Permit NumberBLD18-02545
StatusFinaled
Name ESI
Site Address 1180 S BROADWAY AVE
Project NameWendy's Broadway
Customer NumberBLD18-03733 EARLY START/DEMO
ePlanReviewYes
Description
(WENDY'S) Permit for the remodel of an existing Wendy's. Remodel is for the interior and exterior of the building with work to include: removal of exterior signage awning and installation of new corrugated metal siding over existing wall; new interior non-bearing partition walls; new dining room seating and condiment counters; new LED light fixtures; minor electrical, plumbing, and mechanical; and new interior finishes in compliance with Ch. 8 of the 2015 IBC. All work to be done per the approved plans and applicable codes and ordinances. This building is fully Fire Sprinklered with an approved Fire Alarm system. Any alterations or modifications to the building’s Fire Sprinkler or Fire Alarm system WILL REQUIRE A SEPARATE PERMIT and shall be installed per NFPA 13 and NFPA 72 as regulated by the Boise Fire Department. **JAR**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 4/8/20205/7/2020 DONE
mailed 5-8-2020
Second Notice 3/15/20204/3/2020 DONE
mailed 4-6-2020
First Notice2/7/20202/7/20203/5/2020 DONE
DetailsBrandon Shaw
mailed 3-6-20
BLD-Final2/6/20202/7/20202/7/2020PPASS
DetailsBrandon Shaw
Phil Phone #: ###-####
DOC - Permit Finaled2/7/20202/7/20202/7/2020PPASS
DetailsBrandon Shaw
FIRE-Final Inspection2/7/20202/7/20202/7/2020PPASS
DetailsJim Page
Previously noted items have been corrected, fire sprinkler inspection is complete, fire alarm inspection is complete, hood suppression system inspection is complete, fire extinguishers are placed with current inspection tags. Final life fire safety inspection is complete, signature card not available at time of inspection.
Fees Due Hold1/10/2020 2/6/2020 DONE
DetailsGabe Brenner
FIRE-Final Inspection1/8/20201/9/20201/9/2020AFAIL
DetailsJim Page
Provide city approved drawings and small documents required for the life fire safety inspection. Addressing for corner lots needs to comply with section 505.3 of the BMC. A minimum of 18 inches of clearance from bottom of fire sprinkler head to top of storage is required per IFC and NFPA13.

Marvin Phone #: ###-####
BLD-Final11/14/201811/14/201811/14/2018PPART
DetailsJim Storey
Devin Phone #: ###-#### Temp. Occ. is OK for two weeks, pending plumbing final... 480// remove door dead bolts.
Zoning Approval11/14/201811/14/201811/14/2018 DONE
DetailsAndrea Tuning
BLD-Final11/13/201811/13/201811/13/2018PFAIL
DetailsBrandon Shaw
Need Fire and PLM finals...
Temp. Occ. is OK for two weeks, pending plumbing final...
FIRE-Final Inspection11/13/201811/13/201811/13/2018PPART
DetailsTroy Cobbley
A temporary for life safety is ok with Ron until the fire sprinkler and fire alarm modifications have been performed. Standard time length applies.

Devin Phone #: ###-####
Plan Reviewer's activity  11/13/2018 DONE
DetailsJulie Romig
Received confirmation from CDHD that no inspection is required. Email attached.
FIRE-Final Inspection11/9/201811/9/201811/9/2018PFAIL
DetailsTroy Cobbley
Provide address, provide small documents, provide correct occupant load sign, provide exit discharge lights, provide verification fo hood suppression/cert. for new fryer, provide fire sprinkler protection for the attached room and cooler, re-mount fire extinguishers, install all ceilings, Restroom door hardware to meet ADA requirements, relocate sprinkler pendant at the new soda machine vertical chase. If the total amount of sprinkler heads exceeds 20 then a fire alarm/sprinkler monitoring system will be required.


Marvin Phone #: ###-####
BLD-Final11/8/201811/9/201811/9/2018ANR
DetailsJim Storey
Marvin Phone #: ###-####
Zoning Approval11/9/201811/9/201811/9/2018 PASS
DetailsJosh Wilson
BLD-Framing/Rough-in11/5/201811/6/201811/6/2018APASS
DetailsJim Storey
Marvin Phone #: ###-#### above ceilling ok
Issue PAID IN FULL permit  10/22/2018 DONE
Inspection Record Card- Bld  10/22/2018 DONE
Plan assigned to (JAR)7/23/20187/23/201810/19/2018 DONE
DetailsJulie Romig
10/19 - 5th Rev - 1st Rev Comp - L3 Wendy's Remodel
Routing - PLAN CHECK10/16/2018 10/19/2018 FAIL
DetailsJulie Romig
Routing - PLAN CHECK10/19/2018 10/19/2018 PASS
DetailsJulie Romig
PLANS/APPL TAKEN TO FRONT DESK  10/19/2018 DONE
Permit Ready to Issue  10/19/2018 DONE
MET
NEED
REVISED VALUE (NEED COMPANY NAME ON 306 BLH)

MET
GC FORM
Routing - PLAN CHECK10/4/2018 10/10/2018 FAIL
DetailsJulie Romig
Corrections Required - structural design (drawings/calcs) to be updated to match construction of building.
Routing - Design Review9/7/2018 9/10/2018 PASS
DetailsAndrea Tuning
Routing - PLAN CHECK9/7/2018 9/7/2018 FAIL
DetailsJulie Romig
Corrections Required - Need structural calculations and attachment details for new canopies.
Routing - PLAN CHECK9/6/2018 9/7/2018 FAIL
DetailsJulie Romig
Corrections Required - Need structural calculations and attachment details for new canopies.
Routing - Design Review9/6/2018 9/7/2018 FAIL
DetailsAndrea Tuning
Provide weather protection at least 5-feet in average depth over all building entrances.
Provide weather protection at least 5-feet in depth along 60% of the south and west facing façades.
Routing - FIRE8/24/20188/24/20188/28/2018 PASS
DetailsErika Akin
Attached revised comments to case
Routing - Design Review8/24/2018 8/27/2018 FAIL
DetailsAndrea Tuning
Provide weather protection at least 5-feet in average depth over all building entrances.
Provide weather protection at least 5-feet in depth along 60% of the south and west facing façades.
Routing - PLAN CHECK8/24/2018 8/24/2018 PASS
DetailsJulie Romig
Route to Impact Fee Review8/20/20188/23/20188/21/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK7/23/2018 8/20/2018 FAIL
DetailsJulie Romig
1st review completed  8/20/2018 FAIL
DetailsJulie Romig
Routing - FIRE7/23/20187/23/20188/13/2018 PASS
DetailsErika Akin
Attached comments to case
Routing PW Environmental7/24/2018 7/24/2018 PASS
DetailsRick Christenson
Routing - PLUMBING7/23/2018 7/24/2018 PASS
DetailsBill VanDegrift
Verify all backflow assemblies have been certified.
Routing - Addressing7/23/2018 7/24/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS7/23/2018 7/24/2018 PASS
DetailsMorgan Webb
Routing - Design Review7/23/2018 7/24/2018 FAIL
DetailsAndrea Tuning
Fail - A Design Review application is required for any exterior building modifications.
Intake Approval  7/20/2018 PASS
Application received  7/17/2018 DONE
Application submitted via PDS Online on Jul 17 2018 11:08AM