BLD-Final | 4/29/2019 | 4/30/2019 | 4/30/2019 | P | PASS |
Tony Young
|
|
|
text requesting garage code // Kerry Phone #: ###-####
|
DOC - Permit Finaled | 4/30/2019 | 4/30/2019 | 4/30/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Blower Door Test Results | 4/29/2019 | 4/29/2019 | 4/30/2019 | P | DONE |
Tony Young
|
|
|
text requesting garage code // Kerry Phone #: ###-####/// 4.4
|
BLD-Final | 4/29/2019 | 4/29/2019 | 4/29/2019 | P | PEND |
Tony Young
|
|
|
text requesting garage code // Kerry Phone #: ###-####
|
BLD-Final | 4/26/2019 | 4/29/2019 | 4/29/2019 | A | NR |
Tony Young
|
|
|
text requesting garage code // Kerry Phone #: ###-####,, needs more fire caulking,, blower door test results
|
BLD-Final | 4/17/2019 | 4/17/2019 | 4/17/2019 | P | NR |
Tony Young
|
|
|
Call for garage code // Kerry Phone #: ###-####,, c/n posted,, fire caulking, tempered glass, blower door test,, drainage to maintain on property
|
BLD-Energy code compliance | 12/13/2018 | 12/14/2018 | 12/14/2018 | A | PASS |
Tony Young
|
|
|
Kerrie Phone #: ###-####
|
BLD-Energy code compliance | 12/10/2018 | 12/12/2018 | 12/12/2018 | A | PART |
Tony Young
|
|
|
Kerry Phone #: ###-####,, seal pack ok,, needs energy code inspection after insulation
|
BLD-Framing/Rough-in | 12/10/2018 | 12/12/2018 | 12/12/2018 | A | PART |
Tony Young
|
|
|
Kerry Phone #: ###-####,, needs tempered glass by the final,, needs egress out of master bed room by final,, ok to insulate
|
BLD-Framing/Rough-in | 12/11/2018 | 12/11/2018 | 12/11/2018 | A | NR |
Tony Young
|
|
|
Kerry Phone #: ###-####,, still working,, c/n
|
BLD-Wall Bracing | 11/27/2018 | 11/28/2018 | 11/28/2018 | A | PART |
Tony Young
|
|
|
Carrie Phone #: ###-####,, exterior ok after minor fixes
|
Elevation Cert Rec'd-Midconst | | | 11/19/2018 | | DONE |
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to occupancy approval. Jason Taylor ###-####
|
BLD-Footing | 10/18/2018 | 10/18/2018 | 10/18/2018 | P | PASS |
Jim Sly
|
|
|
Derick Phone #: ###-####
|
BLD-Footing | 10/17/2018 | 10/18/2018 | 10/18/2018 | A | DEFR |
Tony Young
|
|
|
Derick Phone #: ###-####
|
Issue PAID IN FULL permit | | | 10/5/2018 | | DONE |
|
|
|
|
OVERRIDE | | | 10/3/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 8/21/2018 | 8/21/2018 | 10/3/2018 | | DONE |
Rob Patrick
|
|
|
09/07 sfd L2 ePlan: 9/11 Failed; Corrections Required
|
Routing - PLAN CHECK | 10/3/2018 | | 10/3/2018 | | PASS |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/3/2018 | | DONE |
Rob Patrick
|
|
|
|
Permit Ready to Issue | | | 10/3/2018 | | DONE |
|
|
|
|
Routing PW Flood Plain | 10/2/2018 | | 10/2/2018 | | PASS |
Jason C. Taylor
|
|
|
NOTE:
Two Elevation Certificates will be required; one prior to any vertical construction, and one based upon finished construction. These certificates will need to be reviewed and approved by Public Works staff prior to framing/occupancy approval. Jason Taylor ###-####
|
1st review completed | | | 9/11/2018 | | FAIL |
Rob Patrick
|
|
|
Corrections Required
|
Routing - PLAN CHECK | 8/21/2018 | | 9/11/2018 | | FAIL |
Rob Patrick
|
|
|
|
Route to Impact Fee Review | 8/21/2018 | 8/24/2018 | 8/22/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 8/21/2018 | | 8/21/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLANNING | 8/21/2018 | | 8/21/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 8/21/2018 | | 8/21/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/21/2018 | | 8/21/2018 | | PASS |
Morgan Webb
|
|
|
|
Routing PW Flood Plain | 8/21/2018 | | 8/21/2018 | | FAIL |
Jason C. Taylor
|
|
|
Provide elevation of Finish Slab floor on plan. Elevation is listed on Elevation Certificate. Elevation Certificate need revised -see changemarks. Jason Taylor ###-####
|
Plans ACCEPTED BY PLAN TECH | | | 8/21/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/21/2018 | | |
|
|
|
|
Intake Approval | | | 8/21/2018 | | PASS |
|
|
|
|
Intake Approval | | | 8/14/2018 | | PASS |
|
|
|
Building cross section of the whole building and an elevation certificate or a letter of map revision.
|
Application received | | | 8/13/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 13 2018 2:14PM
|