Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD18-02968
StatusIssued
Name CASCADE ENTERPRISES INC
Site Address 11818 W JOPLIN RD
Project NameWB. Sewer hydroclorate tank
Customer Number 
ePlanReviewYes
Description
(CITY OF BOISE SEWER/JOPLIN) (THE TANK ANCHORS ARE A DEFERRED SUBMITAL. THE ANCHORAGE ENGINEERING IS REQUIRED TO BE SUBMITTED FOR REVIEW PRIOR TO ANY ANCHORAGE INSTALLATION AND PRIOR TO THE INSTALLATION OF THE TANK) Pernit for the installation of a new hydroclorate storage tank with work to include the removal of the existing tank and the construction of a new foundation, containment area and the installation of the new tank with realted mechanical systems per the approved plans. CDM
Contact Information
See Activities list for contact information
Show Inspection Activities Only
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Aging Inspection11/1/201911/1/201911/1/2019 CANC
DetailsTell Riley
BLD-Final6/18/20196/20/20196/20/2019APASS
DetailsTell Riley
Joe Phone #: ###-####//final is complete per approved plans//MTI summary report reviewed onsite//
BLD-Footing11/13/201811/14/201811/14/2018APART
DetailsJim Sly
Call Joe @ ###-#### for site access and Entry Point Phone #: ###-#### Inspection requested via web by Damian Hendricks
OK pending MTI special inspections, tests, and approvals.
Issue PAID IN FULL permit  11/7/2018 DONE
Inspection Record Card- Bld  11/7/2018 DONE
OVERRIDE  10/25/2018  
Plan assigned to (CDM)8/22/20188/22/201810/25/2018 PASS
DetailsCarl D Madsen
09/28 Boise Sewer/Joplin New
Routing - PLAN CHECK10/18/2018 10/25/2018 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL10/18/2018 10/25/2018 PASS
DetailsCarl D Madsen
Stapley. Deferred submittal on the tank anchors.
PLANS/APPL TAKEN TO FRONT DESK  10/25/2018 DONE
Permit Ready to Issue  10/25/2018 DONE
NEED
GC FORM
REVISED VALUE
Routing Off Site - STRUCTURAL10/8/2018 10/15/2018 FAIL
DetailsCarl D Madsen
Stapley
Routing - PLAN CHECK10/8/2018 10/10/2018 PASS
DetailsCarl D Madsen
Route to Impact Fee Review10/8/201810/11/201810/9/2018 PASS
DetailsEric Bilimoria
Review requested for Commercial Permit
Routing - FIRE8/22/20188/22/201810/5/2018 PASS
DetailsErika Akin
Attached comments to case
1st review completed  10/5/2018 DONE
Routing - PLAN CHECK8/22/2018 8/30/2018 PASS
DetailsCarl D Madsen
Routing Off Site - STRUCTURAL8/22/2018 8/30/2018 FAIL
DetailsCarl D Madsen
Print Statement  8/23/2018 DONE
Print Statement  8/23/2018 DONE
Routing - MECHANICAL8/22/2018 8/23/2018 PASS
DetailsTroy James
Process piping
Routing - PLANNING8/23/2018 8/23/2018 PASS
DetailsSusan Riggs
Routing - Addressing8/22/2018 8/23/2018 PASS
DetailsDoug Chausow
Routing - PUBLIC WORKS8/22/2018 8/22/2018 PASS
DetailsRachael Beierle
Routing - Erosion and Sediment8/22/2018 8/22/2018 PASS
DetailsAndy J. Long
ESC plan waiver approved. Certified RP designated.
Plans ACCEPTED BY PLAN TECH  8/22/2018 DONE
Routing - PLUMBING8/22/2018 8/22/2018 PASS
DetailsDaryl Spivey
No plumbing review required.
Intake Approval  8/20/2018 PASS
Intake Approval  8/16/2018 FAIL
DetailsJavier Guzman
Provide and upload the following:
• On the uploaded Form #310 – Statement of Special Inspections the form must be stamped, signed and dated by the Idaho design engineer
• On the uploaded Form #310 – Statement of Special Inspections the form must be signed by the design professional in charge or property owner
• Provide page number on the specs book that list the stated deferred submittal items
Application received  8/15/2018 DONE
Application submitted via PDS Online on Aug 15 2018 1:16PM