BLD-Final | 12/5/2018 | 12/5/2018 | 12/5/2018 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Steven Shehan
|
DOC - Permit Finaled | 12/5/2018 | 12/5/2018 | 12/5/2018 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 11/29/2018 | 11/29/2018 | 11/29/2018 | P | NR |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Steven Shehan. A mech permit is required for the mini split that has been installed.
|
BLD-Framing/Rough-in | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PASS |
Jim Sly
|
|
|
Inspection requested via web by Steven Shehan Frame and Energy.......OK
|
BLD-Wall cover | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | CANC |
Mike Jordan
|
|
|
Inspection requested via web by Steven Shehan
|
BLD-Wall Bracing | 10/1/2018 | 10/1/2018 | 10/1/2018 | P | PASS |
Mike Jordan
|
|
|
Inspection requested via web by Steven Shehan. Needs to lower window in bedroom to meet egress. Will verify on framing inspection.
|
BLD-Framing/Rough-in | 9/30/2018 | 10/1/2018 | 10/1/2018 | A | CANC |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Steven Shehan
|
BLD-Wall cover | 9/30/2018 | 10/1/2018 | 10/1/2018 | A | FAIL |
Mike Jordan
|
|
|
Phone #: ###-#### Inspection requested via web by Steven Shehan. Needs to renail exterior sheathing.
|
BLD-Foundation | 9/6/2018 | 9/7/2018 | 9/7/2018 | P | PASS |
Mike Jordan
|
|
|
Please make every effort to be here 1pm - 2pm so we can pour after inspection Inspection requested via web by Steven Shehan
|
BLD-Footing | 9/5/2018 | 9/6/2018 | 9/6/2018 | A | PASS |
Mike Jordan
|
|
|
Inspection requested via web by Steven Shehan
|
Issue PAID IN FULL permit | | | 9/5/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/5/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 8/31/2018 | | |
|
|
|
|
OVERRIDE | | | 8/31/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 8/15/2018 | 8/15/2018 | 8/31/2018 | | PASS |
Josh Bogle
|
|
|
08/21 addition, ePlan - 1st done
|
Permit Ready to Issue | | | 8/31/2018 | | DONE |
|
|
|
All requirements met
|
Routing - PLANNING | 8/31/2018 | | 8/31/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - PLAN CHECK | 8/31/2018 | | 8/31/2018 | | PASS |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/31/2018 | | DONE |
Josh Bogle
|
|
|
ESC yese - Energy yes
|
Routing - PLAN CHECK | 8/30/2018 | | 8/30/2018 | | FAIL |
Josh Bogle
|
|
|
|
Plan Reviewer's activity | | | 8/30/2018 | | |
|
|
|
rejected resubmittal - no new site plan
|
Routing - PLANNING | 8/29/2018 | | 8/29/2018 | | FAIL |
Sue Cummings
|
|
|
I need a site plan ,drawn to scale, showing all property lines so I can measure setbacks
|
Routing - PLAN CHECK | 8/29/2018 | | 8/29/2018 | | FAIL |
Josh Bogle
|
|
|
missing joists, footings, braced walls, etc
|
Routing Walk-In (BLD) | 8/22/2018 | 8/22/2018 | 8/22/2018 | A | FAIL |
Josh Bogle
|
|
|
read through the Submittal Checklist with applicant, highlighted all items missing from plans
|
1st review completed | | | 8/17/2018 | | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 8/15/2018 | | 8/17/2018 | | FAIL |
Josh Bogle
|
|
|
plan too lacking in details or accuracy of depiction for a full review
|
Plans ACCEPTED BY PLAN TECH | | | 8/15/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/15/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/15/2018 | | PASS |
|
|
|
|
Intake Approval | | | 8/14/2018 | | FAIL |
|
|
|
Please provide a site plan showing the whole property and the set backs from the property lines.
|
Application received | | | 8/7/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 7 2018 1:47PM
|
Routing - PLANNING | 8/15/2018 | | 8/15/2015 | | FAIL |
Sue Cummings
|
|
|
A site plan, drawn to scale is required to measeure setbacks
|