BLD-Final | 1/9/2019 | 1/10/2019 | 1/10/2019 | P | PASS |
Tony Young
|
|
|
Call 30 minutes ahead // Jeremy Phone #: ###-####
|
DOC - Permit Finaled | 1/10/2019 | 1/10/2019 | 1/10/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Energy code compliance | 11/1/2018 | 11/2/2018 | 11/2/2018 | P | PASS |
Brandon Shaw
|
|
|
Jerimy Phone #: ###-####
|
BLD-Framing/Rough-in | 10/22/2018 | 10/23/2018 | 10/23/2018 | P | PASS |
Tony Young
|
|
|
Jermary Phone #: ###-####,, needs to justify roof venting,, ok to insulate
|
Plan Modification Accepted | | | 10/8/2018 | | DONE |
|
|
|
New manual j report
|
Routing - MECHANICAL | 10/8/2018 | | 10/8/2018 | | PASS |
Troy James
|
|
|
resubmitted manual j report
|
BLD-Wall Bracing | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | PASS |
Mike Jordan
|
|
|
Buster Phone #: ###-####
|
BLD-Foundation | 9/6/2018 | 9/6/2018 | 9/6/2018 | P | PASS |
Tony Young
|
|
|
Brent Phone #: ###-####
|
BLD-Footing | 9/4/2018 | 9/5/2018 | 9/5/2018 | A | PASS |
Dave Hannah
|
|
|
late morning- Jerimy Phone #: ###-####
|
Issue PAID IN FULL permit | | | 9/4/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/4/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 8/31/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 8/15/2018 | 8/15/2018 | 8/31/2018 | | DONE |
|
|
|
08/23 sfd L1 ePlan. 2nd review 8/29 - unresolved changemarks. 1st Review complete 8/21 - clarify mechanical equipment, structural deficiencies, footing details, update energy code tables and R values
|
Routing - PLAN CHECK | 8/29/2018 | | 8/31/2018 | | PASS |
Michael Hanson
|
|
|
Reviewed by JJN. MDH
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/31/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/31/2018 | | DONE |
|
|
|
met
|
Routing - PLAN CHECK | 8/21/2018 | | 8/29/2018 | | FAIL |
Michael Hanson
|
|
|
See ePlan comments from JJN - 5 of 10 changemarks resolved. MDH
|
Routing - PLAN CHECK | 8/21/2018 | | 8/21/2018 | | FAIL |
Michael Hanson
|
|
|
|
1st review completed | | | 8/21/2018 | | FAIL |
|
|
|
Clarify mechanical equipment, structural deficiencies, footing details, update energy code year and R values, structural calculation floor plan doesn't match.
|
Route to Impact Fee Review | 8/10/2018 | 8/13/2018 | 8/13/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Intake Approval | | | 8/10/2018 | | FAIL |
|
|
|
Sheet do not meet size and need to be rotated
|
Plans ACCEPTED BY PLAN TECH | | | 8/10/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/10/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/10/2018 | | DONE |
|
|
|
|
Plan assigned to (M_H) | 8/10/2018 | | 8/10/2018 | | DEFR |
Michael Hanson
|
|
|
08/23 sfd L1 ePlan
|
Routing - MECHANICAL | 8/10/2018 | | 8/10/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/10/2018 | | 8/10/2018 | | PASS |
Jeff Lowe
|
|
|
|
Routing - Addressing | 8/10/2018 | | 8/10/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/10/2018 | | 8/10/2018 | | PASS |
Rachael Beierle
|
|
|
|
Application received | | | 8/9/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 9 2018 9:20AM
|
Intake Approval | | | 8/9/2018 | | FAIL |
|
|
|
need manual J's and drawings must be uploaded individually
|
(F) Reprint permit | | | 8/9/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/9/2018 | | FAIL |
|
|
|
no corrections were done
|