Permit Information
Permit NumberBLD18-02540
StatusIssued
Name KING BUILDING & REMODELING
Site Address 123 W CRESTLINE DR
Project NameHormaechea Remodel
Customer Number 
ePlanReviewYes
Description
Full gut-to-the-stud remodel and addition that adds 1,040sq' of living space and 490sq' of a garage. Final home is 4bd/3.5bth. All work per plans, notes, engineering, local codes & ordinances. Separate electrical, plumbing & mechanical permits required. **JAB**


A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at 208-608-7168 with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at 208-608-7168.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.

An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call 208-608-7070 to schedule an inspection.
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
PubWorks Occupancy Approval9/12/20199/12/20199/12/2019 DONE
DetailsMelissa Jannusch
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
BLD-Energy code compliance11/13/201811/14/201811/14/2018APASS
DetailsDave Hannah
Lynn Phone #: ###-####
BLD-Framing/Rough-in11/5/201811/6/201811/6/2018APASS
DetailsTony Young
John Phone #: ###-####
BLD-Framing/Rough-in10/31/201811/1/201811/1/2018APEND
DetailsBrandon Shaw
Framing good to go...
Foam/air seal to be done before spray foam installation, call air seal...
Plan Modification Accepted  10/31/2018 DONE
New manual j report
Routing - MECHANICAL10/31/2018 10/31/2018 PASS
DetailsTroy James
Resubmitted manual j report. Owner decided to use the existing equipment.
BLD-Wall Bracing10/16/201810/17/201810/17/2018APASS
DetailsTony Young
Ren Phone #: ###-####
BLD-Foundation8/27/20188/27/20188/27/2018PPART
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jon King,, work in progress
BLD-Footing8/20/20188/20/20188/20/2018PPART
DetailsTony Young
Phone #: ###-#### Inspection requested via web by Jon King,, work in progress,, ok
PubWorks Subgrade Approval8/20/20188/20/20188/20/2018 DONE
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
OVERRIDE  8/7/2018  
Routing Walk-In (BLD)8/7/20188/7/20188/7/2018PDONE
DetailsJosh Bogle
Routing - FIRE7/31/20187/31/20188/7/2018 PASS
DetailsTim Frost
Resubmittal SFH ePlan
Plan assigned to (JAB) Josh7/18/20187/18/20188/7/2018 PASS
DetailsJosh Bogle
07/24 remodel ePlan - 2nd review, sent to Hillside & Fire
Routing - PLAN CHECK7/31/2018 8/7/2018 PASS
DetailsJosh Bogle
PLANS/APPL TAKEN TO FRONT DESK  8/7/2018 DONE
DetailsJosh Bogle
ESC yes - Energy yes
Permit Ready to Issue  8/7/2018 DONE
NEED
RP
Issue PAID IN FULL permit  8/7/2018 DONE
Routing - Erosion and Sediment7/31/2018 8/3/2018 PASS
DetailsMelissa Jannusch
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.

Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.

The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
Routing - PLANNING7/18/2018 7/30/2018 PASS
DetailsSusan Riggs
CFH18-00062 Susan Riggs
Routing - PLAN CHECK7/18/2018 7/25/2018 FAIL
DetailsJosh Bogle
Plan Reviewer's activity  7/25/2018 DONE
Received fire flow information of 1500 Gpm. A fire flow of 1750 Gpm is required.

Told the builder via email fire sprinklers will be required in order to reduce the amount of fire flow required.
1st review completed  7/25/2018 FAIL
DetailsJosh Bogle
Plan Reviewer's activity  7/24/2018 DONE
Jon King, sent an updated drawing which I uploaded for him into projectdox. I still cannot approve the project due to missing fire flow information. The rest of the review items have been satisfied.
Routing PW Grading-Hillside7/18/2018 7/23/2018 FAIL
DetailsMelissa Jannusch
Hi Jon,

Listed below are the revisions I am requesting prior to approval for hillside grading of your project on 123 W Crestline drive. Please coordinate with your designer to complete the revisions and give me a call if you have any questions about them.

1. Label and show the foundation drains and where the foundation drains will daylight.

2. Please add the following notes or similar to the grading and drainage plan

The grading plan shall include the following notes:
1. Subgrade shall be inspected by the project engineer responsible for the
geotechnical aspects of the project prior to installation of footings or
slabs.
2. Final grading shall be inspected by the site design engineer. Prior to
occupancy, the site design engineer shall evaluate all grading activities
for compliance with approved plans. A summary of this grading
evaluation and compliance determination shall be sent to the PDSD.
Any revisions to the approved grading plan must be approved by both
the site design engineer and the PDSD. If the grading differs from what
was originally approved, a revised grading plan shall be submitted and
approved before any modified grading is undertaken.


Best,

Melissa

Routing - FIRE7/18/20187/18/20187/19/2018 FAIL
DetailsTim Frost
Routing - PUBLIC WORKS7/18/2018 7/18/2018 PASS
DetailsMorgan Webb
Routing - Erosion and Sediment7/18/2018 7/18/2018 PASS
DetailsMichael Zawacki
Foothills home. RP needed. Site prep inspection required before any ground disturbing activity. OK to begin work inside home without site prep inspection.
Routing - MECHANICAL7/18/2018 7/18/2018 PASS
DetailsTroy James
Plans ACCEPTED BY PLAN TECH  7/18/2018 DONE
Intake Approval  7/18/2018 PASS
Application received  7/16/2018 DONE
Application submitted via PDS Online on Jul 16 2018 6:30PM