BLD-Final | 1/18/2019 | 1/18/2019 | 1/18/2019 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Rogers
|
DOC - Permit Finaled | 1/18/2019 | 1/18/2019 | 1/18/2019 | P | PASS |
Jim Sly
|
|
|
|
BLD-Final | 1/16/2019 | 1/17/2019 | 1/17/2019 | P | NR |
Jim Storey
|
|
|
Clint Phone #: ###-#### need mech insp.
|
BLD-Final | 1/15/2019 | 1/16/2019 | 1/16/2019 | A | NR |
Jim Sly
|
|
|
Clint Phone #: ###-#### Need Mech Final.
|
BLD-Energy code compliance | 10/25/2018 | 10/29/2018 | 10/29/2018 | P | PASS |
Jim Sly
|
|
|
Phone #: ###-#### Inspection requested via web by Clint Rogers
|
BLD-Framing/Rough-in | 10/25/2018 | 10/26/2018 | 10/26/2018 | A | PASS |
Brandon Shaw
|
|
|
Provide straps at header over nook... See red paint...
OK to insulate
|
BLD-Wall Bracing | 9/27/2018 | 9/27/2018 | 9/27/2018 | P | PASS |
Jim Sly
|
|
|
John Phone #: ###-####
|
BLD-Footing | 8/21/2018 | 8/22/2018 | 8/22/2018 | A | PASS |
Jim Sly
|
|
|
pour at 10 // Scott Phone #: ###-####
|
OVERRIDE | | | 8/20/2018 | | |
|
|
|
|
Plan assigned to (RDP) | 8/17/2018 | 8/17/2018 | 8/20/2018 | | DONE |
Rob Patrick
|
|
|
8/15 Failed for Manual J
|
Routing - MECHANICAL | 8/20/2018 | | 8/20/2018 | | PASS |
Troy James
|
|
|
|
Inspection Record Card- Bld | | | 8/20/2018 | | DONE |
Rob Patrick
|
|
|
|
Case Summary (BLD) | | | 8/20/2018 | | DONE |
Rob Patrick
|
|
|
|
PLANS/APPL TAKEN TO FRONT DESK | | | 8/20/2018 | | DONE |
Rob Patrick
|
|
|
|
Inspection Record Card- Bld | | | 8/20/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 8/20/2018 | | DONE |
|
|
|
Need- met
RP
|
Telephone call | | | 8/20/2018 | | DONE |
|
|
|
Spoke with Clint to inform him the permit is ready, got RP name and what fees are due.
|
Issue PAID IN FULL permit | | | 8/20/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/15/2018 | | 8/20/2018 | | PASS |
Rob Patrick
|
|
|
|
Routing - MECHANICAL | 8/15/2018 | | 8/16/2018 | | FAIL |
Troy James
|
|
|
emailed corrections to heating supply
|
Routing Walk-In (BLD) | 8/15/2018 | 8/15/2018 | 8/15/2018 | P | PASS |
Josh Bogle
|
|
|
took in as a level 2 pending Mech review
|
Routing Walk-In (Zoning) | 8/15/2018 | 8/15/2018 | 8/15/2018 | P | DONE |
Tom R. Laws
|
|
|
|
Routing Walk-In (Zoning) | 8/15/2018 | 8/15/2018 | 8/15/2018 | P | PASS |
Tom R. Laws
|
|
|
|
Routing Walk-In (BLD) | 8/15/2018 | 8/15/2018 | 8/15/2018 | P | FAIL |
Rob Patrick
|
|
|
No Manual J for new furnace.
|
1st review completed | | | 8/15/2018 | | FAIL |
Rob Patrick
|
|
|
No Manual J for new furnace.
|
Application received | | 8/15/2018 | | | |
|
|
|
|