BLD-Final | 7/22/2019 | 7/22/2019 | 7/22/2019 | P | PASS |
Dave Hannah
|
|
|
Jon Phone #: ###-####
|
Permanent Occupancy | | | 7/22/2019 | | DONE |
|
|
|
|
BLD-Final | 7/19/2019 | 7/19/2019 | 7/19/2019 | P | FAIL |
Jim Storey
|
|
|
Jon Phone #: ###-#### sd max 24 inches from ceilling in hallway.
|
FIRE-Final Inspection | 7/19/2019 | 7/19/2019 | 7/19/2019 | P | PASS |
Jim Page
|
|
|
Fire sprinkler inspection is complete, fire alarm inspection is complete, fire extinguishers are in common areas with current inspection tags. Final life fire safety inspection for area of work complete.
Jon Phone #: ###-####
|
FIRE-Final Inspection | 7/15/2019 | 7/16/2019 | 7/16/2019 | P | CANC |
Jim Page
|
|
|
Cancelled per conversation with point of contact, will reschedule to coincide with fire alarm inspection.
John Phone #: ###-####
|
FIRE-Final Inspection | 7/12/2019 | 7/12/2019 | 7/12/2019 | P | FAIL |
Jim Page
|
|
|
Fire alarm inspection was requested by the GC for FIR19-00403 but not coordinated with Protex per conversation with Morgan for fire alarm final. Permit holder for fire alarms is responsible for scheduling fire alarm inspection requests. FIR permit for fire alarms is still in issued status, as discussed with the GC, life fire safety inspection will not be completed or finaled until fire alarms are tested, inspected and finaled.
Jon Phone #: ###-####
|
FIRE-Final Inspection | 7/12/2019 | 7/12/2019 | 7/12/2019 | P | CANC |
Jim Page
|
|
|
Duplicate inspection request, this request is cancelled.
Jon Phone #: ###-####
|
BLD-Framing/Rough-in | 6/4/2019 | 6/5/2019 | 6/5/2019 | A | PASS |
Dave Hannah
|
|
|
John- Partial for framing inspection, please call for access Phone #: ###-####
|
BLD-Framing/Rough-in | 4/12/2019 | 4/15/2019 | 4/16/2019 | P | PASS |
Dave Hannah
|
|
|
Jon- please call for access. Phone #: ###-####
|
BLD-Framing/Rough-in | 4/15/2019 | 4/16/2019 | 4/16/2019 | A | PASS |
Dave Hannah
|
|
|
John Phone #: ###-####
|
Print Occupancy Form | | | 2/12/2019 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 2/8/2019 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 2/8/2019 | | DONE |
|
|
|
|
Print Occupancy Form | | | 2/8/2019 | | DONE |
|
|
|
|
CHANGE STATUS TO (ISS) | | | 2/8/2019 | | DONE |
|
|
|
Accidentally printed C of O instead sign off card. Woopsie
|
Telephone call | | | 1/25/2019 | | DONE |
|
|
|
Spoke with Samantha informing her that this permit is going to expire in 11 days and is welcome to send in a request for a 180 day extension. stated she will contact the inspections.
|
Meeting | | | 1/25/2019 | | DONE |
|
|
|
extension request sent in
|
Meeting | | | 1/25/2019 | | DONE |
|
|
|
Per Adele: permit will not be extened due to owner stating permit will be picked up on Monday. Adele also spoke with Tanya Barkel with EKC who also stated they will be in on Monday (1/28/19) to pick up the permit
|
Expiration Notice | 1/9/2019 | 1/31/2019 | 1/9/2019 | | DONE |
Brittany Hill
|
|
|
|
Plan assigned to (CDM) | 8/10/2018 | 8/10/2018 | 9/14/2018 | | PASS |
Carl D Madsen
|
|
|
09/03 R Grey Residential Unit L-3
|
Routing - PLAN CHECK | 9/14/2018 | | 9/14/2018 | | PASS |
Carl D Madsen
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/14/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/14/2018 | | DONE |
|
|
|
Tanya is no longer with EKC, Inc.
Erin Breen will be filling this position she will be coming on board
Monday, February 11th. In the meantime: Please call (###-####)
and ask for the following:
1. Billing and waivers - ask for Charlene Meadows charlene@ekcconstruction.com or Cecyle Brock cecyle@ekcconstructon.com 2. Change Orders - ask for your project manager.
3. Quotes - ask for Paul Haas paul@ekcconstruction.com
Need- all met (tanyab@ekcconstruction.com)
GC Form-
Revised Cert of Value - met
ACHD -met
|
Route to Impact Fee Review | 9/4/2018 | 9/7/2018 | 9/5/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 8/10/2018 | 8/10/2018 | 9/4/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 9/4/2018 | | FAIL |
|
|
|
|
Routing - PLAN CHECK | 8/10/2018 | | 9/3/2018 | | FAIL |
Carl D Madsen
|
|
|
|
Routing - MECHANICAL | 8/10/2018 | | 8/14/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/10/2018 | | 8/10/2018 | | PASS |
David Moser
|
|
|
|
Routing - Addressing | 8/10/2018 | | 8/10/2018 | | PASS |
Doug Chausow
|
|
|
Unit 101
|
Routing - PUBLIC WORKS | 8/10/2018 | | 8/10/2018 | | PASS |
Morgan Webb
|
|
|
|
Intake Approval | | | 8/7/2018 | | PASS |
|
|
|
|
Application received | | | 8/6/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 6 2018 12:12PM
|
First Notice | | 8/1/2019 | | | |
|
|
|
|