Case Summary (BLD) | | | 4/18/2019 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 4/18/2019 | | DONE |
|
|
|
|
BLD-Final | 2/7/2019 | 2/7/2019 | 2/7/2019 | P | DONE |
Tony Young
|
|
|
Kirt- please call an hour before Phone #: ###-####-PLM not finaled yet
|
DOC - Permit Finaled | 2/7/2019 | 2/7/2019 | 2/7/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 2/6/2019 | 2/7/2019 | 2/7/2019 | A | PEND |
Tony Young
|
|
|
Kirt- please call an hour before Phone #: ###-####-PLM not finaled yet
|
BLD-Energy code compliance | 10/9/2018 | 10/9/2018 | 10/9/2018 | P | PASS |
Tony Young
|
|
|
Curt Phone #: ###-####
|
BLD-Framing/Rough-in | 10/4/2018 | 10/5/2018 | 10/5/2018 | A | NH |
Jim Sly
|
|
|
Curt Phone #: ###-#### Called....No call back......Left note No access.
|
BLD-Framing/Rough-in | 10/2/2018 | 10/3/2018 | 10/3/2018 | A | PASS |
Jim Storey
|
|
|
alan Phone #: ###-#### per the reviewed plan pass
|
BLD-Framing/Rough-in | 10/1/2018 | 10/2/2018 | 10/2/2018 | A | PART |
Mike Jordan
|
|
|
Call for access - Alan Phone #: ###-####. No call back for access. Voice mail full, could not leave message. inspected garage only. Possibly needs portal frme?? No acess to plans.
|
BLD-Footing | 9/24/2018 | 9/24/2018 | 9/24/2018 | P | PASS |
Dave Hannah
|
|
|
Hutton Phone #: ###-####
|
BLD-Framing/Rough-in | 9/14/2018 | 9/14/2018 | 9/17/2018 | P | PART |
Dave Hannah
|
|
|
Please call ahead for access, 1hr - Kurt Phone #: ###-#### ok to insulate needs point load tras in crawl space pads and post
|
Routing Walk-In (BLD) | 9/5/2018 | 9/5/2018 | 9/5/2018 | A | PASS |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 9/5/2018 | | 9/5/2018 | | PASS |
Michael Hanson
|
|
|
Plan mod for 320 sqft garage
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/5/2018 | | DONE |
Michael Hanson
|
|
|
|
Inspection Record Card- Bld | | | 9/5/2018 | | DONE |
Michael Hanson
|
|
|
|
Case Summary (BLD) | | | 9/5/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 9/5/2018 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 9/5/2018 | | DONE |
|
|
|
plan mod
|
Routing Walk-In (Zoning) | 8/27/2018 | 8/27/2018 | 8/27/2018 | P | DONE |
Sue Cummings
|
|
|
Add garage to scope
|
Routing Walk-In (BLD) | 8/27/2018 | 8/27/2018 | 8/27/2018 | P | PASS |
Josh Bogle
|
|
|
had a nice chat
|
Routing Walk-In (BLD) | 8/21/2018 | 8/21/2018 | 8/21/2018 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 8/21/2018 | | 8/21/2018 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 8/21/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 8/21/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/21/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 8/21/2018 | | DONE |
|
|
|
permit not including new garage so deducted $15000.00 on total valuation. if they do a plan mod, they'll put the value of the garage at that time
|
Issue PAID IN FULL permit | | | 8/21/2018 | | DONE |
|
|
|
|
Routing Walk-In (Zoning) | 8/3/2018 | 8/3/2018 | 8/3/2018 | P | PASS |
Jeff Lowe
|
|
|
|
Routing Walk-In (BLD) | 8/3/2018 | 8/3/2018 | 8/3/2018 | P | FAIL |
Josh Bogle
|
|
|
needed structural info
|
Routing - PLAN CHECK | 8/3/2018 | | 8/3/2018 | | FAIL |
Josh Bogle
|
|
|
|
1st review completed | | | 8/3/2018 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | | 7/26/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 26 2018 10:44PM
|