BLD-Aging Inspection | 11/29/2019 | 11/29/2019 | 12/2/2019 | | PART |
Jim Storey
|
|
|
not open yet pending sign offs
|
BLD-Final | 7/18/2019 | 7/18/2019 | 7/18/2019 | P | PART |
Jim Storey
|
|
|
tAG Phone #: ###-####
|
BLD-Framing/Rough-in | 7/18/2019 | 7/18/2019 | 7/18/2019 | P | PASS |
Jim Storey
|
|
|
tAG Phone #: ###-#### rated const ok to cover
|
BLD-Framing/Rough-in | 12/27/2018 | 12/28/2018 | 12/28/2018 | A | PASS |
Jim Storey
|
|
|
Tad Phone #: ###-#### framing ok pending trades
|
BLD-Framing/Rough-in | 12/10/2018 | 12/11/2018 | 12/11/2018 | A | PASS |
Mike Jordan
|
|
|
Tad-Partial Phone #: ###-####. fir outs only ok.
|
BLD-Conference | 11/8/2018 | 11/9/2018 | 11/9/2018 | A | FAIL |
Jim Storey
|
|
|
Tad Phone #: ###-#### not a 2hr wall east // have arch field review and resub mit to planreview as to how to proceed to not require fire spk.
|
Print Occupancy Form | | | 10/23/2018 | | DONE |
|
|
|
|
Issue PAID IN FULL permit | | | 10/23/2018 | | DONE |
|
|
|
|
Plan assigned to (JHB) | 8/29/2018 | 8/29/2018 | 10/12/2018 | | PASS |
Joe Bruce
|
|
|
(2nd Rev Comp) 09/20 (L3) - Critty's Tap Room
|
PLANS/APPL TAKEN TO FRONT DESK | | | 10/12/2018 | | DONE |
|
|
|
|
Permit Ready to Issue | | | 10/12/2018 | | DONE |
|
|
|
ALL MET
NEED
ACHD-met
GC FORM
REVISED VALUE
|
Routing - MECHANICAL | 10/11/2018 | | 10/12/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLAN CHECK | 10/11/2018 | | 10/11/2018 | | PASS |
Joe Bruce
|
|
|
|
Plan resubmittals requested | | | 10/11/2018 | | DONE |
Joe Bruce
|
|
|
|
Plan resubmittals received | | | 10/11/2018 | | DONE |
Joe Bruce
|
|
|
|
Routing - PUBLIC WORKS | 10/1/2018 | | 10/11/2018 | | PASS |
Morgan Webb
|
|
|
Added additional restroom **JHB**
|
Routing - PLAN CHECK | 10/1/2018 | | 10/10/2018 | | FAIL |
Joe Bruce
|
|
|
Provide UL listed assembly and form #310 for intumescent coating. **JHB**
|
Routing - MECHANICAL | 10/1/2018 | | 10/4/2018 | | FAIL |
Troy James
|
|
|
Added additional restroom **JHB**
|
Routing - PLUMBING | 10/1/2018 | | 10/2/2018 | | PASS |
Dan Ediger
|
|
|
Added additional restroom **JHB**
Per plans, red line note and ISPC
|
Routing Off Site - C.D.H | 9/10/2018 | | 10/1/2018 | | PASS |
Joe Bruce
|
|
|
10/01 - CDHD: No Review Required. Forms received from application on 9/10. **JHB**
|
1st review completed | | | 10/1/2018 | | FAIL |
Joe Bruce
|
|
|
|
Plan resubmittals received | | | 10/1/2018 | | DONE |
Joe Bruce
|
|
|
|
Route to Impact Fee Review | 9/26/2018 | 9/29/2018 | 9/28/2018 | | PASS |
Eric Bilimoria
|
|
|
Review requested for Commercial Permit
|
Routing - FIRE | 8/29/2018 | 8/29/2018 | 9/25/2018 | | PASS |
Erika Akin
|
|
|
Attached comments to case
|
1st review completed | | | 9/25/2018 | | FAIL |
Joe Bruce
|
|
|
Waiting on CDHD approval. Forms and application for CDHD received & routed on 9/10 after receiving from applicant. **JHB**
|
Plan resubmittals requested | | | 9/25/2018 | | DONE |
Joe Bruce
|
|
|
Failed 1st review but still waiting on CDHD response. **JHB**
|
Routing - PLAN CHECK | 8/29/2018 | | 9/21/2018 | | FAIL |
Joe Bruce
|
|
|
Emailed applicant Plan Review Report and left a voicemail on 09/21.
|
Routing PW Environmental | 8/30/2018 | | 9/6/2018 | | PASS |
Rick Christenson
|
|
|
|
Routing - MECHANICAL | 8/29/2018 | | 9/4/2018 | | PASS |
Troy James
|
|
|
|
Routing - PLUMBING | 8/29/2018 | | 8/30/2018 | | PASS |
Bill VanDegrift
|
|
|
per plans and ISPC
|
Routing - PLANNING | 8/29/2018 | | 8/30/2018 | | PASS |
Leon Letson
|
|
|
|
Routing - Addressing | 8/29/2018 | | 8/30/2018 | | PASS |
Doug Chausow
|
|
|
|
Routing - PUBLIC WORKS | 8/29/2018 | | 8/30/2018 | | PASS |
Rachael Beierle
|
|
|
emailed owner and Arch 08-29-2018 for info
The application states this portion of the building was last utilized as a bar/tavern. I show most recently this space was a salon of some sort. I can say the front portion of the building once served food and drink but the rear portion has no such permits that I can find.
So what I need is:
Demo Drawing or current (existing) floor plan to confirm the latest occupancy and provide any credits available to your new sewer capacity permit.
Count of how many beer taps are going to be installed.
Will this space have an ice machine, mop sink.
|
Plan Reviewer's activity | | | 8/28/2018 | | DONE |
Javier Guzman
|
|
|
Email sent to applicant
Matt,
This project has been moved and will be reviewed as a Major Tenant improvement due to the change of use.
Please make sure that you reach out to ACHD for review on this change of use/occupancy. If additional fees are due they will need to be paid or paid when the permit is issued. If no fees are due, please submit the documentation from ACDH as such.
|
Intake Approval | | | 8/24/2018 | | PASS |
|
|
|
|
Application received | | | 8/15/2018 | | DONE |
|
|
|
Application submitted via PDS Online on Aug 15 2018 2:09PM
|