Permit Information
Permit NumberBLD18-02922
StatusFinaled
Name SCOTT MCGAVIN
Site Address 5479 W OVERLAND RD
Project NamePuentes Spanish Preschool
Customer Number 
ePlanReviewYes
Description
(PUENTES SPANISH PRESCHOOL) A relocated 1,695 s.f modular building for a daycare at Puentes Spanish Preschool with stair and ramp access. This daycare is to be used in conjunction with the existing daycare building on the adjacent parcel. Scope of work includes: engineered set, new ramp and stairs, and new accessible route to the building. NOTE: This building is not fire sprinklered. STATE TAG # 05154 A&B – August 2005. **JHB**
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Third Notice 11/3/201911/26/2019 DONE
mailed 12-2-19
Second Notice 9/30/201910/29/2019 DONE
mailed 11-1
First Notice 8/26/20199/20/2019 DONE
mailed 9-23-19
Telephone call  8/16/2019 DONE
emailed perm c of o to scottydm3@hotmail.com
Permanent Occupancy  8/16/2019 DONE
BLD-Final8/9/20198/9/20198/9/2019PPASS
DetailsTell Riley
Scott Phone #: ###-####//landing at bottom of ramp is now installed and is 5x5// final is complete//
Temporary Occupancy7/5/201910/3/20197/5/2019 DONE
DetailsCandy A. Nichols
as per Jason Blais-ext req granted from 6/24/19 for 90 days
BLD-Conference7/2/20197/2/20197/2/2019PDONE
DetailsTell Riley
Scott Phone #: ###-####//discussed 5x5 landing//will be geting it fixed//
Telephone call  7/2/2019 DONE
called Scott again about temp c of o being expired-he said he emailed Jason Blais but is calling in the final today or tomorrow
Telephone call  6/21/2019 DONE
called Scott about the temp c of o that's about to expire-he will email Jason Blais for an extension
BLD-Conference5/17/20195/24/20195/24/2019ADONE
DetailsJim Sly
Scott Phone #: ###-####
Temporary Occupancy3/26/20196/24/20193/26/2019 DONE
DetailsCandy A. Nichols
Jason Blais ok'd 90 day extension good from 3-24-19
Telephone call  3/20/2019 DONE
called Scott to let know temp c of o is about to expire-he will email Jason Blais
BLD-Conference2/21/20192/21/20192/21/2019PDONE
DetailsJim Sly
BLD-Aging Inspection2/20/20192/20/20192/21/2019 CANC
DetailsJim Sly
BLD-Final12/19/201812/24/201812/24/2018PPART
DetailsJim Sly
Scott Phone #: ###-####
OK for Temp Occ. OK for Perm Occ. when Code complying Landing installed at bottom of ADA ramp.
FIRE-Final Inspection12/21/201812/24/201812/24/2018APASS
DetailsTroy Cobbley
Life safety passed

Scott Phone #: ###-####
Temporary Occupancy12/24/20183/24/201912/24/2018 DONE
DetailsBrittany Hill
FIRE-Final Inspection12/19/201812/20/201812/20/2018AFAIL
DetailsMike Jordan
Scott Phone #: ###-####. Provide address, provide the missing exit sign at west door and provide ADA hardware at restroom.
PubWorks Occupancy Approval12/20/201812/20/201812/20/2018 DONE
DetailsTiffany Lowery
FIRE-Final Inspection12/12/201812/13/201812/13/2018AFAIL
DetailsJim Page
City approved drawings and small documents were not onsite, need city approved drawings to perform official life fire safety inspection. Performed courtesy inspection with non-stamped drawings on site, need to add emergency egress lighting per plans, install exit sign on west door as shown on drawings. Restroom door hardware on southside will not operate when locked, need to install code compliant door hardware. Round type door hardware needs to be changed to lever type door hardware. Thumbturn deadbolt on west exterior door needs to be removed and code compliant hardware needs to be installed.

Scott Phone #: ###-####
BLD-Final12/6/201812/12/201812/12/2018PNR
DetailsJim Sly
Scott Phone #: ###-####
Need Fire/Life and Public Works. Alarm signed off on alarm permit.
BLD-Conference11/29/201811/30/201811/30/2018PDONE
DetailsBrandon Shaw
Scott Phone #: ###-####
FIRE-Final Inspection11/28/201811/29/201811/29/2018PCANC
DetailsTroy Cobbley
Owner was not ready for a final yet. The project related fire alarm permit has not been scheduled for an inspection either.

call half hour before// Scott Phone #: ###-####
Print Occupancy Form  11/21/2018 DONE
BLD-Other10/3/201810/3/201810/3/2018PPASS
DetailsJim Sly
block and tie- Scott Phone #: ###-####
BLD-Foundation10/2/201810/2/201810/2/2018PFAIL
DetailsJim Sly
Call to meet // Scott Phone #: ###-####
Block and tie C/N cross type anchor can only be used in solid rock.
OVERRIDE  9/18/2018  
Issue PAID IN FULL permit  9/18/2018 DONE
Print Occupancy Form  9/18/2018 DONE
Permit Ready to Issue  9/18/2018 DONE
ALL MET
Plan assigned to (JHB)8/17/20188/17/20189/17/2018 PASS
DetailsJoe Bruce
(1st Rev Comp) - 09/06 (L2) - Puentes Pre-School
Routing - PLANNING9/17/2018 9/17/2018 PASS
DetailsDavid Moser
Routing - PLAN CHECK9/17/2018 9/17/2018 PASS
DetailsJulie Romig
PLANS/APPL TAKEN TO FRONT DESK  9/17/2018 DONE
Route to Impact Fee Review9/6/20189/9/20189/7/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - PLAN CHECK8/17/2018 9/6/2018 FAIL
DetailsJoe Bruce
1st review completed  9/6/2018 FAIL
DetailsJoe Bruce
Routing - FIRE8/21/20188/21/20189/5/2018 PASS
DetailsErika Akin
Attached comments to case
Routing PW Drainage8/22/2018 8/30/2018 PASS
DetailsBrian Murphy
Routing PW Solid Waste8/22/2018 8/22/2018 PASS
DetailsEvan Carpenter
Routing PW Sewer Design8/22/2018 8/22/2018 PASS
DetailsDeAnn Brown
Routing PW Street Lights8/22/2018 8/22/2018 PASS
DetailsTom Marshall
Routing - Design Review8/21/2018 8/22/2018 PASS
DetailsKatelyn Menuge
DRH18-00262 Okay pending Idaho Power approval.
Routing - PLANNING8/21/2018 8/22/2018 FAIL
DetailsDavid Moser
CUP18-00005 - Need a letter from Idaho Power due to their underground power line which is next to the building.
Routing - Addressing8/21/2018 8/22/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS8/21/2018 8/22/2018 PASS
DetailsRachael Beierle
CONTACT MIKE SHEPPARD FOR SERVICE INFO
Routing - Erosion and Sediment8/21/2018 8/21/2018 PASS
DetailsMichael Zawacki
RP needed prior to ground disturbances.
Plans ACCEPTED BY PLAN TECH  8/21/2018 DONE
Recd Pcfee & Taken To Pln CK  8/21/2018 DONE
Intake Approval  8/17/2018 PASS
Application received  8/13/2018 DONE
Application submitted via PDS Online on Aug 13 2018 2:22PM