Second Notice | | 11/8/2019 | 11/6/2019 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
First Notice | 9/24/2019 | 9/24/2019 | 10/29/2019 | | DONE |
Mike Jordan
|
|
|
mailed 11-1
|
BLD-Final | 9/24/2019 | 9/24/2019 | 9/24/2019 | P | PASS |
Mike Jordan
|
|
|
Public Works signed off Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
DOC - Permit Finaled | 9/24/2019 | 9/24/2019 | 9/24/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 9/16/2019 | 9/16/2019 | 9/16/2019 | P | PART |
Mike Jordan
|
|
|
have letter from MTI Phone #: ###-#### Inspection requested via web by Todd Landvatter. Received special inspection letter. Need to follow up on public works.
|
BLD-Final | 9/11/2019 | 9/12/2019 | 9/12/2019 | A | PART |
Jim Storey
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter need sing off doc's from si and engineer of record
|
Zoning Approval | 9/12/2019 | 9/12/2019 | 9/12/2019 | | PASS |
Katelyn Menuge
|
|
|
|
FIRE-Final Inspection | 9/10/2019 | 9/11/2019 | 9/11/2019 | A | PASS |
Troy Cobbley
|
|
|
Life safety passed. Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Conference | 8/27/2019 | 8/27/2019 | 8/27/2019 | P | DONE |
Mike Jordan
|
|
|
Need to discuss Area of Refuge signage Please call Todd ###-#### Phone #: ###-#### Inspection requested via web by Brian McCoy
|
Permit Ready to Issue | | | 8/22/2019 | | DONE |
|
|
|
PLAN MOD
|
CHANGE STATUS TO (ISS) | | | 8/22/2019 | | DONE |
|
|
|
plan mod-attached the revised sign off card into e plan in the approved drawings
|
Inspection Record Card- Bld | | | 8/22/2019 | | DONE |
|
|
|
plan mod
|
Plan assigned to (JAR) | 8/16/2019 | 8/16/2019 | 8/20/2019 | | DONE |
Julie Romig
|
|
|
08/22 - Plan Mod West Airpot Industrial Park A
|
Routing - PLAN CHECK | 8/16/2019 | | 8/20/2019 | | PASS |
Julie Romig
|
|
|
|
BLD-Conference | 8/16/2019 | 8/19/2019 | 8/19/2019 | A | DONE |
Mike Jordan
|
|
|
signage questions Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
Plan Modification Accepted | | | 8/16/2019 | | DONE |
|
|
|
As part of the permit comment response provided 10/10/18 for Item #5 - BRS provided a revised sheet showing an additional HC parking stall provided near the south drive
aisle (sheet AS1.1). This revision was approved and permitted, however sheet C1.1 was not revised and coordinated to show this revision. Therefore construction has been
completed per the C1.1 sheet and the ADA ramp was constructed against the parking island to the south as shown in the permitted C1.1 sheet. We would like to request a plan
modification to approve the third HC stall to be relocated behind the south HC stall so that the accessible parking space can share the 5'-0" accessible aisle that accesses the
ADA compliant ramp. This new location will be able to provide a safe and compliant accessible route to the building entrances, as well as provide a 2nd accessible van space
which will provide 8'-0" clear access aisle in lieu of the standard 5'-0" access aisle. This location also maintains the previously approved design intent of the third location sharing
the south access aisle - (approved in the 10/18/18 permit drawings).
|
Telephone call | | | 8/15/2019 | | DONE |
|
|
|
called Todd to let know sub permits are all messed up and not attached to the correct building permits-he will email them to straightened them out
|
BLD-Energy code compliance | 8/2/2019 | 8/5/2019 | 8/5/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Conference | 7/12/2019 | 7/15/2019 | 7/15/2019 | A | DONE |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Framing/Rough-in | 6/24/2019 | 6/25/2019 | 6/25/2019 | P | PASS |
Mike Jordan
|
|
|
part Phone #: ###-#### Inspection requested via web by Todd Landvatter. Insulation for fire wall and upper framing.
|
BLD-Framing/Rough-in | 6/21/2019 | 6/24/2019 | 6/24/2019 | P | PART |
Mike Jordan
|
|
|
Fire riser and electrical room Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Framing/Rough-in | 6/21/2019 | 6/21/2019 | 6/21/2019 | P | CANC |
Mike Jordan
|
|
|
Fire riser and electrical room Phone #: ###-#### >> Inspection requested via web by Todd Landvatter Inspection cancelled from web by: Todd Landvatter
|
BLD-Footing | 5/7/2019 | 5/7/2019 | 5/7/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Pour backs from slab to panel.
|
BLD-Concrete | 5/3/2019 | 5/6/2019 | 5/6/2019 | A | NR |
Mike Jordan
|
|
|
1/2 pour back strip Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Concrete | 3/26/2019 | 3/27/2019 | 3/27/2019 | A | PASS |
Mike Jordan
|
|
|
rebar remaining panels Phone #: ###-#### Inspection requested via web by Todd Landvatter. Remainder of concrete tilt panels. Ok to place concrete pending special inpection.
|
BLD-Footing | 2/13/2019 | 2/14/2019 | 2/15/2019 | P | PEND |
Brandon Shaw
|
|
|
Pending Special Inspection report...
|
BLD-Concrete | 1/31/2019 | 2/1/2019 | 2/1/2019 | P | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Concrete | 1/29/2019 | 1/29/2019 | 1/29/2019 | P | PASS |
Mike Jordan
|
|
|
reinforcing for tilt panels Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Foundation | 12/18/2018 | 12/18/2018 | 12/18/2018 | P | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Rebar for interior slab on grade ok.
|
BLD-Footing | 11/20/2018 | 11/26/2018 | 11/26/2018 | A | PART |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter. reinforcement for interior column pad footings have been fabricated and ready to set into footing. Special inspection is required and will have special inspection. Ok to place concrete pending special inspection approval.
|
BLD-Footing | 11/19/2018 | 11/21/2018 | 11/20/2018 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Todd Landvatter Inspection cancelled from web by: Todd Landvatter
|
Issue PAID IN FULL permit | | | 10/19/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/19/2018 | | DONE |
|
|
|
|
Plan assigned to (JAR) | 8/9/2018 | 8/9/2018 | 10/18/2018 | | DONE |
Julie Romig
|
|
|
10/16 2nd Rev - 1st Rev Comp - 502 West Airport Warehouse
|
Routing PW Drainage | 8/10/2018 | | 10/18/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - PLAN CHECK | 10/10/2018 | | 10/18/2018 | | PASS |
Julie Romig
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/18/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/18/2018 | | DONE |
|
|
|
NEED- all met (brian@sl-builders.com)
GC FORM
REVISED VALUE
|
Routing Off Site - STRUCTURAL | 10/18/2018 | | 10/15/2018 | | PASS |
Julie Romig
|
|
|
|
Route to Impact Fee Review | 9/29/2018 | 10/2/2018 | 10/1/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 9/29/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - PLAN CHECK | 8/9/2018 | | 9/29/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing - FIRE | 8/9/2018 | 8/9/2018 | 9/19/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing Off Site - STRUCTURAL | 8/9/2018 | | 8/21/2018 | | FAIL |
Julie Romig
|
|
|
|
Routing PW Environmental | 8/10/2018 | | 8/14/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing PW Solid Waste | 8/10/2018 | | 8/13/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - MECHANICAL | 8/9/2018 | | 8/13/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 8/9/2018 | | 8/10/2018 | | PASS |
Bill VanDegrift
|
|
|
Per plan and ISPC.
|
Routing - Design Review | 8/9/2018 | | 8/10/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH18-00264 and DRH18-00332
|
Routing PW Street Lights | 8/10/2018 | | 8/10/2018 | | PASS |
Tom Marshall
|
|
|
Street lights are being tracked on BLD18-02802.
|
Routing PW Sewer Design | 8/10/2018 | | 8/10/2018 | | PASS |
DeAnn Brown
|
|
|
|
Routing - Addressing | 8/9/2018 | | 8/10/2018 | | PASS |
Doug Chausow
|
|
|
Address corrected to 2611 S Fry St.
|
Routing - PUBLIC WORKS | 8/9/2018 | | 8/10/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Erosion and Sediment | 8/9/2018 | | 8/9/2018 | | PASS |
Michael Zawacki
|
|
|
Void. Please refer to ESC18-01128
|
Routing - PLANNING | 8/9/2018 | | 8/9/2018 | | PASS |
David Moser
|
|
|
see DRH18-00332
|
Intake Approval | | | 8/7/2018 | | PASS |
|
|
|
|
Application received | | | 8/3/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 3 2018 2:34PM
|