BLD-Final | 1/30/2019 | 1/30/2019 | 1/30/2019 | P | PASS |
Brandon Shaw
|
|
|
Phone #: 2088592629 >> Inspection requested via mobile web by Ben Evans
|
DOC - Permit Finaled | 1/30/2019 | 1/30/2019 | 1/30/2019 | P | PASS |
Brandon Shaw
|
|
|
|
BLD-Blower Door Test Results | 1/30/2019 | 1/30/2019 | 1/30/2019 | P | DONE |
Brandon Shaw
|
|
|
ACH50- 2.9
|
BLD-Final | 1/30/2019 | 1/31/2019 | 1/30/2019 | A | CANC |
Brandon Shaw
|
|
|
Phone #: 2088592629 >> Inspection requested via mobile web by Ben Evans
|
BLD-Wall cover | 11/12/2018 | 11/13/2018 | 11/13/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: 2088592629 >> Inspection requested via mobile web by Ben Evans
|
BLD-Framing/Rough-in | 11/7/2018 | 11/8/2018 | 11/8/2018 | A | PASS |
Brandon Shaw
|
|
|
OK to insulate
|
BLD-Wall Bracing | 10/19/2018 | 10/22/2018 | 10/22/2018 | A | PART |
Jim Sly
|
|
|
Phone #: 2088592629 >> Inspection requested via mobile web by Ben Evans all OK except.....missing HD at W wall Master Closet. marked on floor.
|
BLD-Wall Bracing | 10/18/2018 | 10/19/2018 | 10/19/2018 | P | NR |
Tony Young
|
|
|
Phone #: 2088592629 >> Inspection requested via mobile web by Ben Evans,, not ready
|
BLD-Footing | 10/5/2018 | 10/5/2018 | 10/5/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 10/5/2018 | 10/5/2018 | 10/5/2018 | A | NR |
Dave Hannah
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Footing | 10/3/2018 | 10/4/2018 | 10/4/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Foundation | 9/13/2018 | 9/13/2018 | 9/13/2018 | A | PASS |
Brandon Shaw
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
BLD-Conference | 9/13/2018 | 9/13/2018 | 9/13/2018 | A | CANC |
Brandon Shaw
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron Inspection cancelled via mobile web on Thursday, September 13, 2018.
|
BLD-Foundation | 9/11/2018 | 9/12/2018 | 9/12/2018 | P | PASS |
Brandon Shaw
|
|
|
Work in progress
|
BLD-Footing | 9/11/2018 | 9/11/2018 | 9/11/2018 | P | PASS |
Brandon Shaw
|
|
|
Phone #: 2086971241 >> Inspection requested via mobile web by Heron
|
OVERRIDE | | | 9/7/2018 | | |
|
|
|
|
Plan assigned to (J_N) | 8/23/2018 | 8/23/2018 | 9/7/2018 | | DONE |
|
|
|
08/29 sfd L1 ePlan. 1st review complete 8/29, show girder locations, patio footing detail, clarify energy requirements, garage beam.
|
Issue PAID IN FULL permit | | | 9/7/2018 | | DONE |
|
|
|
|
Inspection Record Card- Bld | | | 9/7/2018 | | DONE |
|
|
|
|
Routing - PLAN CHECK | 8/29/2018 | | 9/7/2018 | | PASS |
Michael Hanson
|
|
|
Per JJN review and phone and email correspondence with applicant. MDH
|
PLANS/APPL TAKEN TO FRONT DESK | | | 9/7/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 9/7/2018 | | DONE |
|
|
|
|
1st review completed | | | 8/29/2018 | | FAIL |
|
|
|
Show girder locations, patio footing details, clarify energy requirements, garage beam
|
Routing - PLAN CHECK | 8/16/2018 | | 8/29/2018 | | FAIL |
Michael Hanson
|
|
|
See eplan comments from JJN. MDH
|
Routing - MECHANICAL | 8/23/2018 | | 8/23/2018 | | PASS |
Troy James
|
|
|
|
Route to Impact Fee Review | 8/16/2018 | 8/19/2018 | 8/17/2018 | | PASS |
Eric Bilimoria
|
|
|
Initial residential review of new SFD permits requested for now.
|
Routing - MECHANICAL | 8/16/2018 | | 8/17/2018 | | FAIL |
Troy James
|
|
|
Emailed corrections to ultimate htg
|
Routing - PLANNING | 8/16/2018 | | 8/16/2018 | | PASS |
Sue Cummings
|
|
|
|
Routing - Addressing | 8/16/2018 | | 8/16/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/16/2018 | | 8/16/2018 | | PASS |
Rachael Beierle
|
|
|
|
Plans ACCEPTED BY PLAN TECH | | | 8/16/2018 | | DONE |
|
|
|
|
Recd Pcfee & Taken To Pln CK | | | 8/16/2018 | | DONE |
|
|
|
|
Intake Approval | | | 8/16/2018 | | PASS |
|
|
|
|
Plan assigned to (M_H) | 8/16/2018 | | 8/16/2018 | | DEFR |
Michael Hanson
|
|
|
08/29 sfd L1 ePlan
|
Application received | | | 8/15/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 15 2018 2:08PM
|
Intake Approval | | | 8/15/2018 | | FAIL |
|
|
|
MISSING
RES
|