BLD-Final | 8/20/2018 | 8/23/2018 | 8/23/2018 | P | PASS |
Jim Storey
|
|
|
Dave Phone #: ###-####
|
FIRE-Final Inspection | 8/20/2018 | 8/23/2018 | 8/23/2018 | A | PASS |
Jim Page
|
|
|
No fire sprinkler modifications (Fire sprinkler cover warehouse only, no the office area on the northside of building), fire extinguishers are placed with current inspection tags, dust collection system is multiple portable units, paint booth fire suppression system has been inspected (FIR17-00330). Final life fire safety inspection complete.
Dave Phone #: ###-####
|
Permanent Occupancy | | | 8/23/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/20/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 8/20/2018 | | DONE |
|
|
|
|
Plan assigned to (CDM) | 8/3/2018 | 8/3/2018 | 8/16/2018 | | PASS |
Carl D Madsen
|
|
|
08/17 Euro Tech Cabinets L-2
|
Routing - FIRE | 8/3/2018 | 8/3/2018 | 8/16/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 8/16/2018 | | DONE |
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/16/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/16/2018 | | DONE |
|
|
|
met
No GC or revised value required, no work authorized under this permit.
|
Routing - PLAN CHECK | 8/3/2018 | | 8/11/2018 | | PASS |
Carl D Madsen
|
|
|
|
Routing - Addressing | 8/3/2018 | | 8/3/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/3/2018 | | 8/3/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 8/3/2018 | | PASS |
|
|
|
|
Application received | | | 7/31/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Jul 31 2018 4:09PM
|