BLD-Final | 7/14/2020 | 7/15/2020 | 7/15/2020 | P | PASS |
Brandon Shaw
|
|
|
Final inspection on pool in back yard. If additional assistance is needed please feel free to call Monica at ###-#### Phone #: ###-#### Inspection requested via web by Monica McNair
|
DOC - Permit Finaled | 7/15/2020 | 7/15/2020 | 7/15/2020 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Footing | 8/29/2018 | 8/30/2018 | 8/30/2018 | A | PASS |
Tony Young
|
|
|
rebar structural steel // Please call with any questions. Phone #: ###-#### Inspection requested via web by Brandy McConkey// pool rebar ok
|
BLD-Concrete | 8/22/2018 | 8/29/2018 | 8/29/2018 | A | PEND |
Tony Young
|
|
|
rebar structural steel // Please call with any questions. Phone #: ###-#### Inspection requested via web by Brandy McConkey,, needs soils approval 1st
|
OVERRIDE | | | 8/13/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 8/13/2018 | 8/13/2018 | 8/13/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing Walk-In (BLD) | 8/13/2018 | 8/13/2018 | 8/13/2018 | A | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (BJM) | 8/8/2018 | 8/8/2018 | 8/13/2018 | | DEFR |
Brian McGowan
|
|
|
08/25? Pool addition in Hillside L2 paper
|
Routing - PLAN CHECK | | | 8/13/2018 | | PASS |
Josh Bogle
|
|
|
|
Routing - PUBLIC WORKS | 8/8/2018 | | 8/13/2018 | | PASS |
Rachael Beierle
|
|
|
|
1st review completed | | | 8/13/2018 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 8/13/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 8/13/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/13/2018 | | DONE |
Josh Bogle
|
|
|
|
Override - Parcel Holds | | | 8/13/2018 | | |
|
|
|
|
Permit Ready to Issue | | | 8/13/2018 | | DONE |
|
|
|
|
Override - Parcel Holds | | | 8/13/2018 | | |
|
|
|
|
Issue PAID IN FULL permit | | | 8/13/2018 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 8/9/2018 | | 8/13/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable must be approved by Public Works prior to scheduling inspections. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
|
Routing - Erosion and Sediment | 8/13/2018 | | 8/13/2018 | | PASS |
Melissa Jannusch
|
|
|
ESC plan and narritive provided. Approved through the planning and zoning process under CFH18-00076.
An erosion and sediment control site preparation inspection is required for this site. The site preparation inspection takes place after all required erosion and sediment control best management practices have been installed and BEFORE any earthwork takes place. Call ###-#### to schedule an inspection.
|
Routing - Erosion and Sediment | | | 8/10/2018 | | FAIL |
Michael Zawacki
|
|
|
ESC plan or waiver request needed.
Based on summary dated 7-24-18 requires cat 2 hillside because of proposed amount of grading.
|
Routing - PLANNING | | | 8/10/2018 | | PASS |
|
|
|
|
Routing - Addressing | 8/9/2018 | | 8/9/2018 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/8/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/8/2018 | | PASS |
|
|
|
|
Override - Parcel Holds | | | 8/8/2018 | | |
|
|
|
|
Override - Parcel Holds | | | 8/8/2018 | | |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/8/2018 | | DONE |
|
|
|
|
PubWorks Subgrade Approval | 8/27/2018 | 8/27/2018 | | | DONE |
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the pool subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Application received | | 8/8/2018 | | | |
|
|
|
|