Third Notice | | 4/8/2020 | 5/7/2020 | | DONE |
|
|
|
mailed 5-8-2020
|
Second Notice | | 3/15/2020 | 4/3/2020 | | DONE |
|
|
|
mailed 4-6-2020
|
First Notice | 2/7/2020 | 2/7/2020 | 3/5/2020 | | DONE |
Brandon Shaw
|
|
|
mailed 3-6-20
|
BLD-Final | 2/6/2020 | 2/7/2020 | 2/7/2020 | P | PASS |
Brandon Shaw
|
|
|
Phil Phone #: ###-####
|
DOC - Permit Finaled | 2/7/2020 | 2/7/2020 | 2/7/2020 | P | PASS |
Brandon Shaw
|
|
|
|
FIRE-Final Inspection | 2/7/2020 | 2/7/2020 | 2/7/2020 | P | PASS |
Jim Page
|
|
|
Previously noted items have been corrected, fire sprinkler inspection is complete, fire alarm inspection is complete, hood suppression system inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection is complete, signature card not available at time of inspection.
|
Fees Due Hold | 1/10/2020 | | 2/6/2020 | | DONE |
Gabe Brenner
|
|
|
|
FIRE-Final Inspection | 1/8/2020 | 1/9/2020 | 1/9/2020 | A | FAIL |
Jim Page
|
|
|
Provide city approved drawings and small documents required for the life fire safety inspection. Addressing for corner lots needs to comply with section 505.3 of the BMC. A minimum of 18 inches of clearance from bottom of fire sprinkler head to top of storage is required per IFC and NFPA13.
Marvin Phone #: ###-####
|
BLD-Final | 11/14/2018 | 11/14/2018 | 11/14/2018 | P | PART |
Jim Storey
|
|
|
Devin Phone #: ###-#### Temp. Occ. is OK for two weeks, pending plumbing final... 480// remove door dead bolts.
|
Zoning Approval | 11/14/2018 | 11/14/2018 | 11/14/2018 | | DONE |
Andrea Tuning
|
|
|
|
BLD-Final | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | FAIL |
Brandon Shaw
|
|
|
Need Fire and PLM finals... Temp. Occ. is OK for two weeks, pending plumbing final...
|
FIRE-Final Inspection | 11/13/2018 | 11/13/2018 | 11/13/2018 | P | PART |
Troy Cobbley
|
|
|
A temporary for life safety is ok with Ron until the fire sprinkler and fire alarm modifications have been performed. Standard time length applies.
Devin Phone #: ###-####
|
Plan Reviewer's activity | | | 11/13/2018 | | DONE |
Julie Romig
|
|
|
Received confirmation from CDHD that no inspection is required. Email attached.
|
FIRE-Final Inspection | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | FAIL |
Troy Cobbley
|
|
|
Provide address, provide small documents, provide correct occupant load sign, provide exit discharge lights, provide verification fo hood suppression/cert. for new fryer, provide fire sprinkler protection for the attached room and cooler, re-mount fire extinguishers, install all ceilings, Restroom door hardware to meet ADA requirements, relocate sprinkler pendant at the new soda machine vertical chase. If the total amount of sprinkler heads exceeds 20 then a fire alarm/sprinkler monitoring system will be required.
Marvin Phone #: ###-####
|
BLD-Final | 11/8/2018 | 11/9/2018 | 11/9/2018 | A | NR |
Jim Storey
|
|
|
Marvin Phone #: ###-####
|
Zoning Approval | 11/9/2018 | 11/9/2018 | 11/9/2018 | | PASS |
Josh Wilson
|
|
|
|
BLD-Framing/Rough-in | 11/5/2018 | 11/6/2018 | 11/6/2018 | A | PASS |
Jim Storey
|
|
|
Marvin Phone #: ###-#### above ceilling ok
|
Issue PAID IN FULL permit | | | 10/22/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/22/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 7/23/2018 | 7/23/2018 | 10/19/2018 | | DONE |
Julie Romig
|
|
|
10/19 - 5th Rev - 1st Rev Comp - L3 Wendy's Remodel
|
Routing - PLAN CHECK | 10/16/2018 | | 10/19/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 10/19/2018 | | 10/19/2018 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/19/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/19/2018 | | DONE |
|
|
|
MET
NEED
REVISED VALUE (NEED COMPANY NAME ON 306 BLH)
MET
GC FORM
|
Routing - PLAN CHECK | 10/4/2018 | | 10/10/2018 | | FAIL |
Julie Romig
|
|
|
Corrections Required - structural design (drawings/calcs) to be updated to match construction of building.
|
Routing - Design Review | 9/7/2018 | | 9/10/2018 | | PASS |
Andrea Tuning
|
|
|
|
Routing - PLAN CHECK | 9/7/2018 | | 9/7/2018 | | FAIL |
Julie Romig
|
|
|
Corrections Required - Need structural calculations and attachment details for new canopies.
|
Routing - PLAN CHECK | 9/6/2018 | | 9/7/2018 | | FAIL |
Julie Romig
|
|
|
Corrections Required - Need structural calculations and attachment details for new canopies.
|
Routing - Design Review | 9/6/2018 | | 9/7/2018 | | FAIL |
Andrea Tuning
|
|
|
Provide weather protection at least 5-feet in average depth over all building entrances.
Provide weather protection at least 5-feet in depth along 60% of the south and west facing façades.
|
Routing - FIRE | 8/24/2018 | 8/24/2018 | 8/28/2018 | | PASS |
Erika Akin
|
|
|
Attached revised comments to case
|
Routing - Design Review | 8/24/2018 | | 8/27/2018 | | FAIL |
Andrea Tuning
|
|
|
Provide weather protection at least 5-feet in average depth over all building entrances.
Provide weather protection at least 5-feet in depth along 60% of the south and west facing façades.
|
Routing - PLAN CHECK | 8/24/2018 | | 8/24/2018 | | PASS |
Julie Romig
|
|
|
|
Route to Impact Fee Review | 8/20/2018 | 8/23/2018 | 8/21/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 7/23/2018 | | 8/20/2018 | | FAIL |
Julie Romig
|
|
|
|
1st review completed | | | 8/20/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 7/23/2018 | 7/23/2018 | 8/13/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing PW Environmental | 7/24/2018 | | 7/24/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - PLUMBING | 7/23/2018 | | 7/24/2018 | | PASS |
Bill VanDegrift
|
|
|
Verify all backflow assemblies have been certified.
|
Routing - Addressing | 7/23/2018 | | 7/24/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/23/2018 | | 7/24/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Design Review | 7/23/2018 | | 7/24/2018 | | FAIL |
Andrea Tuning
|
|
|
Fail - A Design Review application is required for any exterior building modifications.
|
Intake Approval | | | 7/20/2018 | | PASS |
|
|
|
|
Application received | | | 7/17/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 17 2018 11:08AM
|