BLD-Other | 8/4/2020 | 8/5/2020 | 8/5/2020 | P | PART |
Jim Storey
|
|
|
Complaint of new roof extending over property line. c/n posted no plan on site. pending call back to resolve what was aproved by plan review.
|
BLD-Aging Inspection | 4/16/2020 | 4/16/2020 | 4/16/2020 | | PASS |
Jim Storey
|
|
|
Expires: 06/01/20
|
BLD-Aging Inspection | 12/4/2019 | 12/4/2019 | 12/4/2019 | | PASS |
Jim Storey
|
|
|
|
Routing Walk-In (BLD) | 11/27/2019 | 11/27/2019 | 11/27/2019 | P | PASS |
Josh Bogle
|
|
|
|
BLD-Conference | 10/11/2019 | 10/14/2019 | 10/14/2019 | A | NH |
Dave Hannah
|
|
|
Josh Phone #: ###-#### no one on site no one at phone #
|
BLD-Footing | 7/22/2019 | 7/23/2019 | 7/23/2019 | A | PASS |
Jim Storey
|
|
|
Jesse Phone #: ###-####
|
Routing Walk-In (BLD) | 7/23/2019 | 7/23/2019 | 7/23/2019 | P | FAIL |
Josh Bogle
|
|
|
Discussed plan modification requirements with applicant. Informed to have new plans drawn up showing the changes and modifications. Resubmittal required.
|
OVERRIDE | | | 4/5/2019 | | |
|
|
|
|
Telephone call | | | 4/5/2019 | | DONE |
|
|
|
tried calling Josh to let know permit is ready but mail box is full-will email
|
Issue PAID IN FULL permit | | | 4/5/2019 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 4/5/2019 | | DONE |
|
|
|
plan mod please do not re issue
NEED RP
|
Routing Walk-In (BLD) | 4/4/2019 | 4/4/2019 | 4/4/2019 | P | DONE |
Josh Bogle
|
|
|
dropped off plans
|
Plan assigned to (JAB) Josh | 3/29/2019 | 3/29/2019 | 4/4/2019 | | PASS |
Josh Bogle
|
|
|
4/4 addition, paper - 1st done
|
Routing - PLAN CHECK | 4/4/2019 | | 4/4/2019 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 4/4/2019 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 4/4/2019 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 4/4/2019 | | DONE |
Josh Bogle
|
|
|
ESC yes - Energy yes
|
Routing - PLAN CHECK | 3/29/2019 | | 4/3/2019 | | FAIL |
Josh Bogle
|
|
|
joists don't span, missing footings
|
Routing - MECHANICAL | 3/29/2019 | | 4/1/2019 | | PASS |
Troy James
|
|
|
|
Routing Walk-In (Zoning) | 3/29/2019 | 3/29/2019 | 3/29/2019 | P | PASS |
Katelyn Menuge
|
|
|
DRH18-00486
|
Plan assigned to (JAB) Josh | 3/29/2019 | 3/29/2019 | 3/29/2019 | | DONE |
Josh Bogle
|
|
|
took in as a level two - routed to mechanical
|
Plan Modification Accepted | | | 3/29/2019 | | DONE |
|
|
|
submit for full remodel-
|
Routing Walk-In (BLD) | 7/25/2018 | 7/25/2018 | 7/25/2018 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 7/25/2018 | | 7/25/2018 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 7/25/2018 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 7/25/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 7/25/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 7/25/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 7/25/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 7/25/2018 | | DONE |
|
|
|
|
Application received | | 7/25/2018 | | | |
|
|
|
|