BLD-Final | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | DONE |
Tony Young
|
|
|
Justin Phone #: ###-####// c of o issued
|
DOC - Permit Finaled | 2/10/2020 | 2/10/2020 | 2/10/2020 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 2/7/2020 | 2/10/2020 | 2/10/2020 | A | DEFR |
Tony Young
|
|
|
Justin Phone #: ###-####
|
BLD-Final | 1/22/2020 | 1/22/2020 | 1/22/2020 | P | FAIL |
Tony Young
|
|
|
Justin Phone #: ###-####// needs blower door test results, hand rail per code.. fire caulking
|
PubWorks Occupancy Approval | 1/21/2020 | 1/21/2020 | 1/21/2020 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s design professional indicating that the final grading and drainage is acceptable has been received by Public Works. Final occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Aging Inspection | 9/5/2019 | 9/5/2019 | 9/6/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Aging Inspection | 9/4/2019 | 9/4/2019 | 9/6/2019 | | PEND |
Tony Young
|
|
|
|
BLD-Wall Bracing | 4/23/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Jim Sly
|
|
|
shear // Justin Phone #: ###-####
|
BLD-Energy code compliance | 4/23/2019 | 4/23/2019 | 4/23/2019 | P | PASS |
Jim Sly
|
|
|
Justin Phone #: ###-####
|
BLD-Framing/Rough-in | 4/18/2019 | 4/18/2019 | 4/18/2019 | P | FAIL |
Brandon Shaw
|
|
|
See previous entry, Wall Brace...
|
BLD-Wall Bracing | 4/18/2019 | 4/18/2019 | 4/18/2019 | P | FAIL |
Brandon Shaw
|
|
|
Provide revised Engineering for wall bracing- windows and walls added/deleted, not as per plans... Hold downs to be as per plans... Interior WSP to be as per plans... Provide revised plans for as built- Master bath, Fireplace, upstairs bedrooms and baths not as per plans...
|
BLD-Wall Bracing | 4/9/2019 | 4/9/2019 | 4/9/2019 | P | FAIL |
Tony Young
|
|
|
Justin Phone #: ###-####,, needs nailed off per plan
|
Override - Parcel Holds | 4/9/2019 | 1/1/1900 | 4/9/2019 | | |
|
|
|
Shear wall inspection
|
BLD-Foundation | 1/3/2019 | 1/3/2019 | 1/3/2019 | P | PART |
Tony Young
|
|
|
Gibert Phone #: ###-####
|
BLD-Footing | 12/21/2018 | 12/21/2018 | 12/21/2018 | P | PART |
Tony Young
|
|
|
Giber Phone #: ###-####,, work in progress,, new engineering coming,, verified through engineer
|
PubWorks Subgrade Approval | 11/27/2018 | 11/27/2018 | 11/27/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Foundation | 10/15/2018 | 10/16/2018 | 10/16/2018 | A | PART |
Tony Young
|
|
|
wall // Sergio Phone #: ###-####,, work in progress,, ok
|
Fees Due Hold | 9/18/2018 | | 10/15/2018 | | DONE |
Brittany Hill
|
|
|
|
(F) Reprint permit | | | 10/2/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 9/17/2018 | | |
|
|
|
|
Telephone call | | | 9/17/2018 | | DONE |
|
|
|
called Kristine to let know permit is ready and how much is owed
|
Issue & PRINT to be Invoiced | | | 9/17/2018 | | DONE |
|
|
|
Kristine came in to pay but the checks were over the amount that is due and take 2 weeks to be redone-Rita ok'd permits to be issued so footing/foundation inspections can be done. No other inspections can be done until the new checks have been recieved
|
Case Summary (BLD) | | | 9/17/2018 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 9/17/2018 | | 9/17/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
Prior to obtaining a final for the permit, the roof storm drainage system must be inspected by Public Works. Call Melissa Jannusch at ###-####.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - PUBLIC WORKS | 9/17/2018 | | 9/17/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing - PLANNING | 9/17/2018 | | 9/17/2018 | | PASS |
David Moser
|
|
|
|
Case Summary (BLD) | | | 9/17/2018 | | DONE |
Michael Hanson
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/17/2018 | | DONE |
Michael Hanson
|
|
|
|
Inspection Record Card- Bld | | | 9/17/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/17/2018 | | DONE |
|
|
|
met
|
Plan assigned to (M_H) | 8/9/2018 | | 9/17/2018 | | DONE |
Michael Hanson
|
|
|
08/28 sfd L2 Paper. 1st review completed - Energy, WUI, Structural corrections required. MDH
|
Routing - PLAN CHECK | 8/30/2018 | | 9/17/2018 | | PASS |
Michael Hanson
|
|
|
|
Plan resubmittals received | | | 9/6/2018 | | DONE |
|
|
|
Received two copies structural calcs and full size plan sheets A1.0, A2.0, A2.1, A3.0, A3.1, A5.0, A7.0, A8.0, 1.0 Grading, 2.0 Erosion; taken to Michael Hanson
|
Routing - FIRE | 8/30/2018 | 8/30/2018 | 8/30/2018 | | PASS |
Erika Akin
|
|
|
Attached revised comments to case
|
1st review completed | | | 8/30/2018 | | FAIL |
Michael Hanson
|
|
|
Energy, WUI, Structural corrections required. MDH
|
Routing - PLAN CHECK | | | 8/30/2018 | | FAIL |
Michael Hanson
|
|
|
Energy, WUI, Structural corrections required. MDH
|
Routing - FIRE | 8/17/2018 | 8/9/2018 | 8/24/2018 | | FAIL |
Erika Akin
|
|
|
Attached comments to case and plans
|
Plan resubmittals received | | | 8/20/2018 | | DONE |
Christina Prado
|
|
|
Received two sets revised structural calculations; stamped and taken to M_H for review
|
Routing - Erosion and Sediment | 8/17/2018 | | 8/17/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Certified RP & PD. Site preparation inspection is REQUIRED.
|
Routing - MECHANICAL | | | 8/17/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/16/2018 | | 8/16/2018 | | PASS |
David Moser
|
|
|
CFH18-00073
|
Routing - PUBLIC WORKS | 8/9/2018 | | 8/16/2018 | | FAIL |
Rachael Beierle
|
|
|
SEE HILLSIDE
|
Routing PW Grading-Hillside | 8/10/2018 | | 8/16/2018 | | FAIL |
Melissa Jannusch
|
|
|
Hi Kristine,
Before I can pass the hillside grading review for BLD18-02892 for 5025 N Corralero ln, I will need the following:
1. Please provide retaining wall calculations for all walls greater than four feet (measured from bottom of footing to top of wall) or greater than two feet that is containing a surcharge (slope or structure behind the wall). Both walls for this project will require engineering.
2. Provide the site suitability letter from MTI dated July 17, 2018
Please provide two copies of the documents to the PDS front counter as resubmittals for the project.
Feel free to give me a call if you have questions.
Best,
Melissa
|
Route to Impact Fee Review | 8/9/2018 | 8/12/2018 | 8/10/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing PW Sewer Rating | 8/10/2018 | | 8/10/2018 | | PASS |
Rachael Beierle
|
|
|
|
Routing - Addressing | 8/9/2018 | | 8/10/2018 | | PASS |
Doug Chausow
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/9/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/9/2018 | | PASS |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/9/2018 | | DONE |
|
|
|
|
Application received | | 8/9/2018 | | | |
|
|
|
|