phone #: ###-#### Inspection requested via web by Andrew Clark mech insp.failled
|
BLD-Framing/Rough-in | 1/28/2019 | 1/29/2019 | 1/29/2019 | P | NR |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Andrew Clark no access and no sign off for mech
|
BLD-Framing/Rough-in | 1/21/2019 | 1/22/2019 | 1/22/2019 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Andrew Clark pending trade instaltion.
|
BLD-Footing | 1/9/2019 | 1/10/2019 | 1/10/2019 | A | PASS |
Jim Storey
|
|
|
Andrew Phone #: ###-####
|
Issue PAID IN FULL permit | | | 12/27/2018 | | DONE |
|
|
|
|
Expiration Notice | 12/11/2018 | 1/3/2019 | 12/11/2018 | | DONE |
Brittany Hill
|
|
|
|
Plan assigned to (JAB) Josh | 7/19/2018 | 7/19/2018 | 9/28/2018 | | PASS |
Josh Bogle
|
|
|
07/25 addition ePlan - 1st done
|
Routing - PLAN CHECK | 9/28/2018 | | 9/28/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/28/2018 | | DONE |
Josh Bogle
|
|
|
Additional Review fees (see agency comments folder in ePlan) - ESC no - Energy yes
|
Permit Ready to Issue | | | 9/28/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 9/25/2018 | | 9/25/2018 | | FAIL |
Josh Bogle
|
|
|
inadequate headers, footings not matching engineering
|
Routing - PLAN CHECK | 9/19/2018 | | 9/19/2018 | | FAIL |
Josh Bogle
|
|
|
point load, header, footing, & head height issues
|
Telephone call | | | 8/27/2018 | | DONE |
|
|
|
Spoke with Andrew, deleted duplicate files
|
Routing - PLAN CHECK | 8/27/2018 | | 8/27/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - MECHANICAL | 8/15/2018 | | 8/17/2018 | | PASS |
Troy James
|
|
|
Bonus room heating design is with existing equipment, new ductwork only.
|
Routing - PLAN CHECK | 8/15/2018 | | 8/17/2018 | | FAIL |
Josh Bogle
|
|
|
|
Plan Reviewer's activity | | | 8/15/2018 | | DONE |
Josh Bogle
|
|
|
resubmit received task - cycle two
|
1st review completed | | | 7/26/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 7/19/2018 | | 7/26/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - MECHANICAL | 7/19/2018 | | 7/24/2018 | | FAIL |
Troy James
|
|
|
Talked to applicant about heating design. He was going to find out and get back to me.
|
Routing - PLANNING | 7/19/2018 | | 7/19/2018 | | PASS |
Sue Cummings
|
|
|
|
Intake Approval | | | 7/19/2018 | | PASS |
|
|
|
Plans taken in for review, missing few details still.
|
Plans ACCEPTED BY PLAN TECH | | | 7/19/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/19/2018 | | DONE |
|
|
|
no fee taken at intake, 406
|
Intake Approval | | | 7/17/2018 | | FAIL |
Candy A. Nichols
|
|
|
still have not uploaded the correct info-told them to check the list and uplaod the required items
|
Intake Approval | | | 7/16/2018 | | FAIL |
|
|
|
NEED
All measurements to property lines
File names label correctly
Footing for deck
Manual J due to "Design build new HVAC for additional upper level space" marked on plans
|
Application received | | | 7/13/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 13 2018 9:52AM
|
Intake Approval | | | 7/13/2018 | | FAIL |
|
|
|
need to update to 2015 IRC.
need correct file names.
footings for deck.
floor framing.
treads and risers on the stairs.
Manual J
site plan
|
Intake Approval | | | 7/13/2018 | | FAIL |
|
|
|
7-13-18 Please see pervious prescreen checklist items listed above (6)
(The plans in the drawing folder have been deleted, to make it easier for uploading with correct drawing file names.)
For questions on the New HVAC report (manual J,D or S) please call Troy James at 208-###-####
|