First Notice | 3/13/2019 | 3/13/2019 | 4/16/2019 | | DONE |
Jim Sly
|
|
|
This permit finaled on the web by Dwayne Robinson
|
BLD-Final | 3/13/2019 | 3/13/2019 | 3/13/2019 | P | PASS |
Jim Sly
|
|
|
Michael with KMM-says work is done can''t get a hold of Id Tow Cnst needs final Phone #: ###-####
|
DOC - Permit Finaled | 3/13/2019 | 3/13/2019 | 3/13/2019 | P | PASS |
Jim Sly
|
|
|
|
Telephone call | | | 3/13/2019 | | DONE |
|
|
|
Michael from, KMM called said permit tech told him we need the 302 & 306 but Idaho Tower Construction alread filled them out. They fired KMM out to do work and now the permit is ready for a final. I scheduled CAN
|
Inspection Record Card- Bld | | | 12/17/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 12/17/2018 | | DONE |
|
|
|
|
Telephone call | | | 12/17/2018 | | DONE |
|
|
|
emailed kurt@idahotowerconstruction.com;dwayne@idahotowerconstruction.com;matt@idahotowerconstruction.com asked if one of them could sign and send back building permit
|
Plan assigned to (M_H) | 12/3/2018 | | 12/14/2018 | | DONE |
Michael Hanson
|
|
|
12/14 #518 L2 ePlan. T-Mobile Antenna
|
Routing - PLAN CHECK | 12/3/2018 | | 12/14/2018 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 12/14/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 12/14/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 12/14/2018 | | DONE |
|
|
|
NEED
GC FORM
REVISED VALUE (FROM THE GC. APPLICANT TRIED TO SEND IN)
|
Routing - PLANNING | 12/3/2018 | | 12/4/2018 | | PASS |
Nicolette Womack
|
|
|
|
Intake Approval | | | 12/3/2018 | | PASS |
Joe Bruce
|
|
|
|
Intake Approval | | | 8/23/2018 | | FAIL |
Joe Bruce
|
|
|
Please submit the following information that was not provided from the last the last pre-screen review:
2. Missing 304 form completed and signed - Form needs to be signed by the Owner.
5. Missing structural engineering stamped and signed by an Idaho registered engineer
Thank You,
Joe Bruce
Boise city plan review
###-####
|
Intake Approval | | | 8/7/2018 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. Missing 518 Checklist completed and signed
2. Missing 304 form completed and signed
3. Drawings sheets must be individually uploaded
4. Drawings sheets must be min. 18"x24" sheet size
5. Missing structural engineering stamped and signed by an Idaho registered engineering
6. Missing mounting bracket details
7. Missing planning and zoning approval letter.
|
Application received | | | 7/24/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 24 2018 10:49AM
|