BLD-Final | 10/19/2018 | 10/22/2018 | 10/22/2018 | A | PASS |
Dave Hannah
|
|
|
This is the final bldg inspection for Terry Reilly Channel Letter Set) Call Aaron for Questions Phone #: ###-#### Phone #: ###-#### Inspection requested via web by Dana Vance
|
DOC - Permit Finaled | 10/22/2018 | 10/22/2018 | 10/22/2018 | P | PASS |
Dave Hannah
|
|
|
|
Plan assigned to (M_H) | 8/3/2018 | | 8/8/2018 | | DONE |
Michael Hanson
|
|
|
CSN18-00187
|
Intake Approval | | | 8/8/2018 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 8/8/2018 | | DONE |
Michael Hanson
|
|
|
|
Routing - PLAN CHECK | 8/8/2018 | | 8/8/2018 | | PASS |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/8/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 8/8/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/8/2018 | | DONE |
|
|
|
|
Application received | | | 8/1/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 1 2018 4:53PM
|
First Notice | 10/22/2018 | 10/22/2018 | | | |
Dave Hannah
|
|
|
|