First Notice | | 12/31/2018 | 1/5/2019 | | DONE |
|
|
|
This permit finaled on the web by Michael McHargue
|
Print Occupancy Form | | | 12/21/2018 | | DONE |
|
|
|
|
Permanent Occupancy | | | 12/21/2018 | | DONE |
|
|
|
|
BLD-Final | 12/19/2018 | 12/20/2018 | 12/20/2018 | A | PASS |
Mike Jordan
|
|
|
Adam Phone #: ###-####. ADa mirrors have been provided. Ok for perm occ.
|
CHANGE STATUS TO (ISS) | | | 12/19/2018 | | DONE |
|
|
|
plan mod
|
Permit Ready to Issue | | | 12/6/2018 | | DONE |
|
|
|
PLAN MOD DO NOT ISSUE AGAIN
|
Plan assigned to (JAR) | 12/3/2018 | 12/3/2018 | 12/5/2018 | | DONE |
Julie Romig
|
|
|
*12/06 - Plan Mod - Nancy Jane Salon Exit Lighting
|
Routing - PLAN CHECK | 12/5/2018 | | 12/5/2018 | | PASS |
Julie Romig
|
|
|
Plan Mod
|
BLD-Final | 12/3/2018 | 12/4/2018 | 12/4/2018 | P | PART |
Mike Jordan
|
|
|
Adam Phone #: ###-####. Ok for temp occ. Needs to provide mirors in ADA restrooms with reflective surface at 40 inches.
|
FIRE-Final Inspection | 12/3/2018 | 12/3/2018 | 12/3/2018 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Adam Phone #: ###-####
|
Plan Modification Accepted | | | 12/3/2018 | | DONE |
|
|
|
emergency lights shown on shee A-1.2 change to match E2.0L
|
FIRE-Final Inspection | 11/30/2018 | 11/30/2018 | 11/30/2018 | P | FAIL |
Troy Cobbley
|
|
|
Need the additional address for the corner lot as discussed, need the emergency lighting corrected, need all doors and hardware installed (pocket doors to meet ADA), test the duct smoke detectors
Adam Phone #: ###-####
|
BLD-Ceiling Grid Inspection | 11/28/2018 | 11/28/2018 | 11/28/2018 | P | PASS |
Mike Jordan
|
|
|
Adam Phone #: ###-####
|
BLD-Energy code compliance | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PART |
Mike Jordan
|
|
|
Adam Phone #: ###-#### Inspection requested via web by Adam Joslin. Fire blocking has been completed. Ok to cover pending mech. rough in inspection.
|
BLD-Framing/Rough-in | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | PART |
Mike Jordan
|
|
|
Adam Phone #: ###-####. Ok to insulate. Need mech. rough in inspection. Complete all fire blocking
|
Issue PAID IN FULL permit | | | 10/10/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 10/10/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 8/10/2018 | 8/10/2018 | 10/5/2018 | | DONE |
Julie Romig
|
|
|
1st Rev Comp - 2nd Comp - L3 Nancy Jane Salon
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/5/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/5/2018 | | DONE |
|
|
|
Email permit to: Michael McHargue, mike@prusikbuilt.com
Need
GC Form - met
Revised Cert Value - met
***CLOSE OUT BLD18-03076 WHEN ISSUED, verify all trades moved
|
Routing - MECHANICAL | 10/3/2018 | | 10/3/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 9/18/2018 | | 9/21/2018 | | PASS |
Julie Romig
|
|
|
|
Routing - MECHANICAL | 9/18/2018 | | 9/21/2018 | | FAIL |
Troy James
|
|
|
Called mechanical engineer and asked why comments have not been resolved. The owner wants to install a recirculating table that is not approved.
|
Routing - Design Review | 9/18/2018 | | 9/18/2018 | | PASS |
Katelyn Menuge
|
|
|
|
Route to Impact Fee Review | 9/14/2018 | 9/17/2018 | 9/17/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 9/14/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 8/10/2018 | | 9/14/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 8/10/2018 | 8/10/2018 | 9/7/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing - PLANNING | 8/10/2018 | | 9/7/2018 | | FAIL |
Katelyn Menuge
|
|
|
Show that the top of the rooftop equipment will be lower than the top of parapet.
Window/door changes also require design review approval prior to sign-off.
|
Routing - MECHANICAL | 8/10/2018 | | 8/13/2018 | | FAIL |
Troy James
|
|
|
|
Routing - PLUMBING | 8/10/2018 | | 8/10/2018 | | PASS |
Bill VanDegrift
|
|
|
See redline markups and install per ISPC.
|
Routing - Addressing | 8/10/2018 | | 8/10/2018 | | PASS |
Doug Chausow
|
|
|
Ste 110
|
Routing - PUBLIC WORKS | 8/10/2018 | | 8/10/2018 | | PASS |
Morgan Webb
|
|
|
|
Plan Reviewer's activity | | | 8/10/2018 | | DONE |
|
|
|
As this is a first time buildout of this space provide verification of ACHD fees due. Verification is required prior to the issuance of a building permit.
|
Intake Approval | | | 8/7/2018 | | PASS |
|
|
|
|
Intake Approval | | | 8/1/2018 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. Must create vanilla shell space building permit when dividing existing vanilla shell. NEW VANILLA SHELL MUST BE CREATED FOR THE LEFT OVER SHELL SPACE SINCE A T.I. REDUCING THE ORIGINAL VANILLA SHELL AREA.
2. All sheets must be stamped, signed, and dated by an Idaho state design professional. Missing on electrical sheets. - COMPLETED
3. Missing site specific fire flow letter - COMPLETED
4. Structural engineering and/or plans required for new roof top mechanical units. MECHANICAL INFORMATION NOT INCLUDED IN BLD17-03282, WITHOUT WE CAN NOT VERIFY STRUCTURAL.
|
Intake Approval | | | 7/31/2018 | | FAIL |
Michael Hanson
|
|
|
This permit has failed prescreen due to the following:
1. Must create vanilla shell space building permit when dividing existing vanilla shell.
2. All sheets must be stamped, signed, and dated by an Idaho state design professional. Missing on electrical sheets.
3. Missing site specific fire flow letter
4. Structural engineering and/or plans required for new roof top mechanical units.
|
Application received | | | 7/26/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 26 2018 4:55PM
|