BLD-Final | 1/2/2020 | 1/2/2020 | 1/2/2020 | P | DONE |
Tony Young
|
|
|
larry Phone #: ###-####
|
BLD-Blower Door Test Results | 1/2/2020 | 1/2/2020 | 1/2/2020 | P | DONE |
Tony Young
|
|
|
larry Phone #: ###-####// 4.2
|
DOC - Permit Finaled | 1/2/2020 | 1/2/2020 | 1/2/2020 | P | PASS |
Tony Young
|
|
|
c of o issued
|
BLD-Aging Inspection | 11/13/2019 | 11/13/2019 | 11/20/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Final | 11/18/2019 | 11/18/2019 | 11/18/2019 | P | NR |
Tony Young
|
|
|
Larry Phone #: ###-####,, needs blower door test results,, fall protection on 2nd floor bedroom windows
|
BLD-Aging Inspection | 11/12/2019 | 11/12/2019 | 11/13/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Energy code compliance | 7/1/2019 | 7/1/2019 | 7/1/2019 | P | PASS |
Tony Young
|
|
|
Larry Phone #: ###-####
|
BLD-Framing/Rough-in | 6/27/2019 | 6/27/2019 | 6/27/2019 | P | PART |
Tony Young
|
|
|
Larry Phone #: ###-####,, corrections,, ok to insulate
|
BLD-Wall Bracing | 6/12/2019 | 6/12/2019 | 6/12/2019 | P | PART |
Brandon Shaw
|
|
|
Work in progress... Blocking for interior shear to be complete before framing rough-in...
|
BLD-Aging Inspection | 4/25/2019 | 4/25/2019 | 4/30/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 4/24/2019 | 4/24/2019 | 4/26/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Foundation | 12/11/2018 | 12/11/2018 | 12/11/2018 | P | PART |
Tony Young
|
|
|
victor,, work in progress,, ok
|
BLD-Footing | 12/10/2018 | 12/10/2018 | 12/10/2018 | P | PASS |
Tony Young
|
|
|
Victor Phone #: ###-####
|
BLD-Footing | 12/3/2018 | 12/4/2018 | 12/4/2018 | A | FAIL |
Tony Young
|
|
|
Victor Phone #: ###-####,, ground is frozen
|
BLD-Foundation | 10/30/2018 | 10/31/2018 | 10/31/2018 | A | PART |
Dave Hannah
|
|
|
wall // Edgar Phone #: ###-####
|
BLD-Footing | 10/29/2018 | 10/29/2018 | 10/29/2018 | P | PART |
Tony Young
|
|
|
Manny Phone #: ###-####,, garage footing ok
|
OVERRIDE | | | 10/18/2018 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 10/18/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/18/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 9/6/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 8/13/2018 | 8/13/2018 | 9/6/2018 | | DONE |
|
|
|
08/15 sfd L1 ePlan. 1st review complete, roof and foundation structural deficiencies, garage braced wall calculations, floor joist structural deficiencies.
|
Routing - PLAN CHECK | 9/6/2018 | | 9/6/2018 | | PASS |
Brian McGowan
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/6/2018 | | DONE |
Brian McGowan
|
|
|
|
Permit Ready to Issue | | | 9/6/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/23/2018 | | 8/23/2018 | | FAIL |
Brian McGowan
|
|
|
|
1st review completed | | | 8/15/2018 | | FAIL |
|
|
|
2nd Review, show calculations for header, show code reference or calculations for bracing in roof. 1st review, Roof and foundation structural deficiencies, garage braced wall calculations, floor joist structural deficiencies.
|
Routing - PLAN CHECK | 8/2/2018 | | 8/15/2018 | | FAIL |
Brian McGowan
|
|
|
As per Jenny's Review
|
Routing - PLANNING | 8/2/2018 | | 8/14/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - MECHANICAL | 8/2/2018 | | 8/7/2018 | | PASS |
Chad Schwendiman
|
|
|
|
Route to Impact Fee Review | 8/2/2018 | 8/5/2018 | 8/3/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - Addressing | 8/2/2018 | | 8/3/2018 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 8/2/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 2 2018 1:54PM
|
Plan assigned to (BJM) | 8/2/2018 | 8/2/2018 | 8/2/2018 | | DEFR |
Brian McGowan
|
|
|
08/15 sfd L1 ePlan
|
Plans ACCEPTED BY PLAN TECH | | | 8/2/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/2/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/2/2018 | | PASS |
|
|
|
|
Routing - PUBLIC WORKS | 8/2/2018 | | 8/2/2018 | | PASS |
Morgan Webb
|
|
|
|