BLD-Final | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: ###-#### Inspection requested via web by Gus Brandon
|
DOC - Permit Finaled | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 3.75
|
BLD-Other | 4/4/2019 | 4/4/2019 | 4/4/2019 | P | PASS |
Brandon Shaw
|
|
|
Soffit Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Energy code compliance | 4/3/2019 | 4/4/2019 | 4/4/2019 | P | PASS |
Brandon Shaw
|
|
|
Insulation is on for am so possibly later in the day? Phone #: ###-#### Inspection requested via web by Gus Brandon
|
BLD-Framing/Rough-in | 4/2/2019 | 4/2/2019 | 4/2/2019 | P | PASS |
Brandon Shaw
|
|
|
OK to insulate...
|
BLD-Conference | 3/7/2019 | 3/7/2019 | 3/7/2019 | A | DEFR |
Brandon Shaw
|
|
|
Work ih progress...
|
BLD-Aging Inspection | 3/7/2019 | 3/7/2019 | 3/7/2019 | | CANC |
Brandon Shaw
|
|
|
|
BLD-Foundation | 10/23/2018 | 10/23/2018 | 10/23/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PART |
Mike Jordan
|
|
|
Edger Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/11/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/11/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 8/7/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 8/1/2018 | 8/1/2018 | 8/7/2018 | | DONE |
|
|
|
08/06 sfd L1 ePlan. 1st review complete, clarify mechanical equipment, update code year on structural calculations, beam B4 doesn't match plans and structural calculations
|
Routing - PLAN CHECK | 8/3/2018 | | 8/7/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/7/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 8/7/2018 | | DONE |
|
|
|
|
1st review completed | | | 8/3/2018 | | FAIL |
|
|
|
Mechanical equipment placement, code year on structural calculations, beam does not match plan and structural calculations
|
Routing - PLAN CHECK | 7/24/2018 | | 8/3/2018 | | FAIL |
Michael Hanson
|
|
|
See comments from JJN. MDH
|
Plan assigned to (M_H) | 7/24/2018 | | 8/1/2018 | | DEFR |
Michael Hanson
|
|
|
08/06 sfd L1 ePlan
|
Routing - MECHANICAL | 7/24/2018 | | 7/26/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 7/24/2018 | 7/27/2018 | 7/25/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Application received | | | 7/24/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 24 2018 9:03AM
|
Plans ACCEPTED BY PLAN TECH | | | 7/24/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 7/24/2018 | | DONE |
|
|
|
|
Intake Approval | | | 7/24/2018 | | PASS |
|
|
|
|
Routing - PLANNING | 7/24/2018 | | 7/24/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 7/24/2018 | | 7/24/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 7/24/2018 | | 7/24/2018 | | PASS |
Morgan Webb
|
|
|
|