BLD-Final | 3/25/2019 | 4/2/2019 | 4/2/2019 | P | PASS |
Tony Young
|
|
|
We need a final on the deck project we built. The landscaping is not finished yet but that is a different contractor. Hence the steps from the east side are not complete because they are part of the landscape. Please call me with any questions. The plans and engineering sign off for the handrail are in the tackle box marked "plans". thanks Phone #: ###-#### Inspection requested via web by Michael Kuhn
|
DOC - Permit Finaled | 4/2/2019 | 4/2/2019 | 4/2/2019 | P | PASS |
Tony Young
|
|
|
|
BLD-Final | 3/23/2019 | 3/25/2019 | 3/25/2019 | A | PART |
Tony Young
|
|
|
We need a final on the deck project we built. The landscaping is not finished yet but that is a different contractor. Hence the steps from the east side are not complete because they are part of the landscape. Please call me with any questions. The plans and engineering sign off for the handrail are in the tackle box marked "plans". thanks Phone #: ###-#### Inspection requested via web by Michael Kuhn,, need to close off future step area on the north/east corner,, then ok
|
BLD-Framing/Rough-in | 1/28/2019 | 1/29/2019 | 1/29/2019 | A | PASS |
Brandon Shaw
|
|
|
needing an engineering connection inspection. Phone #: ###-#### Inspection requested via web by Michael Kuhn
|
BLD-Footing | 12/3/2018 | 12/5/2018 | 12/5/2018 | P | CANC |
Tony Young
|
|
|
Give me a call if you have any questions. Thanks Michael Phone #: ###-#### Inspection requested via web by Michael Kuhn
|
PubWorks Subgrade Approval | 12/3/2018 | 12/3/2018 | 12/3/2018 | | DONE |
Melissa Jannusch
|
|
|
DECK FOOTING A letter from the applicant’s geotechnical engineer indicating that the deck footing/column subgrade is acceptable has been received by Public Works. Footing inspection may be scheduled with the Building Department. Melissa Jannusch ###-####.
|
Routing Walk-In (BLD) | 11/9/2018 | 11/9/2018 | 11/9/2018 | P | DONE |
Josh Bogle
|
|
|
|
Plan assigned to (JAB) Josh | 10/8/2018 | 10/8/2018 | 11/9/2018 | | PASS |
Josh Bogle
|
|
|
10/09 deck, paper - 1st done
|
Routing - PLAN CHECK | 11/9/2018 | | 11/9/2018 | | PASS |
Josh Bogle
|
|
|
|
Inspection Record Card- Bld | | | 11/9/2018 | | DONE |
Josh Bogle
|
|
|
|
Case Summary (BLD) | | | 11/9/2018 | | DONE |
Josh Bogle
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 11/9/2018 | | DONE |
Josh Bogle
|
|
|
|
Permit Ready to Issue | | | 11/9/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 11/9/2018 | | DONE |
|
|
|
|
Routing PW Grading-Hillside | 10/8/2018 | | 10/8/2018 | | PASS |
Melissa Jannusch
|
|
|
A letter from the applicant’s geotechnical engineer indicating that the footing/column subgrade is acceptable must be approved by Public Works prior to scheduling a footing inspection. Please e-mail the stamped inspection approval letter to mjannusch@cityofboise.org and allow 24 hours for subgrade approval processing. Call Melissa Jannusch at ###-#### with questions.
|
Routing - PLAN CHECK | 10/8/2018 | | 10/8/2018 | | FAIL |
Josh Bogle
|
|
|
missing details - see e-mail 10.8.18
|
Routing Walk-In (BLD) | 10/3/2018 | 10/3/2018 | 10/3/2018 | A | PASS |
Michael Hanson
|
|
|
|
Routing Walk-In (Zoning) | 8/15/2018 | 8/15/2018 | 8/15/2018 | A | PASS |
Jeff Lowe
|
|
|
|
Routing Walk-In (BLD) | 8/15/2018 | 8/15/2018 | 8/15/2018 | A | FAIL |
Josh Bogle
|
|
|
|
Routing - PLAN CHECK | 8/15/2018 | | 8/15/2018 | | FAIL |
Josh Bogle
|
|
|
deck - needs Hillside/WUI details
|
1st review completed | | | 8/15/2018 | | FAIL |
Josh Bogle
|
|
|
|
Application received | | 8/15/2018 | | | |
|
|
|
|