BLD-Final | 1/9/2019 | 1/10/2019 | 1/10/2019 | P | PART |
Mike Jordan
|
|
|
Jose Phone #: ###-####. Ok for temp occ. Needs to provide ADA pos. Also needs fire to sign perm.
|
FIRE-Final Inspection | 1/9/2019 | 1/10/2019 | 1/10/2019 | A | PART |
Troy Cobbley
|
|
|
A temporary for life safety is ok with Ron's permission until the fire sprinkler permit for upgrades has been finaled
Jose Phone #: ###-####
|
FIRE-Final Inspection | 12/12/2018 | 12/12/2018 | 12/12/2018 | P | FAIL |
Troy Cobbley
|
|
|
Life safety will be ok to pass when I'm directed by the Building Dept/Fire Dept. that an acceptable agreement has been reached on the fire sprinkler system.
|
BLD-Final | 12/10/2018 | 12/11/2018 | 12/11/2018 | A | NR |
Mike Jordan
|
|
|
Tony Phone #: ###-####. fire/life safety has failed.
|
FIRE-Final Inspection | 12/10/2018 | 12/11/2018 | 12/11/2018 | A | FAIL |
Jim Page
|
|
|
Reference Troys notes entered on 06DEC2018, as of this inspection no upgrade aggreement has been made.
Tony Phone #: ###-####
|
FIRE-Final Inspection | 12/5/2018 | 12/6/2018 | 12/6/2018 | A | FAIL |
Troy Cobbley
|
|
|
I'm working with Collier's and the Boise Fire Dept on the required upgrade to the fire sprinkler system that was an issue in 2016. Also need the painted head in the restroom replaced, fire extinguisher hung as discussed and the door hardware changed to single action ADA type as discussed. The fire sprinkler permit needs finaled as well.
Tony Phone #: ###-####
|
BLD-Framing/Rough-in | 11/2/2018 | 11/5/2018 | 11/5/2018 | A | CANC |
Mike Jordan
|
|
|
Ocsar Phone #: ###-####
|
BLD-Framing/Rough-in | 11/2/2018 | 11/5/2018 | 11/5/2018 | A | PASS |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Approved plans on site. ok.
|
BLD-Framing/Rough-in | 11/1/2018 | 11/2/2018 | 11/2/2018 | A | PART |
Mike Jordan
|
|
|
Tony Phone #: ###-####. Interior wood framed walls ok. No approved plans on site. Will reschedule for pm inspection.
|
Issue PAID IN FULL permit | | | 9/11/2018 | | DONE |
|
|
|
|
Print Occupancy Form | | | 9/11/2018 | | DONE |
|
|
|
|
Routing - FIRE | 8/9/2018 | 8/9/2018 | 9/5/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
Plan assigned to (M_H) | 8/9/2018 | | 9/5/2018 | | DONE |
Michael Hanson
|
|
|
09/03 #520 L3 ePlan. 1st review completed
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/5/2018 | | DONE |
Michael Hanson
|
|
|
|
Permit Ready to Issue | | | 9/5/2018 | | DONE |
|
|
|
NEED
GC FORM
REVISED VALUE
(if no mech value need MIS for mech insp for restaurant occupancy)
|
Route to Impact Fee Review | 8/31/2018 | 9/3/2018 | 9/4/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - PLAN CHECK | 8/9/2018 | | 8/31/2018 | | PASS |
Michael Hanson
|
|
|
|
1st review completed | | | 8/31/2018 | | DONE |
Michael Hanson
|
|
|
|
Routing PW Environmental | 8/13/2018 | | 8/22/2018 | | PASS |
Terry Alber
|
|
|
Require point source grease abatement on triple sink.
|
Routing - PLUMBING | 8/9/2018 | | 8/13/2018 | | PASS |
Bill VanDegrift
|
|
|
1) add a floor sink for the water cooled
ice cream maker
2) add an R.P. for the ice cream maker
|
Routing - PUBLIC WORKS | 8/9/2018 | | 8/13/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - Addressing | 8/9/2018 | | 8/10/2018 | | PASS |
Doug Chausow
|
|
|
|
Application received | | | 8/7/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 7 2018 9:15AM
|
Intake Approval | | | 8/7/2018 | | PASS |
|
|
|
|