Letter of compliance/Occupancy | | | 4/9/2020 | | DONE |
|
|
|
|
BLD-Final | 4/8/2020 | 4/8/2020 | 4/8/2020 | P | PASS |
Brandon Shaw
|
|
|
Justin **cleared** Phone #: ###-####
|
DOC - Permit Finaled | 4/8/2020 | 4/8/2020 | 4/8/2020 | P | PASS |
Brandon Shaw
|
|
|
|
PubWorks Occupancy Approval | 4/3/2020 | 4/3/2020 | 4/3/2020 | | DONE |
Melissa Jannusch
|
|
|
A bond for the sites final grading and re-vegetation has been received by Public Works. Occupancy may be approved by the building department. Melissa Jannusch ###-####.
|
BLD-Final | 3/27/2020 | 3/27/2020 | 3/27/2020 | P | PART |
Jim Storey
|
|
|
sean Phone #: ###-#### bld insp. ok for occupance/ bond app. in works
|
BLD-Conference | 3/17/2020 | 3/18/2020 | 3/18/2020 | A | PASS |
Jim Storey
|
|
|
Justin Phone #: ###-####
|
BLD-Framing/Rough-in | 10/3/2019 | 10/4/2019 | 10/4/2019 | A | PASS |
Brandon Shaw
|
|
|
Garage only // Justin Phone #: ###-####
|
BLD-Energy code compliance | 7/22/2019 | 7/23/2019 | 7/23/2019 | A | PASS |
Brandon Shaw
|
|
|
Justin Phone #: ###-####
|
BLD-Framing/Rough-in | 6/27/2019 | 6/28/2019 | 6/28/2019 | A | PART |
Tony Young
|
|
|
house only- Justin Phone #: ###-####,, fire block with rock wool ok,, verify at energy inspection,, ok to insulate
|
BLD-Framing/Rough-in | 6/11/2019 | 6/12/2019 | 6/12/2019 | A | PART |
Tony Young
|
|
|
Justin Cafferty - Partial framing inspection Phone #: ###-####,,, soffits ok to cover
|
BLD-Conference | 6/4/2019 | 6/5/2019 | 6/5/2019 | A | PART |
Tony Young
|
|
|
Justin Phone #: ###-####,, ?s on fireplace,, measure from firebox brick
|
BLD-Energy code compliance | 5/9/2019 | 5/10/2019 | 5/10/2019 | A | PART |
Tony Young
|
|
|
Partial energy on soffits - Sean ###-####,, soffits with living above insulation ok,, spray foam,, ok to cover with rated material
|
BLD-Framing/Rough-in | 5/3/2019 | 5/7/2019 | 5/7/2019 | A | PART |
Dave Hannah
|
|
|
Justin-partial on lower soffits to cover Phone #: ###-#### ok all but for lagger needs to have lags screws added
|
Routing - MECHANICAL | 3/28/2019 | | 3/28/2019 | | PASS |
Troy James
|
|
|
Manual j report
|
BLD-Wall Bracing | 3/18/2019 | 3/19/2019 | 3/19/2019 | A | PASS |
Tony Young
|
|
|
shear // justin Phone #: ###-####,, mostly existing and moment frame,, per Dean Briggs engineer
|
Issue PAID IN FULL permit | | | 3/8/2019 | | DONE |
|
|
|
|
OVERRIDE | | | 3/7/2019 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 3/4/2019 | 3/4/2019 | 3/7/2019 | | PASS |
Josh Bogle
|
|
|
|
Telephone call | | | 3/7/2019 | | DONE |
|
|
|
spoke with sean informing him that this plan mod is ready and informed him that there are still PW fees due as well.
|
Routing - PLAN CHECK | 3/7/2019 | | 3/7/2019 | | PASS |
Josh Bogle
|
|
|
stair engineering provided - calcs & plans - 1/2hr PR fee
|
Case Summary (BLD) | | | 3/7/2019 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 3/7/2019 | | DONE |
|
|
|
PLAN MOD
|
CHANGE STATUS TO (ISS) | | | 3/4/2019 | | DONE |
|
|
|
as per JAB-need engineering for the stairs-change status to keep the project going until they bring it in
|
Plan Modification Accepted | | | 3/4/2019 | | DONE |
|
|
|
deferred submittalson the stairs-went and got JAB
|
PubWorks Subgrade Approval | 12/18/2018 | 12/18/2018 | 12/18/2018 | | DONE |
Melissa Jannusch
|
|
|
FROST WALLS AND COLUMN FOOTINGS. A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
BLD-Footing | 12/12/2018 | 12/12/2018 | 12/12/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress... Frost protection is required...
|
PubWorks Subgrade Approval | 12/11/2018 | 12/11/2018 | 12/11/2018 | | DONE |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
OVERRIDE | | | 11/30/2018 | | |
|
|
|
|
Plan assigned to (JAB) Josh | 10/25/2018 | 10/25/2018 | 11/30/2018 | | PASS |
Josh Bogle
|
|
|
plan mod
|
CHANGE STATUS TO (ISS) | | | 11/30/2018 | | DONE |
|
|
|
plan mod
|
Plan resubmittals received | | | 11/30/2018 | | DONE |
|
|
|
Two copies of sheets cover, c1.0, c2.0, a100, a101, a102, a110, a111, a112, sa112, a113, sa113, a114, a120, a121, a122, a130, a200, a201, a202, a300, a301, a600, a800, and a801. takne to josh
|
Routing - PLAN CHECK | 11/30/2018 | | 11/30/2018 | | PASS |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 11/30/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/30/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 11/30/2018 | | DONE |
|
|
|
plan mod
|
Routing - PLAN CHECK | | | 11/7/2018 | | FAIL |
Josh Bogle
|
|
|
construction documents are incomplete
|
Routing - PLANNING | 11/7/2018 | | 11/7/2018 | | PASS |
Sue Cummings
|
|
|
Site plan received O.K. now
|
Plan resubmittals received | | | 11/7/2018 | | DONE |
|
|
|
Plan Mod resubmittal-received sheet A101 and took to JAB
|
Routing - Erosion and Sediment | 11/5/2018 | | 11/6/2018 | | PASS |
Andy J. Long
|
|
|
ESC plan approved. Valid PD and RP. Site preparation inspection is required prior to significant earthwork
|
Routing - PLANNING | | | 11/5/2018 | | FAIL |
|
|
|
Need one site plan with all new construction AND lot lines showing setbacks.
|
Routing PW Grading-Hillside | 10/25/2018 | | 11/2/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
The final inspection of the site grading and drainage work shall be done by the design engineer. Written approval shall be submitted to Boise Public Works prior to the issuance of the building final.
|
Routing - Addressing | 10/25/2018 | | 10/25/2018 | | PASS |
Doug Chausow
|
|
|
|
Plan Modification Accepted | | | 10/25/2018 | | |
|
|
|
plan mod accepted to enclose basement patio and convert to living space
|
Routing Walk-In (BLD) | 8/10/2018 | 8/10/2018 | 8/10/2018 | P | DONE |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 8/10/2018 | | 8/10/2018 | | PASS |
Josh Bogle
|
|
|
|
1st review completed | | | 8/10/2018 | | DONE |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 8/10/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 8/10/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/10/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 8/10/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 8/10/2018 | | DONE |
|
|
|
|
Application received | | 8/10/2018 | | | |
|
|
|
|
Routing - PUBLIC WORKS | 10/25/2018 | | | | |
|
|
|
|