Third Notice | | 2/11/2020 | 2/14/2020 | | DONE |
|
|
|
This permit finaled on the web by Jeremy Barber
|
Second Notice | | 1/9/2020 | 2/6/2020 | | DONE |
|
|
|
MAILED 2-7-20
|
First Notice | 12/11/2019 | 12/11/2019 | 12/30/2019 | | DONE |
Mike Jordan
|
|
|
mailed 1-1-20
|
BLD-Final | 12/10/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####
|
DOC - Permit Finaled | 12/11/2019 | 12/11/2019 | 12/11/2019 | P | PASS |
Mike Jordan
|
|
|
|
FIRE-Final Inspection | 12/10/2019 | 12/11/2019 | 12/11/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Jason - ###-####
|
FIRE-Conference | 12/6/2019 | 12/6/2019 | 12/6/2019 | P | DONE |
Troy Cobbley
|
|
|
Jason and I went over life safety requirements for the remaining phase of work for this project. Need verification that exit discharge lights will not be required out of the two remaining marked exits.
|
BLD-Ceiling Grid Inspection | 11/20/2019 | 11/20/2019 | 11/20/2019 | P | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####
|
CHANGE STATUS TO (ISS) | | | 10/15/2019 | | DONE |
|
|
|
plan mod fee paid change to ISS status
|
Routing - PLAN CHECK | 10/10/2019 | | 10/14/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod review approved
|
Plan Reviewer's activity | | | 10/14/2019 | | PASS |
|
|
|
Plan mod review approved
|
Permit Ready to Issue | | | 10/14/2019 | | DONE |
|
|
|
plan mod
|
Plan assigned to (CJW) | 10/8/2019 | | 10/14/2019 | | PASS |
Gemma Flores
|
|
|
3rd plan mod CDHC (at permits desk after plan intake review)
|
BLD-Framing/Rough-in | 10/11/2019 | 10/11/2019 | 10/11/2019 | P | PASS |
Brandon Shaw
|
|
|
Final phase...
|
Routing - PLAN CHECK | 10/8/2019 | | 10/10/2019 | | PASS |
Carl Westfall
|
|
|
3rd plan mod plan intake review approved
|
Plan Modification Accepted | | | 10/8/2019 | | DONE |
|
|
|
3rd plan mod submitted by Richard Carlos. Adding a wall between Office - PWS Brent 357 and Hallway 361. Sheet A2.01, A2.11b, A9.01 and D2.02
|
Plan assigned to (CJW) | 10/3/2019 | 10/3/2019 | 10/7/2019 | | PASS |
Carl Westfall
|
|
|
plan mod - Central District Health Department (plan intake approved)
|
Plan Reviewer's activity | | | 10/7/2019 | | PASS |
|
|
|
2nd plan mod approved
|
Permit Ready to Issue | | | 10/7/2019 | | DONE |
|
|
|
PLAN MOD
|
Print Occupancy Form | | | 10/7/2019 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 10/3/2019 | | 10/3/2019 | | PASS |
Carl Westfall
|
|
|
Plan intake review
|
Plan Modification Accepted | | | 10/3/2019 | | DONE |
|
|
|
Plan mod-CURRENTLY ELECTRICAL ROOM 150 IS OPEN TO HALLWAY 156. WE ARE MODIFYING THIS SPACE BY ENCLOSING IT WITH A WALL AND DOOR. WE ARE ALSO ADDING A LIGHT FIXTURE AND SWITCH TO ELECTRICAL ROOM 150-sheets A2.01, A2.11a, A7.01, A9.01, E0.02, AND E1.11A-no valuation fees will change-assigned to Carl W
|
BLD-Final | 8/16/2019 | 8/19/2019 | 8/19/2019 | A | PART |
Mike Jordan
|
|
|
CAMERON Phone #: ###-####. ,Phase 2 ok to occupy.
|
BLD-Final | 8/14/2019 | 8/16/2019 | 8/16/2019 | P | CANC |
Mike Jordan
|
|
|
Cameron Phone #: ###-####
|
FIRE-Final Inspection | 8/14/2019 | 8/15/2019 | 8/15/2019 | A | FAIL |
Troy Cobbley
|
|
|
This life safety inspection was for Phase 2. The phase 2 fire sprinkler and fire alarm work needs to be completed. I noted exit signs missing and one area that needs the exit sign repaired and emergency lighting provided.. Also Jason agreed that an old aluminum door with a deadbolt will be removed.
Jason Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/16/2019 | 7/17/2019 | 7/17/2019 | A | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 7/2/2019 | 7/3/2019 | 7/3/2019 | P | PART |
Mike Jordan
|
|
|
Cameron Phone #: ###-####-please call prior to meet. Ceiling grid in phase 2 ok pending MEP's rough in inspections.
|
CHANGE STATUS TO (ISS) | | | 7/2/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 7/2/2019 | | DONE |
|
|
|
plan mod
|
Plan assigned to (CJW) | 5/21/2019 | 5/21/2019 | 5/29/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod - CDHD new mop sink (routed to staff)
|
Plan Reviewer's activity | | | 5/29/2019 | | PASS |
|
|
|
Plan mod approved
|
Permit Ready to Issue | | | 5/29/2019 | | DONE |
|
|
|
plan mod so please do not re-issue
5-30-19 Plan mod fees paid **SEWER FEES STILL DUE**
|
Routing - MECHANICAL | 5/22/2019 | | 5/28/2019 | | PASS |
Troy James
|
|
|
Exhaust fan
|
Routing PW Sewer Rating | 5/22/2019 | | 5/23/2019 | | PASS |
Morgan Webb
|
|
|
Added mop sink
|
Routing - PLUMBING | 5/22/2019 | | 5/23/2019 | | PASS |
Daryl Spivey
|
|
|
new mop sink-install per ISPC
|
Routing - PLAN CHECK | 5/21/2019 | | 5/22/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod plan intake review approved. Sent to permits desk.
|
Routing - PLAN CHECK | 5/22/2019 | | 5/22/2019 | | PASS |
Carl Westfall
|
|
|
Plan mod review approved
|
Plan resubmittals received | | | 5/21/2019 | | DONE |
|
|
|
convert half of existing storage room 130 into a janitor's closet
|
BLD-Framing/Rough-in | 5/16/2019 | 5/16/2019 | 5/16/2019 | P | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####. Interior steel stud framed walls only for phase 2 ok.
|
BLD-Framing/Rough-in | 5/14/2019 | 5/14/2019 | 5/14/2019 | P | NR |
Mike Jordan
|
|
|
Jason Phone #: ###-####. Needs plumbing and electrical rough in inspections first.
|
BLD-Final | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | PART |
Mike Jordan
|
|
|
jason Phone #: ###-####. Ok to occupy phase 1.
|
FIRE-Final Inspection | 3/27/2019 | 3/27/2019 | 3/27/2019 | P | PART |
Troy Cobbley
|
|
|
Life safety passed for the phase 1 area of work.
jason Phone #: ###-####
|
BLD-Final | 3/26/2019 | 3/26/2019 | 3/26/2019 | P | NR |
Mike Jordan
|
|
|
Jason Phone #: ###-####
|
FIRE-Final Inspection | 3/25/2019 | 3/26/2019 | 3/26/2019 | A | FAIL |
Troy Cobbley
|
|
|
Need panic hardware as shown on the approved drawings, need occupant load signs, need addtional emergency lights/exit discharge lights as discussed.
Jason Phone #: ###-####
|
FIRE-Conference | 3/18/2019 | 3/18/2019 | 3/18/2019 | P | DONE |
Troy Cobbley
|
|
|
Jason and I spoke about fire sprinkler and fire alarm isuues that need addressed prior to a phase 1 approval.
|
BLD-Ceiling Grid Inspection | 1/28/2019 | 1/28/2019 | 1/28/2019 | P | PART |
Mike Jordan
|
|
|
jason Phone #: ###-####..Ceiling grid for phase 1 ok pending MEP's.
|
BLD-Framing/Rough-in | 1/10/2019 | 1/11/2019 | 1/11/2019 | A | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####. Hardlids and soffits for phase 1 area A. Pending fire sprinkler rough in inspection.
|
BLD-Framing/Rough-in | 12/17/2018 | 12/18/2018 | 12/18/2018 | P | PASS |
Mike Jordan
|
|
|
Jason Phone #: ###-####. INterior stel stud framed walls for phase 1. Grids 3 to 8.
|
Issue PAID IN FULL permit | | | 11/14/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 11/14/2018 | | DONE |
|
|
|
|
Routing - FIRE | 10/11/2018 | 10/15/2018 | 10/15/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Plan assigned to (CJW) | 8/15/2018 | 8/15/2018 | 10/15/2018 | | PASS |
Carl Westfall
|
|
|
(2nd done) 08/30/18 (L3 - 15 days) (ePlan - 76 sheet) CDHD Office
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/15/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/15/2018 | | DONE |
|
|
|
NEED- all met
GC FORM-met
REVISED VALUE
|
Routing - PLAN CHECK | 10/10/2018 | | 10/11/2018 | | PASS |
Carl Westfall
|
|
|
|
Plan resubmittals received | | | 10/10/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 9/24/2018 | 9/27/2018 | 9/25/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 8/15/2018 | | 9/24/2018 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
1st review completed | | | 9/24/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 9/24/2018 | | DONE |
|
|
|
|
Routing - FIRE | 8/15/2018 | 8/15/2018 | 9/10/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and emailed architect
|
Routing Off Site - STRUCTURAL | 8/15/2018 | | 8/27/2018 | | PASS |
Carl Westfall
|
|
|
Chris Holladay (AHJ)
|
Routing - MECHANICAL | 8/15/2018 | | 8/20/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 8/15/2018 | | 8/20/2018 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - PUBLIC WORKS | 8/15/2018 | | 8/17/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 8/15/2018 | | 8/16/2018 | | PASS |
Doug Chausow
|
|
|
|
Intake Approval | | | 8/10/2018 | | PASS |
|
|
|
|
Application received | | | 7/25/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 25 2018 7:37AM
|