BLD-Final | 9/24/2018 | 9/24/2018 | 9/24/2018 | P | PASS |
Dave Hannah
|
|
|
Julie Phone #: ###-####
|
BLD-Final | 9/13/2018 | 9/14/2018 | 9/14/2018 | P | NR |
Mike Jordan
|
|
|
Please ahead for access - Julie Phone #: ###-####. Nees eelctrical final and install door hardware.
|
FIRE-Final Inspection | 9/13/2018 | 9/14/2018 | 9/14/2018 | A | PASS |
Mike Jordan
|
|
|
Please ahead for access - Julie Phone #: ###-####. No fire sprinkler or alarm mods were done. building inspector to verify door hardware on final.
|
BLD-Framing/Rough-in | 8/15/2018 | 8/16/2018 | 8/16/2018 | A | PART |
Tony Young
|
|
|
Julie Phone #: ###-####,, walls ok,, 3 west/south
|
Issue PAID IN FULL permit | | | 8/14/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 8/14/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/8/2018 | | 8/10/2018 | | PASS |
Michael Hanson
|
|
|
|
Plan assigned to (M_H) | 8/9/2018 | | 8/10/2018 | | DONE |
Michael Hanson
|
|
|
08/14 518 L1 ePlan Boise Cascade Third Floor
|
1st review completed | | | 8/10/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/10/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 8/10/2018 | | DONE |
|
|
|
NEED
GC FORM
REVISED VALUE
|
Plan assigned to (JG) | 8/8/2018 | 8/8/2018 | 8/9/2018 | | DEFR |
Javier Guzman
|
|
|
8/14 L1 Boise Cascade Third Floor ePlan
|
Intake Approval | | | 8/8/2018 | | PASS |
Javier Guzman
|
|
|
|
Application received | | | 7/26/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 26 2018 9:08AM
|