Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD18-02725
StatusFinaled
Name DOUG LASHER CONSTRUCTION
Site Address 2475 S APPLE ST Unit: 103
Project NameOsteoStrong - Suite #103
Customer Number 
ePlanReviewYes
Description
(OSTEO STRONG- CARRIAGE CROSSING-BLDG #2 - SUITE #103) Permit is to remodel an existing 1,348 sq. ft. tenant space for business use. Approval is contingent upon adhering to the approved plans on file and plan review report. Work to include: construction of interior non-bearing walls to create a break room, (2) closets, a massage room, a consult area, and a reception/waiting area, millwork, select new gypsum ceiling soffit, select new light fixtures, electrical work and interior finishes in compliance with Ch. 8 of the current IBC. This building is Not Fire Sprinklered. **JG**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 1/12/20191/16/2019 DONE
This permit finaled on the web by bryan murdoch
Third Notice 12/18/20181/7/2019 DONE
Mailed 1-11-19
Second Notice 11/16/201812/13/2018 DONE
mailed 12-14
First Notice 11/9/201811/6/2018 DONE
mailed 11-12
BLD-Final10/30/201810/30/201810/30/2018PPASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by bryan murdoch
FIRE-Final Inspection10/30/201810/30/201810/30/2018APASS
DetailsJim Page
No fire sprinklers, no fire alarms, fire extinguisher is placed with a current inspection tag. Final life fire safety inspection for area of work complete.

Fire/life safety Phone #: ###-#### Inspection requested via web by bryan murdoch
Permanent Occupancy  10/30/2018 DONE
Print Occupancy Form  10/29/2018 DONE
BLD-Framing/Rough-in9/17/20189/18/20189/18/2018PPASS
DetailsJim Storey
Phone #: ###-#### Inspection requested via web by bryan murdoch
Issue PAID IN FULL permit  9/7/2018 DONE
Print Occupancy Form  9/7/2018 DONE
Plan assigned to (JG)8/9/20188/9/20189/4/2018 PASS
DetailsJavier Guzman
1st rev comp, 8/27 L3 Osteo strong ePlan*
Routing - PLAN CHECK9/4/2018 9/4/2018 PASS
DetailsJavier Guzman
PLANS/APPL TAKEN TO FRONT DESK  9/4/2018 DONE
Permit Ready to Issue  9/4/2018 DONE
Need
GC Form
Revised Cert of Value
Route to Impact Fee Review8/29/20189/1/20188/30/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
1st review completed  8/29/2018 FAIL
DetailsJavier Guzman
Routing - FIRE8/9/20188/9/20188/28/2018 PASS
DetailsErika Akin
Attached comments to case
Routing - PLAN CHECK8/9/2018 8/27/2018 FAIL
DetailsJavier Guzman
Routing - Addressing8/9/2018 8/10/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS8/9/2018 8/10/2018 PASS
DetailsMorgan Webb
Intake Approval  8/7/2018 PASS
Intake Approval  8/1/2018 FAIL
DetailsMichael Hanson
This permit has failed prescreen due to the following:
1. Provide existing door hardware information
2. Provide lighting information - COMcheck lighting plan and lighting fixture schedule
3. Provide mechanical note that states "no change to mechanical systems" or if new provide mechanical plans
Application received  7/31/2018 DONE
Application submitted via PDS Online on Jul 31 2018 11:06AM