Information based on query as of Wednesday, July 24, 2024.
Permit Information
Permit NumberBLD18-02882
StatusFinaled
Name BUSTER BUILT
Site Address 2525 N WOODY DR
Project NameWoody Home
Customer NumberDEMO BLD18-02038
ePlanReviewYes
Description
**PRESCRIPTIVE ENERGY METHOD** Permit for the construction of a new 1260 sq. ft., one story single family dwelling with 2 bedrooms, 2 bathrooms, approximately 525 sq. ft. of covered patio/porch, has existing detached garage per the approved plans and any notations. R-1C zoning and setbacks per planning. JJN
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/9/20191/10/20191/10/2019PPASS
DetailsTony Young
Call 30 minutes ahead // Jeremy Phone #: ###-####
DOC - Permit Finaled1/10/20191/10/20191/10/2019PPASS
DetailsTony Young
BLD-Energy code compliance11/1/201811/2/201811/2/2018PPASS
DetailsBrandon Shaw
Jerimy Phone #: ###-####
BLD-Framing/Rough-in10/22/201810/23/201810/23/2018PPASS
DetailsTony Young
Jermary Phone #: ###-####,, needs to justify roof venting,, ok to insulate
Plan Modification Accepted  10/8/2018 DONE
New manual j report
Routing - MECHANICAL10/8/2018 10/8/2018 PASS
DetailsTroy James
resubmitted manual j report
BLD-Wall Bracing10/2/201810/2/201810/2/2018PPASS
DetailsMike Jordan
Buster Phone #: ###-####
BLD-Foundation9/6/20189/6/20189/6/2018PPASS
DetailsTony Young
Brent Phone #: ###-####
BLD-Footing9/4/20189/5/20189/5/2018APASS
DetailsDave Hannah
late morning- Jerimy Phone #: ###-####
Issue PAID IN FULL permit  9/4/2018 DONE
Inspection Record Card- Bld  9/4/2018 DONE
OVERRIDE  8/31/2018  
Plan assigned to (J_N)8/15/20188/15/20188/31/2018 DONE
Details
08/23 sfd L1 ePlan. 2nd review 8/29 - unresolved changemarks. 1st Review complete 8/21 - clarify mechanical equipment, structural deficiencies, footing details, update energy code tables and R values
Routing - PLAN CHECK8/29/2018 8/31/2018 PASS
DetailsMichael Hanson
Reviewed by JJN. MDH
PLANS/APPL TAKEN TO FRONT DESK  8/31/2018 DONE
Details
Permit Ready to Issue  8/31/2018 DONE
met
Routing - PLAN CHECK8/21/2018 8/29/2018 FAIL
DetailsMichael Hanson
See ePlan comments from JJN - 5 of 10 changemarks resolved. MDH
Routing - PLAN CHECK8/21/2018 8/21/2018 FAIL
DetailsMichael Hanson
1st review completed  8/21/2018 FAIL
Details
Clarify mechanical equipment, structural deficiencies, footing details, update energy code year and R values, structural calculation floor plan doesn't match.
Route to Impact Fee Review8/10/20188/13/20188/13/2018 PASS
DetailsEric Bilimoria
Initial residential review of new SFD permits requested for now.
Intake Approval  8/10/2018 FAIL
Sheet do not meet size and need to be rotated
Plans ACCEPTED BY PLAN TECH  8/10/2018 DONE
Intake Approval  8/10/2018 PASS
Recd Pcfee & Taken To Pln CK  8/10/2018 DONE
Plan assigned to (M_H)8/10/2018 8/10/2018 DEFR
DetailsMichael Hanson
08/23 sfd L1 ePlan
Routing - MECHANICAL8/10/2018 8/10/2018 PASS
DetailsTroy James
Routing - PLANNING8/10/2018 8/10/2018 PASS
DetailsJeff Lowe
Routing - Addressing8/10/2018 8/10/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS8/10/2018 8/10/2018 PASS
DetailsRachael Beierle
Application received  8/9/2018 DONE
Application submitted via PDS Online on Aug 9 2018 9:20AM
Intake Approval  8/9/2018 FAIL
need manual J's and drawings must be uploaded individually
(F) Reprint permit  8/9/2018 DONE
Intake Approval  8/9/2018 FAIL
no corrections were done