Case Summary (BLD) | | | 6/6/2020 | | DONE |
|
|
|
|
Letter of compliance/Occupancy | | | 12/19/2019 | | DONE |
|
|
|
|
Second Notice | | 11/8/2019 | 11/6/2019 | | DONE |
|
|
|
This permit finaled on the web by Brian McCoy
|
First Notice | 10/17/2019 | 10/17/2019 | 10/29/2019 | | DONE |
Mike Jordan
|
|
|
mailed 11-1
|
BLD-Final | 10/17/2019 | 10/17/2019 | 10/17/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
DOC - Permit Finaled | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | PASS |
Mike Jordan
|
|
|
|
BLD-Final | 10/16/2019 | 10/16/2019 | 10/16/2019 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
FIRE-Final Inspection | 10/16/2019 | 10/16/2019 | 10/16/2019 | P | PASS |
Troy Cobbley
|
|
|
Life safety passed.
Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
PubWorks Occupancy Approval | 9/24/2019 | 9/24/2019 | 9/24/2019 | | DONE |
Tiffany Lowery
|
|
|
|
Zoning Approval | 9/12/2019 | 9/12/2019 | 9/12/2019 | | PASS |
Katelyn Menuge
|
|
|
|
BLD-Wall cover | 9/3/2019 | 9/3/2019 | 9/3/2019 | P | PASS |
Mike Jordan
|
|
|
fire riser 1 hr insulation Phone #: ###-#### Inspection requested via web by Todd Landvatter. Framing at south wall is now frmed to bottom of roof deck. Ok to sheet rock.
|
BLD-Framing/Rough-in | 8/22/2019 | 8/23/2019 | 8/23/2019 | A | PART |
Mike Jordan
|
|
|
Fire riser room Phone #: ###-#### Inspection requested via web by Todd Landvatter. Needs to frame both sides of joist to roof deck, south wall. ok to one side and insulate.
|
Telephone call | | | 8/20/2019 | | DONE |
|
|
|
emailed todd@sl-builders.com about the address change and asked him to contact all his subs and let them know as well. He said he would
|
BLD-Concrete | 7/1/2019 | 7/1/2019 | 7/1/2019 | P | PASS |
Mike Jordan
|
|
|
2nd 1/2 pourback Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Concrete | 6/25/2019 | 6/27/2019 | 6/27/2019 | P | PASS |
Mike Jordan
|
|
|
Pourback strip. 1/2 Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Concrete | 5/10/2019 | 5/13/2019 | 5/13/2019 | A | CANC |
Mike Jordan
|
|
|
reinforcing wall panels. Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Concrete | 5/13/2019 | 5/13/2019 | 5/13/2019 | P | PASS |
Mike Jordan
|
|
|
Concrete tilt panels 12 and 31 thru 39.
|
BLD-Footing | 4/18/2019 | 4/18/2019 | 4/18/2019 | P | DONE |
Mike Jordan
|
|
|
concrete scheduled for 1:00PM. rebar for west and south. Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Footing | 4/16/2019 | 4/17/2019 | 4/17/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter. reinforcement for east and north footings ok. Work in progress on south and west exterior footings. Ok to place pending special inspection.
|
BLD-Concrete | 4/4/2019 | 4/5/2019 | 4/5/2019 | A | PASS |
Mike Jordan
|
|
|
reinforcing panels Phone #: ###-#### Inspection requested via web by Todd Landvatter. Concrete tilt panels 1 thru 30, except 12.
|
BLD-Concrete | 4/4/2019 | 4/4/2019 | 4/4/2019 | A | NR |
Mike Jordan
|
|
|
Reinforcing wall panels (partial) Phone #: ###-#### Inspection requested via web by Todd Landvatter
|
BLD-Foundation | 1/30/2019 | 1/31/2019 | 1/31/2019 | A | PASS |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter. Slab on grade
|
BLD-Footing | 11/26/2018 | 11/27/2018 | 11/27/2018 | A | PART |
Mike Jordan
|
|
|
Ready at 9am. Phone #: ###-#### Inspection requested via web by Todd Landvatter. New mats built and placed with # 6 rebar as per approved plans. Work is still in progress. ok to place concrete pending special inspection approval.
|
BLD-Footing | 11/20/2018 | 11/26/2018 | 11/26/2018 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Todd Landvatter. reinforcement for interior column pad footings. Approved plans call for #6 reinforcement top and bottom mats. Contractor has constructed mats from #5 rebar.
|
BLD-Footing | 11/19/2018 | 11/21/2018 | 11/20/2018 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### >> Inspection requested via web by Todd Landvatter Inspection cancelled from web by: Todd Landvatter
|
Plan assigned to (CJW) | 8/9/2018 | 8/9/2018 | 10/17/2018 | | PASS |
Carl Westfall
|
|
|
(2nd done) 09/10/18 (new - 25 days) (ePlan - 70 sheets) West Airport Warehouse New
|
Routing - PLAN CHECK | 10/16/2018 | | 10/17/2018 | | PASS |
Carl Westfall
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/17/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/17/2018 | | DONE |
|
|
|
Need:
ACHD
GC form- met
Revised value from GC-met
RP-met
|
Issue PAID IN FULL permit | | | 10/17/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 10/17/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 10/16/2018 | | DONE |
|
|
|
|
Plan resubmittals received | | | 10/16/2018 | | DONE |
|
|
|
|
Routing Off Site - STRUCTURAL | 10/11/2018 | | 10/15/2018 | | PASS |
Carl Westfall
|
|
|
Chris Holladay (AHJ)
|
Routing - PLAN CHECK | 10/10/2018 | | 10/11/2018 | | FAIL |
Carl Westfall
|
|
|
Item #4 with reference to the accessible means of egress has not been resolved yet. Otherwise, the drawings are approved pending structural.
|
Routing PW Sewer Design | 10/11/2018 | | 10/11/2018 | | PASS |
DeAnn Brown
|
|
|
|
Plan resubmittals received | | | 10/10/2018 | | DONE |
|
|
|
|
Route to Impact Fee Review | 9/27/2018 | 9/30/2018 | 9/28/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
1st review completed | | | 9/27/2018 | | DONE |
|
|
|
|
Plan resubmittals requested | | | 9/27/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/9/2018 | | 9/27/2018 | | FAIL |
Carl Westfall
|
|
|
Revised drawings required
|
Routing - FIRE | 8/9/2018 | 8/9/2018 | 9/19/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Routing Off Site - STRUCTURAL | 8/9/2018 | | 8/21/2018 | | FAIL |
Carl Westfall
|
|
|
Chris Holladay (AHJ)
|
Routing PW Environmental | 8/9/2018 | | 8/14/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 8/9/2018 | | 8/13/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 8/9/2018 | | 8/10/2018 | | PASS |
Daryl Spivey
|
|
|
Per plan and ISPC.
|
Routing - Design Review | 8/9/2018 | | 8/10/2018 | | PASS |
Katelyn Menuge
|
|
|
DRH18-00264 and DRH18-00332
|
Routing PW Drainage | 8/9/2018 | | 8/10/2018 | | PASS |
Brian Murphy
|
|
|
|
Routing - Addressing | 8/9/2018 | | 8/10/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/9/2018 | | 8/10/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Sewer Design | 8/9/2018 | | 8/10/2018 | | FAIL |
DeAnn Brown
|
|
|
Sewer extension plans have not been approved. Approval of plans requires revised plans per redlines sent to KM Engineering and easement documents.
|
Routing PW Solid Waste | 8/9/2018 | | 8/9/2018 | | PASS |
Evan Carpenter
|
|
|
|
Routing - Erosion and Sediment | 8/9/2018 | | 8/9/2018 | | PASS |
Michael Zawacki
|
|
|
Void. Please refer to ESC18-01128
|
Routing PW Street Lights | 8/9/2018 | | 8/9/2018 | | PASS |
Tom Marshall
|
|
|
|
Routing - PLANNING | 8/9/2018 | | 8/9/2018 | | PASS |
David Moser
|
|
|
see DRH18-00332
|
Intake Approval | | | 8/7/2018 | | PASS |
|
|
|
|
Application received | | | 8/3/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 3 2018 3:19PM
|